MONTHYEARML24124A0342024-05-0101 May 2024 Summary of Public Meeting Concerning Annual Assessment of Catawba Nuclear Station Units 1 and 2, McGuire Nuclear Station Units 1 and 2, Oconee Nuclear Station Units 1, 2, and 3, Brunswick Steam Electric Plant Units 1 and 2, Shearon Harris ML24071A1692024-03-15015 March 2024 February 2024 Subsequent License Renewal Public Draft Environmental Impact Statement Meetings-Memo ML24071A1702024-03-15015 March 2024 February 2024 Oconee Draft EIS Public Meetings - Summary ML23118A2852023-05-0202 May 2023 Public Meeting Summary - 2022 Annual Assessment Meeting Regarding Catawba Nuclear Station, McGuire Nuclear and Oconee Nuclear Station ML22200A0772022-08-0808 August 2022 SLRA - Summary of July 14, 2022 and July 28, 2022 Public Meetings ML22193A0182022-07-18018 July 2022 SLRA - Summary of June 30, 2022 Public Meeting ML22129A0062022-05-10010 May 2022 Summary of April 20, 2022, Meeting with Duke Energy Progress, LLC, to Discuss Proposed License Amendment Request to Revise Reactor Coolant System Pressure Isolation Valve Operational Leakage Surveillance Requirement Frequency (L-2022-LRM 00 ML22124A2052022-05-0404 May 2022 Summary of May 4, 2022, Clarification Call with Duke Energy Carolinas, LLC, Application to Revise TS 3.7.7, Low Pressure Service Water (LPSW) System ML22130A0122022-05-0404 May 2022 SLRA - Summary of April 28, 2022 Public Meeting ML22075A2042022-04-0505 April 2022 SLRA - Summary of March 7, 2022 Public Meeting ML22084A6142022-04-0404 April 2022 SLRA - Summary of March 16, 2022 (Closed Public Meeting) ML22094A1112022-04-0404 April 2022 Public Meeting Summary 2021 Annual Assessment Meeting Catawba Dockets Nos. 50-413 and 50-414; McGuire No. 50-369 and 50-370; Oconee. 50-269, 50-270, and 50-287 ML22063A1162022-03-0808 March 2022 SLRA - Summary of Public Meeting Dated February 17, 2022 ML21341A5542021-12-29029 December 2021 Summary of November 29, 2021, Meeting with Duke Energy Progress, LLC and Duke Energy Carolinas, LLC to Discuss a Planned License Amendment Request to Relocate ML21348A5452021-12-14014 December 2021 December 13, 2021, Clarification Call Summary Use of an Alternative to the ASME Code Case N-853 Acceptance Criteria ML21279A1542021-11-0808 November 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Summary Memo ML21279A1192021-08-25025 August 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Summary ML21195A2692021-07-14014 July 2021 Meeting Summary: Pre-Submittal Meeting for the Oconee Subsequent License Renewal Application (EPID Number: L-2020-RNW-0028) (Docket Numbers: 50 269, 50-270, and 50-287) - Memo ML21195A2712021-07-14014 July 2021 Meeting Summary: Pre-Submittal Meeting for the Oconee Subsequent License Renewal Application (EPID Number: L-2020-RNW-0028) (Docket Numbers: 50 269, 50-270, and 50-287) - Summary ML21102A0612021-04-27027 April 2021 April 14, 2021, Meeting Summary Regarding Pre-Application Meeting to Discuss Proposed Relief Request Related to Code Case N-853 ML21099A0932021-04-0909 April 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Catawba, McGuire, and Oconee Nuclear Stations ML20266G2192020-11-0303 November 2020 Regulatory Audit Report Regarding License Amendment Request to Revise the Licensing Basis for High Energy Line Breaks Outside of the Containment Building ML20141L4172020-05-20020 May 2020 EOC Public Meeting Summary ML19331A5202019-12-12012 December 2019 Summary of Meeting with Duke Energy Carolinas, LLC to Discuss Submitted License Amendment Request for Oconee Nuclear Station, Units 1, 2, and 3 Regarding High Energy Line Break Licensing Basis ML19220A6702019-08-26026 August 2019 Summary of August 7, 2019, Meeting with Duke Energy Progress, LLC and Duke Energy Carolinas, LLC to Discuss a Proposed License Amendment Request for a Common Emergency Plan ML19207A0172019-07-30030 July 2019 Summary of Meeting with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment Request for Oconee Nuclear Station, Units 1, 2, and 3 Regarding High Energy Line Break Licensing Basis ML19102A3352019-04-12012 April 2019 Public