Text

CRFA System Instrumentation 3.3.7.1 3.3 INSTRUMENTATION 3.3.7.1 Control Room Fresh Air (CRFA) System Instrumentation LCO 3.3.7.1 The CRFA System instrumentation for manual isolation shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3 During operations with a potential for draining the reactor vessel (OPDRVs).

ACTIONS


NOTE-------------------------------------

Separate Condition entry is allowed for each channel.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or more channels A.1 Place channel in 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> inoperable. trip.

B. Required Action and B.1 Close associated 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> associated Completion isolation dampers.

Time not met. I GRAND GULF 3.3-73 Amendment No. .-4-&, 157

Drywell Pressure 3.6.5.4 3.6 CONTAINMENT SYSTEMS 3.6.5.4 Drywell Pressure LCO 3.6.5.4 Drywell-to-primary containment differential pressure shall be 2 -0.25 psid and < 2.0 psid. I APPLICABILITY: MODES 1. 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Drywell-to-primary A.1 Restore drywell-to- 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> containment primary containment differential pressure differential pressure not within limits. to within limits.

B. Required Action and B.1 Be in MODE 3. 12 hours0.5 days <br />0.0714 weeks <br />0.0164 months <br /> associated Completion Time not met. AND B.2 Be in MODE 4. 36 hours1.5 days <br />0.214 weeks <br />0.0493 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.5.4.1 Verify drywell-to-primary containment 12 hours0.5 days <br />0.0714 weeks <br />0.0164 months <br /> differential pressure is within limits.

GRAND GULF 3.6 -62 Amendment No. 420, 157

Organization 5.2 5.0 ADMINISTRATIVE CONTROLS 5.2 Organization 5.2.1 Onsite and Offsite Orcanizations Onsite and offsite organizations shall be established for unit operation and corporate management, respectively. The onsite and offsite organizations shall include the positions for activities affecting safety of the nuclear power plant.

a. Lines of authority, responsibility, and communication shall be defined and established throughout highest management levels, intermediate levels, and all operating organization positions. These relationships shall be documented and updated, as appropriate, in organization charts, functional descriptions of departmental responsibilities and relationships, and job descriptions for key personnel positions, or in equivalent forms of documentation. These requirements, including the plant specific titles of those personnel fulfilling the responsibilities of the positions delineated in these Technical.Specifications, shall be documented in the UFSAR;
b. The plant manager shall be responsible for overall safe operation of the plant and shall have control over those onsite activities necessary for safe operation and maintenance of the plant;
c. A specified corporate executive shall have corporate responsibility for overall plant nuclear safety and shall take any measures needed to ensure acceptable performance of the staff in operating, maintaining, and providing technical support to the plant to ensure nuclear safety. The specified corporate executive shall be documented in the UFSAR; and
d. The individuals who train the operating staff, carry out radiation protection activities, or perform quality assurance functions may report to the appropriate onsite manager; however, these individuals shall have sufficient organizational freedom to ensure their independence from operating pressures.

(continued)

GRAND GULF 5.0-2 Amendment No. 120, 157

Organization 5.2 5.2 Organization (continued) 5.2.2 Unit Staff The unit staff organization shall include the following:

a. A non-licensed operator shall be on site when fuel is in the reactor and an additional non-licensed operator shall be on site while the unit is in MODE 1, 2, or 3.
b. At least one licensed RO shall be present in the control room when fuel is in the reactor. In addition, while the unit is in MODE 1, 2, or 3, at least one licensed SRO shall be present in the control room.
c. Shift crew composition may be one less than the minimum requirement of 10CFR50.54(m)(2)(i) and Specifications 5.2.2.a and 5.2.2.g for a period of time not to exceed 2 hours0.0833 days <br />0.0119 weeks <br />0.00274 months <br /> in order to accommodate unexpected absence of on-duty shift crew members provided immediate action is taken to restore the shift crew composition to within the minimum requirements.
d. A health physicist shall be on site when fuel is in the reactor. The position may be vacant for not more than 2 hours0.0833 days <br />0.0119 weeks <br />0.00274 months <br />, in order to provide for unexpected absence, provided immediate action is taken to fill the required position.
e. Administrative procedures shall be developed and implemented to limit the working hours of unit staff who perform safety related functions (e.g., licensed SROs, licensed ROs, health physicists, non-licensed operators, and key maintenance personnel).

