MONTHYEARML0209302122002-03-28028 March 2002 Proposed Technical Specifications Changes & Exemption Request for Use of Framatome Anp Advanced Mark-BW Fuel Project stage: Request ML0213503742002-05-13013 May 2002 Request for Withholding Information from Public Disclosure by Letter Dated 03/28/2002 Project stage: Withholding Request Acceptance ML0220500122002-07-23023 July 2002 Ltr, Proposed Technical Specification Changes and Exemption Request Regarding Use of Framatome and Advanced Mark-BW Fuel Project stage: Other ML0222702432002-08-0202 August 2002 Small Break LOCA Evaluation in Support of Proposed Technical Specifications Changes & Exemption Request Use of Framatome Anp Advanced Mark-BW Fuel Project stage: Other ML0224601642002-08-16016 August 2002 Large Break LOCA Analysis in Support of Proposed Technical Specifications Changes & Exemption Request to Use Framatome Anp Advanced Mark-BW Fuel Project stage: Other ML0233303622002-11-15015 November 2002 Revised Loca Analysis Schedule in Support of Proposed Technical Specifications Changes and Exemption Request to Use Framatome Anp Advanced Mark-BW Fuel Project stage: Other ML0302701122003-01-24024 January 2003 Fax, Request for Additional Information Framatome Fuel Transition Project stage: RAI ML0308003902003-03-21021 March 2003 Request for Additional Information on Small-break LOCA Evaluation in Support of Proposed Technical Specifications Changes and Exemption Request to Use Framatome Anp Advanced Mark-BW Fuel Project stage: RAI ML0309104342003-03-31031 March 2003 Facsimile Transmission of Questions for Proposed Technical Specifications Changes and Exemption Request, Use of Framatome Anp Advanced Mark-BW Fuel Project stage: Other ML0313306512003-05-0606 May 2003 Request to Use Subsequent Edition and Addenda of ASME Section XI for Qualification of Examination Personnel Project stage: Request ML0314007262003-05-0909 May 2003 Request for Additional Information, Proposed Technical Specifications Changes and Exemption Request to Use Framatome Anp Advanced Mark-BW Fuel Project stage: Request ML0316106732003-06-10010 June 2003 Withholding from Public Disclosure, Document Response to Request for Additional Information and Revised Pages for March 2002 Evaluation Report - Framatome Fuel Transition Program Technical Specification Change Project stage: RAI ML0316403882003-06-12012 June 2003 N. Anna, Units 1 and 2 - Framatome Anp Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0323200022003-08-19019 August 2003 Facsimile Transmission of Questions for Proposed Technical Specifications Changes, Use of Framatome Anp Advanced Mark-BW Fuel Project stage: Other ML0327315722003-09-0808 September 2003 Facsimile Transmission of Questions on Proposed License Amendment to Use Framatome Anp Advanced Mark-BW Fuel Project stage: Other ML0325500032003-09-11011 September 2003 Facsimile Transmission of Questions on Proposed License Amendment to Use Framatome Anp Advanced Mark-BW Fuel Project stage: Other ML0328205902003-10-0606 October 2003 Meeting Summary - Usnrc/Vepco & Anp - to Discuss Framatome Fuel Transition Program at North Anna, Units 1 and 2 Project stage: Meeting ML0335002392003-12-0808 December 2003 Proposed Technical Specifications Changes & Exemption Request for Use of Framatome Anp Advanced Mark-BW Fuel Supplemental Information for Realistic Large Break Loss of Coolant Accident (Rlbloca) Containment Model Project stage: Supplement ML0401405092004-01-0606 January 2004 Stations, Units 1 and 2 - Engineering Evaluation Results and Closure of Commitment for Management of Environmentally Assisted Fatigue in Safety Injection Accumulator and Charging Nozzles Project stage: Request ML0401405102004-01-0606 January 2004 Supplemental Information for Realistic Large Break Loss of Coolant Accident (Rlbloca) Containment Pressure Analysis Proposed Technical Specifications Change & Exemption Request for Use of Framatome Anp Advanced Mark-BW Fuel Project stage: Supplement ML0401405642004-01-13013 January 2004 Facsimile Transmission of Question for Proposed Technical Specifications Changes, Use of Framatome Anp Advanced Mark-BW Fuel (Tacs MB4714 and MB4715) Project stage: Other ML0402908102004-01-22022 January 2004 Proposed Technical Specifications Changes & Exemption Request for Use of Framatome Anp Advanced Mark-BW Fuel, Response to Request for Additional Information Regarding Assessment of Fuel Assembly Bow Concern Project stage: Response to RAI ML0405505522004-02-12012 February 2004 Proposed Technical Specifications Changes and Exemption Request for Use of Framatome Anp Advanced Mark-BW Fuel, Supplemental Information for Loss of Coolant Accident Mixed Core Effects Project stage: Supplement ML0406909252004-03-0101 March 2004 Supplemental Information for SBLOCA Slot Breaks, Per Proposed Technical Specifications Changes and Exemption Request for Use of Framatome Anp Advanced Mark-BW Fuel Project stage: Supplement ML0419502182004-07-0101 July 2004 Day Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes Pursuant to the Requirements of 10 CFR 50.46 Project stage: Request ML0423305602004-08-20020 August 2004 Technical Specification Amendment No. 237, Pages 2.0-1, 4.0-1, 5.6-3, 5.6-4, 5.6-5 Project stage: Other ML0423306592004-08-20020 August 2004 8/20/04, North Anna, Unit 1, Issuance of Amendment Re. Conversion to Framatome Advanced Mark-BW Fuel Project stage: Approval 2003-05-09