Meeting Summary - Oconee Nuclear Station Docket Nos. 50-269, 50-270, and 50-287 ML19087A0622019-04-11011 April 2019 Summary of March 25, 2019, Public Teleconference with Duke Energy to Discuss the Request for Additional Information Response Regarding the Proposed Alternative to the Depth Sizing Qualification Requirement (Duke Energy Fleet Relief Request ML18227B2122018-09-0505 September 2018 Summary of August 1, 2018, Meeting with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment Request for Oconee Nuclear Station, Units 1, 2, and 3 Regarding Tornado Mitigation Licensing Basis ML18134A2292018-05-14014 May 2018 Summary of April 26, 2018, Public Teleconference with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment and 3 Regarding Technical Specification 3.8.1 ML18082A1082018-03-29029 March 2018 Summary of February 28, 2018, Meeting with Duke Energy Carolinas, LLC to Discuss Proposed LAR Regarding Tornado Mitigation Licensing Basis ML18082A0582018-03-23023 March 2018 Summary of Meeting with Oconee Nuclear Station to Discuss Annual Assessment of Oconee for the Period of January 01, 2017 - December 31, 2017 ML17179A3472017-07-18018 July 2017 Summary of Meeting with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment Request for Oconee Nuclear Station, Units 1, 2, and 3 Regarding Thermal Margin for the Standby Shutdown Facility ML17103A0292017-04-13013 April 2017 Summary of Meeting to Provide Opportunities to Discuss Annual Assessment of Oconee Nuclear Station Units 1, 2 and 3 ML16166A4022016-06-27027 June 2016 Summary of November 18, 2015, and December 15, 2015, Meetings with Duke Energy Carolinas, LLC to Discuss a Proposed Relief Request in Accordance with 10 CFR 50.55a(z) for the Oconee Nuclear Station, Units 1, 2, and 3 ML16132A4352016-05-20020 May 2016 Summary of October 13, 2015, Meeting with Duke Energy Carolinas, LLC to Discuss Proposed LAR to Support Keowee Dam Stator Replacement ML15161A4312015-06-19019 June 2015 Summary of Meeting with Duke Energy Carolinas, LLC, to Discuss Ongoing Major Projects at Oconee Nuclear Station, Units 1, 2 and 3 ML15089A1642015-04-27027 April 2015 Summary of February 25, 2015, Partially Closed Meeting with Industry Stakeholders Regarding the Babcock and Wilcox Loss of Coolant Accident Evaluation Model Analysis ML15113A6262015-04-23023 April 2015 April 14, 2015 Summary of Public Meeting on Oconee Nuclear Station, Units 1, 2 and 3 to Discuss the Annual Assessment ML14356A0052014-12-31031 December 2014 Summary of December 3, 2014, Category 1 Public Meeting with Duke Energy Carolinas, LLC to Discuss NTTF Recommendation 2.1, Flooding Response for Oconee Nuclear Station, Units 1, 2, and 3 ML14147A3652014-05-27027 May 2014 Annual Assessment Public Meeting Summary Memo ML14069A3492014-03-13013 March 2014 Summary of Meeting with Duke Energy Carolinas, LLC, to Discuss Ongoing Major Projects at Oconee Nuclear Station, Units 1, 2, and 3 ML13336A5982013-12-0404 December 2013 Summary of Meeting with Duke Energy Carolinas, LLC, to Discuss the Proposed One-time TS Completion Time Change to Perform Khu Generator Field Pole Rewind Maintenance - Oconee Nuclear Station Units 1, 2, and 3 (TAC Nos. ME9021, ME9022, and M ML13312A9882013-11-0808 November 2013 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Provide Opportunities to Discuss the Planned Fukushima-Related Modifications ML13281A6972013-10-21021 October 2013 10/3/13 Summary of Meeting with Duke Energy Carolinas, LLC to Discuss the Protected Service Water System Operation - Oconee Nuclear Station Units 1, 2, and 3 (TAC Nos. ME7737, ME7738, ME7739, ME7746, ME7747, and ME7748) ML13281A5412013-10-21021 October 2013 9/24/2013 - Oconee Nuclear Station, Units 1, 2, and 3, Summary of Meeting with Duke Energy Carolinas, LLC, to Discuss the Jocassee Dam Seismic Analysis ML13241A4482013-08-29029 August 2013 August 28, 2013 Summary of Public Meeting - Major Projects Status Meeting with Oconee ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13134A5232013-05-14014 May 2013 5/9/2013 Summary of Public Meeting with Duke Energy Corp., Oconee Nuclear Station to Provide Opportunities to Discuss the Annual Assessment for the Year 2012 ML13122A4362013-05-0606 May 2013 Summary of April 9, 2013, Meeting with Duke Energy Carolinas, LLC, to Discuss the Re-evaluation of External Flooding for Oconee Nuclear Station, Units 1, 2, and 3 2024-05-01