Adequate shift coverage shall be maintained without routine heavy use of overtime. However, in the event that unforeseen problems require substantial amounts of overtime to be used, or during extended periods of shutdown for refueling, major maintenance, or major plant modification, on a temporary basis the following guidelines shall be followed:

1. An individual should not be permitted to work more than 16 hours0.667 days <br />0.0952 weeks <br />0.0219 months <br /> straight, excluding shift turnover time; -
2. An individual should not be permitted to work more than 16 hours0.667 days <br />0.0952 weeks <br />0.0219 months <br /> in any 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period, nor more than 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> in any 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> period, nor more than 72 hours3 days <br />0.429 weeks <br />0.0986 months <br /> in any 7 day period, all excluding shift turnover time; (continued)

GRAND GULF 5.0-3 Amendment No. F4, 157

Unit Staff Qualifications 5.3 5.0 ADMINISTRATIVE CONTROLS 5.3 Unit Staff Qualifications 5.3.1 Each member of the unit staff shall meet or exceed the minimum qualifications of ANSI/ANS-3.1-1978, except as clarified in the Quality Assurance Program Manual, for comparable positions as modified by Specification 5.2.2.f, except for the radiation protection manager and the STA, who shall meet or exceed the education and experience requirements of ANSI/ANS 3.1-1981 as endorsed by Regulatory Guide 1.8, Revision 2, 1987.

GRAND GULF 5.0-5 Amendment No. 120, 157

Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.8 Explosive Gas and Storage Tank Radioactivity Monitoring Program (continued)

b. A surveillance program to ensure that the quantity of radioactive material contained in any outside temporary tank not including liners for shipping radwaste is < 10 curies, excluding tritium and dissolved or entrained noble gases.

The provisions of SR 3.0.2 and SR 3.0.3 are applicable to the Explosive Gas and Storage Tank Radioactivity Monitoring Program surveillance frequencies.

5.5.9 Diesel Fuel Oil Testing Program A diesel fuel oil testing program to implement required testing of both new fuel oil and stored fuel oil shall be established.

The program shall include sampling and testing requirements, and acceptance criteria, all in accordance with applicable ASTM Standards. The purpose of the program is to establish the following:

a. Acceptability of new fuel oil for use prior to addition to storage tanks, and acceptability of stored fuel oil every 92 days, by determining that the fuel oil has:
1. a water and sediment contents within limits, and
2. a kinematic viscosity within limits for ASTM 2D fuel oil;
b. Total particulate concentration of the new fuel is

< 2 mg/100 ml when tested in accordance with ASTM D-2274-70 within 7 days after addition of the new fuel to the storage tank; and

c. Total particulate concentration of the fuel oil in the storage tanks is < 2 mg/100 ml when tested every 92 days in accordance with ASTM D-2274-70.

The provisions of SR 3.0.2 and SR 3.0.3 are applicable to the Diesel Fuel Oil Testing Program testing frequencies.

(continued)

GRAND GULF 6.0-14 Amendment No. 442-, 157

Programs and Manuals 5.5 5.5 Programs and Manuals (continued) 5.5.11 Technical Specifications (TS) Bases Control Program This program provides a means for processing changes to the Bases of these Technical Specifications.

a. Changes to the Bases of the TS shall be made under appropriate administrative controls and reviews.
b. Licensees may make changes to Bases without prior NRC approval provided the changes do not require either of the following:
1. A change in the TS incorporated in the license; or
2. A change to the updated FSAR or Bases that requires NRC approval pursuant to 10 CFR 50.59.
c. The Bases Control Program shall contain provisions to ensure that the Bases are maintained consistent with the UFSAR.
d. Proposed changes that do not meet the criteria of either Specification 5.5.11.b.1 or Specification 5.5.11.b.2 above shall be reviewed and approved by the NRC prior to implementation. Changes to the Bases implemented without prior NRC approval shall be provided to the NRC on a frequency consistent with 10 CFR 50.71(e).

5.5.12 10 CFR 50. Appendix J. Testing Program This program establishes the leakage rate testing program of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions. This program shall be implemented in accordance with the Safety Evaluation issued by the Office of Nuclear Reactor Regulation dated April 26, 1995 (GNRI-95/00087) as modified by the Safety Evaluation issued for Amendment No. 135 to the Operating License.

Consistent with standard scheduling practices for Technical Specifications required surviellances, intervals for the recommended surveillance frequency for Type A, B and C testing may be extended by up to 25 percent of the test interval, not to exceed 15 months.