[Table View] |
Text
VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 May 6, 2003 U.S. Nuclear Regulatory Commission Serial No.03-312 Attention: Document Control Desk NL&OS/ETS RO Washington, D.C. 20555 Docket Nos. 50-338/339 50-281 License Nos. NPF-4/7 DPR-37 Gentlemen:
VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 AND 2 SURRY POWER STATION UNIT 2 REQUEST TO USE SUBSEQUENT EDITION AND ADDENDA OF ASME SECTION XI FOR QUALIFICATION OF EXAMINATION PERSONNEL 10 CFR 50.55a(g)(4)(iv) permits the use of subsequent editions and addenda of ASME Section Xl (Code), subject to its endorsement by the regulations in paragraph 10 CFR 50.55a(b) and approval by the Commission.
It also allows the use of portions of editions and addenda provided that all related requirements of the respective editions and addenda are met.
Currently paragraph 10 CFR 50.55a(b) of the regulations endorses the 1998 Edition through the 2000 Addenda of ASME Section XI with certain modifications and limitations. Pursuant to 10 CFR 50.55a(g)(4)(iv) Virginia Electric and Power Company (Dominion) requests approval to use the 1998 Edition through the 2000 Addenda of ASME Section Xl, subsection IWA-2300, including references CP-1 89 1995 Edition, Appendix VI and Appendix VII and any rule modification and limitation, to establish the examiner qualification requirements for North Anna Units 1 & 2, Surry Unit 2, and the Surry and North Anna Containment programs. It is our position that IWA-2300 of the Code, including references CP-189 -
1995, Appendix VI and Appendix VIl, contain the related portions associated with examiner qualification, and only these sections of the Code would be affected.
The VT-1, VT-2, VT-3 examination requirements will be maintained and not the General Visual and Detailed Visual requirements for IWE of the later Code.
Using common examiner qualification requirements will result in resource flexibility and eliminate unnecessary administrative burden associated with multiple tracking of examiner qualification by station or program.
Surry Unit 1 will be entering its fourth inspection interval on October 14, 2003 using the 1998 Edition through the 2000 Addenda of ASME Section Xl as the basis for the ISI Program. Surry Unit 2 is currently in the third inspection interval using the 1989 Edition of ASME Section Xl until its fourth interval update on May 10, 2004, when it will also update to the 1998 Edition through the 2000 Addenda of ASME Section Xl. North Anna Unit 1 is in its third interval utilizing the 1989 Edition of ASME Section Xl including CP-189 - 1991 and does not require a ISI program update until May 1, 2009. North Anna Unit 2 is in its third interval utilizing the 1995 Edition through the 1996 Addenda of 1AN
ASME Section Xi and does not require a program update until December 14, 2010.
The containment programs (IWE & IWL) for each of the four units currently use the 1992 Edition and the 1992 Addenda of ASME Section Xl and are on separate inspection intervals (1St interval IWE and 2nd interval IWL).
In order to effectively schedule and use Dominion inspection personnel, we request NRC approval by October 14, 2003, consistent with the start of the Surry Unit 1 fourth interval. The use of the 1998 Edition through the 2000 Addenda of ASME Section XI, subsection IWA-2300, including references CP-189 1995 Edition, Appendix VI and Appendix VII, is requested for the remainder of the three units' inservice inspection intervals and the four units' containment inspection intervals. If you have any further questions or require additional information, please contact us.
Very truly yours, Leslie N. Hartz Vice President - Nuclear Engineering Commitments made in this letter: None cc:
U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW Suite 23 T85 Atlanta, Georgia 30303-8931 Mr. M. J. Morgan NRC Senior Resident Inspector North Anna Power Station Mr. R. A. Musser NRC Senior Resident Inspector Surry Power Station Mr. J. E. Reasor, Jr.
Old Dominion Electric Cooperative Innsbrook Corporate Center, Suite 300 4201 Dominion Blvd.
Glen Allen, Virginia 23060