[Table view] |
Text
April 7, 2003 LICENSEE: DUKE ENERGY COMPANY FACILITY: OCONEE NUCLEAR STATION, UNITS 1, 2 AND 3
SUBJECT:
SUMMARY
OF MARCH 20, 2003, MEETING TO DISCUSS TORNADO MITIGATION On March 20, 2003, the Nuclear Regulatory Commission (NRC) met with Duke Energy Company (the licensee) to discuss the June 7, 2002, submittal that dealt with tornado mitigation. (A meeting had already been held on December 10, 2002, to discuss this submittal.) is a list of the meeting attendees. Enclosure 2 is an electronic message that was sent by the licensee to the NRC prior to the meeting. The June 7, 2002, submittal, minutes of the December 10, 2002, meeting, and the handouts provided by the licensee for the March 20, 2003, meeting are accessible electronically from the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams/html. The accession number for the June 7, 2002, submittal is ML021710770; the accession number for the minutes of the December 10, 2002, meeting is ML030020017; and the accession number for the handouts provided during the March 20, 2003, meeting is ML030830443.
Prior to the meeting, the NRC had sent questions to the licensee concerning the June 7, 2002, submittal. Draft answers to these questions were provided in the licensees handout entitled Duke Responses to RAI Concerning Proposed License Amendment Request to Fully Credit the Standby Shutdown Facility and to Eliminate Crediting the Spent Fuel Pool to High Pressure Injection System Flow Path for Tornado Mitigation, Oconee Nuclear Station, Units 1, 2 and 3.
The contents of this handout, which had been provided to the NRC the day before the meeting, were discussed during the meeting.
Following are the some of the action items that resulted from the meeting:
- 1. The NRC agreed to relook at the response to Question 1 to determine whether any additional information is required.
- 2. The licensee agreed to expand its response to Question 2 to provide more details regarding the risk benefit that could be achieved by eliminating certain tornado vulnerabilities.
- 3. The licensee agreed to expand its response to Question 5b to provide additional justification for the use of 0.1 as the probability of the failure of the pressurizer safety valves to reseat following liquid relief.
- 4. The licensee agreed to expand its response to Question 15 to include some historic data on lake level and the methods that can be used to control lake level.
- 5. The licensee agreed to expand its response to Question 19 to provide further discussion of the secondary side heat removal run failure.
In addition, the NRC noted it had not had time to thoroughly review the draft responses, since the NRC had received them the day before the meeting. After NRC completes its review of the draft responses, there may be additional comments and questions.
Docket Nos. 50-269, 50-270 and 50-287
Enclosures:
As stated cc w/encls: See next page
ML030970098 NRC-001 OFFICE PDII-1/PM PDII-1/LA PDII-1/SC NAME LOlshan CHawes JNakoski DATE 4/2/2003 3/31/2003 4/3/2003 LIST OF ATTENDEES MEETING TO DISCUSS TORNADO MITIGATION MARCH 20, 2003 NRC DUKE C. Doutt D. Brewer J. Lazevnick D. Coyle L. Lois E. Burchfield L. Olshan R. Gambrell J. Nakoski L. Kanipe M. Pohida S. Newman R. Schin* L Nicholson T. Specht J. Tatum
- Participated by telephone Enclosure 1
Leonard Olshan - Tornado Meeting Page 1 From: "Larry E Nicholson" <Ienicholson@duke-energy.com>
To: <Ino@nrc.gov>
Date: 3/17/03 2:22PM
Subject:
Tornado Meeting
- Lenny, We intend on getting you written responses to the staffs questions tomorrow in time for your folks to read before the meeting. I plan on leading us thru by summarizing the question then opening up for questions. We are not preparing a separate presentation, etc.