GRAND GULF 5.0-16 Amendment No. 446, 157

Reporting Requirements Reporting Requirements 5.6 5.6 Reporting Requirements 5.6.2 Annual Radiolocical Environmental Operating Report (continued) results are not available for inclusion with the report, the report shall be submitted noting and explaining the reasons for the missing results. The missing data shall be submitted in a supplementary report as soon as possible.

5.6.3 Radioactive Effluent Release Report The Radioactive Effluent Release Report covering the operation of the unit during the previous calendar year shall be submitted by May 1 of each year. The report shall include a summary of the quantities of radioactive liquid and gaseous effluents and solid waste released from the unit. The material provided shall be consistent with the objectives outlined in the ODCM and process control program and in conformance with 10 CFR 50.36a and 10 CFR 50, Appendix I, Section IV.B.1.

5.6.4 Monthly Operating Reports Routine reports of operating statistics and shutdown experience, including documentation of all challenges to the main steam safety/relief valves, shall be submitted on a monthly basis no later than the 15th of each month following the calendar month covered by the report.

5.6.5 Core Operating Limits Report (COLR)

a. Core operating limits shall be established prior to each reload cycle, or prior to any remaining portion of a reload cycle, and shall be documented in the COLR for the following:
1) LCO 3.2.1, Average Planar Linear Heat Generation Rate (APLHGR),
2) LCO 3.2.2, Minimum Critical Power Ratio (MCPR),
3) LCO 3.2.3, Linear Heat Generation Rate CLHGR)
4) LCO 3.2.4, Fraction of Core Boiling Boundary (FCBB).
5) LCO 3.3.1.1, RPS Instrumentation, Table 3.3.1.1-1 function 2.d, and
6) LCO 3.3.1.3, Period Based Detection System (PBDS).

_ GL (continued)

GRAND GULF 5.0-18 Amendment No. 111-, -

High Radiation Area 5.7 5.0 ADMINISTRATIVE CONTROLS 5.7 High Radiation Area 5.7.1 Pursuant to 10 CFR 20, paragraph 20.1601(c), in lieu of the requirements of 10 CFR 20.1601(a), each high radiation area, as defined in 10 CFR 20, in which the intensity of radiation is

> 100 mrem/hr but < 1000 mrem/hr, shall be barricaded and conspicuously posted as a high radiation area and entrance thereto shall be controlled by requiring issuance of a Radiation Work Permit (RWP). Individuals qualified in radiation protection procedures (e.g., health physicists) or personnel continuously escorted by such individuals may be exempt from the RWP issuance requirement during the performance of their assigned duties in high radiation areas with exposure rates S 1000 mrem/hr, provided they are otherwise following plant radiation protection procedures for entry into such high radiation areas.

Any individual or group of individuals permitted to enter such areas shall be provided with or accompanied by one or more of the following:

a. A radiation monitoring device that continuously indicates the radiation dose rate in the area.
b. A radiation monitoring device that continuously integrates the radiation dose rate in the area and alarms when a preset integrated dose is received. Entry into such areas with this monitoring device may be made after the dose rate levels in the area have been established and personnel are aware of them.
c. An individual qualified in radiation protection procedures with a radiation dose rate monitoring device, who is responsible for providing positive control over the activities within the area and shall perform periodic radiation surveillance at the frequency specified by the radiation protection supervision in the RWP.

5.7.2 In addition to the requirements of Specification 5.7.1, areas with radiation levels 2 1000 mrem/hr shall be provided with locked or continuously guarded doors to prevent unauthorized entry and the keys shall be maintained under the administrative control of the operations shift management or radiation protection supervision.

Doors shall remain locked except during periods of access by personnel under an approved RWP that shall specify the dose rate (continued)

GRAND GULF 5.0-22 Amendment No. o, 157

High Radiation Area 5.7 5.7 High Radiation Area 5.7.2 (continued) levels in the immediate work areas and the maximum allowable stay times for individuals in those areas. In lieu of the stay time specification of the RWP, direct or remote (such as closed circuit TV cameras) continuous surveillance may be made by personnel qualified in radiation protection procedures to provide positive exposure control over the activities being performed within the area.

5.7.3 In addition to the requirements of Specification 5.7.1, for individual high radiation areas with radiation levels of > 1000 mrem/hr, accessible to personnel, that are located within large areas such as reactor containment, where no enclosure exists for purposes of locking, or that is not continuously guarded, and where no enclosure can be reasonably constructed around the individual area, that individual area shall be barricaded and conspicuously posted, and a flashing light shall be activated as a warning device.

GRAND GULF 5.0-23 Amendment No. a-2-, 157