Also, I thought it might be useful to share beforehand some broad philosophical perspectives the we used to influence our direction:
Oconee was originally licensed with the single Station ASW pump as the means of post-tornado secondary cooling. Primary makeup was not discussed. Post-TMI interactions still focused on secondary makeup. The staff acknowledged EFW and Station ASW limitations, and offered an option to either fully protect the SSF or analyze the Station ASW.
The staff ultimately accepted the current strategy primarily based on the SSF. At this time the SSF was included in our licensing basis for Tornadoes. The HPI-SFP flowpath was added to the UFSAR by Duke around 1990 since it was available and could be used for an outside design basis seal LOCA. This option was not added to meet any regulatory requirement or as a result of any staff interactions. We have since realized that the complications and uncertainties associated with this alignment do not justify retaining this flowpath as a viable mitigation option. A decision was made in 2000 to upgrade the RCP seals, with a risk benefit far off setting the benefit from this flowpath option.
Duke felt it important to launch a significant Tornado Project in large part due to the contribution of Tornadoes to our overall CDF. However, it is important to note that from an overall CDF perspective, Oconee is around the middle of the fleet.
Since our existing tornado licensing basis was already essentially risk-based, the initial phase of our current project was to update our Tornado PRA to state-of-the art. We have had this model validated by independent experts and it has been heavily inspected by the region. Our previous model generally considered the tornado a Unit 3 event only w/LOOP on the other 2 units. Our new model integrates the risk from a total site impact following the full range of tornadoes.
Duke has and will continue to evaluate insights revealed by the PRA work and explore potential avenues to reduce risk. We implemented a mod to resolve an aux power vulnerability for Keowee.
The bottom line, however, is that there are no additional, reasonable modifications that would produce an appreciable risk benefit. The RCP seal mod was the only option, which has been done. Otherwise, a major redesign of the plant is not an option. Hardening the SSF, while not producing substantial risk benefit, does provide a deterministically assured means of tornado mitigation for all 3 units. We will know we have a system, complete with power, that will survive the tornado.
Hope this helps.
Larry Enclosure 2
Oconee Nuclear Station cc:
Ms. Lisa F. Vaughn Mr. L. E. Nicholson Legal Department (ECIIX) Compliance Manager Duke Energy Corporation Duke Energy Corporation 422 South Church Street Oconee Nuclear Site Charlotte, NC 28201-1006 7800 Rochester Highway Seneca, SC 29672 Anne W. Cottingham, Esquire Winston and Strawn Ms. Karen E. Long 1400 L Street, NW Assistant Attorney General Washington, DC 20005 North Carolina Department of Justice P.O. Box 629 Manager, LIS Raleigh, NC 27602 NUS Corporation 2650 McCormick Drive, 3rd Floor Mr. C. Jeffrey Thomas Clearwater, FL 34619-1035 Manager - Nuclear Regulatory Licensing Duke Energy Corporation Senior Resident Inspector 526 South Church Street U.S. Nuclear Regulatory Commission Charlotte, NC 28201-1006 7812B Rochester Highway Seneca, SC 29672 Mr. Richard M. Fry, Director Division of Radiation Protection Mr. Henry Porter, Director North Carolina Department of Environment, Division of Radioactive Waste Management Health, and Natural Resources Bureau of Land and Waste Management 3825 Barrett Drive Department of Health and Environmental Raleigh, NC 27609-7721 Control 2600 Bull Street Mr. Peter R. Harden, IV Columbia, SC 29201-1708 VP-Customer Relations and Sales Westinghouse Electric Company Mr. Michael A. Schoppman 6000 Fairview Road, 12th Floor Framatome ANP Charlotte, NC 28210 1911 North Ft. Myer Drive, Suite 705 Rosslyn, VA 22209