February 2003 Monthly Operating Report for Catawba, Units 1, & 2
ML030790259
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 03/13/2003
From: Dimmery T
Duke Energy Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML030790259 (9)


Text

S Duke Duke Energy Corporation 526 South Church Street En PO. Box 1006 Charlotte, NC 28201-1006 March 13, 2003 U.S. Nuclear Regulatory Commission Attention:

Document Control Desk Washington, D.C.

20555

Subject:

Duke Energy Corporation Catawba Nuclear Station, Units 1, and 2 Docket Numbers 50-413 and 50-414 Monthly Performance and Operation Status-February, 2003 Please find attached information concerning the performance and operation status of the Catawba Nuclear Station for the month of February, 2003.

Any questions or comments may be directed to Roger A. Williams at (704) 382-5346.

Sincerely, Terry Dimmery, Manager Nuclear Business Support Attachment XC:

L.

A.

Reyes, Regional Administrator

USNRC, Region II Chandu Patel, Project Manager
USNRC, ONRR INPO Records Center Ms. Margaret Aucoin Nuclear Assurance Corporation Dottie Sherman, ANI Library American Nuclear Insurers Darrell Roberts, Senior Resident Inspector

Document Control Desk U.S.

NRC -

Catawba bxc:

Gary Gilbert (CN01RC)

K.

E. Nicholson (CN01RC)

RGC Site Licensing File ELL (ECO50)

Operating Data Report Docket No.

Date Completed By Telephone Operating Status

1. Unit Name:

Catawba 1

2. Reporting Period:

February 1, 2003 - February 28, 2003

3. Licensed Thermal Power (MWt):

3411

4. Nameplate Rating (Gross MWe):

1305 *

5. Design Electrical Rating (Net Mwe):

1145

6. Maximum Dependable Capacity (Gross MWe):

1192

7. Maximum Dependable Capacity(Net MWe):

1129

8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:

50-413 March 13,2003 Roger Williams 704-382-5346 Notes: *Nameplate Rating (GrossMWe) calculated as 1450.000 MVA *.90 power factor per Page iii, NUREG-0020.

9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month

11. Hours in Reporting Period 672.0
12. Number of Hours Reactor was Critical 641.6
13. Reactor Reserve Shutdown Hours 0.0
14. Hours Generator On-Line 634.9
15. Unit Reserve Shutdown Hours 0.0
16. Gross Thermal Energy Generated (MWH) 2145247
17. Gross Electrical Energy Generated (MWH) 769572
18. Net Electrical Energy Generated (MWH) 728977
19. Unit Service Factor 94.5
20. Unit Availability Factor 94.5
21. Unit Capacity Factor (Using MDC Net) 96.1
22. Unit Capacity Factor (Using DER Net) 94.7
23. Unit Forced Outage Rate 5.5
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)

YTD 1416.0 1385.6 0.0 1378.9 0.0 25115023 1683417 1597581 97.4 97.4 99.9 98.5 2.6 Cumulative 154897.0 128490.9 0.0 126974.5 0.0 439979508 148929340 140495267 82.0 82.0 80.2 79.2 5.5

25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation 3A - 3/13/2003

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-413 UNIT NAME: Catawba 1 DATE: March 13, 2003 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: February. 2003 (1) Reason A - Equipment failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)

H - Other (Explain)

(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 30- 2/13/2003 No.

Date:

Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

MAIN TURBINE TRIP GENERATED BY HI HI STEAM GENERATOR lB 1 02/04/03 F

37.10 A

LEVEL Summary:

Catawba unit I began the month of February operating at approximately 100% full power. On 03/04/02 at 1005 a automatic reactor trip was initiated from 100% full power by a main turbine trip generated by Hi Hi steam generator lB level. The unit was placed on-line 02/05/03 at 2311. During power escalation, the unit held at 18% power from 02/06/03 at 0013 to 0103 due to main feedwater nozzle swap. The unit held at 55% power from 0520 to 0550 to place second main feedwater pump in service. The unit held at 87% power from 1044 to 1207 to perform the main turbine control valve movement test. The unit returned to 100% full power on 02/06/03 at 1700 and operated at or near 100% full power the.

remainder of the month.

MONTHLY REFUELING INFORMATION REQUEST

1.

Facility name:

Catawba Unit 1

2.

Scheduled next refueling shutdown: November 2003

3.

Scheduled restart following refueling: December 2003 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.

4.

Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

6.

Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).

7.

Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 944

8.

Present licensed fuel pool capacity: 1418 Size of requested or planned increase: -

9.

Projected date of last refueling which can be accommodated by present license capacity:

November 2009 DUKE POWER COMPANY DATE: March 13,2003 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

Operating Data Report Docket No.

Date Completed By Telephone Operating Status

1. Unit Name:

Catawba 2

2. Reporting Period:

February 1, 2003 - February 28, 2003

3. Licensed Thermal Power (MWt):

3411

4. Nameplate Rating (Gross MWe):

1305 *

5. Design Electrical Rating (Net Mwe):

1145

6. Maximum Dependable Capacity (Gross MWe):

1192

7. Maximum Dependable Capacity(Net MWe):

1129

8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:

50-414 March 13,2003 Roger Williams 704-382-5346 Notes: *Nameplate Rating (GrossMWe) calculated as 1450.000 MVA *.90 power factor per Page iii, NUREG-0020.

9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:
11. Hours in Reporting Period
12. Number of Hours Reactor was Critical
13. Reactor Reserve Shutdown Hours
14. Hours Generator On-Line
15. Unit Reserve Shutdown Hours
16. Gross Thermal Energy Generated (MWH)
17. Gross Electrical Energy Generated (MWH)
18. Net Electrical Energy Generated (MWH)
19. Unit Service Factor
20. Unit Availability Factor
21. Unit Capacity Factor (Using MDC Net)
22. Unit Capacity Factor (Using DER Net)
23. Unit Forced Outage Rate
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Initial Criticality Initial Electricity Commercial Operation This Month 672.0 672.0 0.0 672.0 0.0 2271473 823027 783384 100.0 100.0 103.3 101.8 0.0 YTD 1416.0 1416.0 0.0 1416.0 0.0 29921734 1742551 1658638 100.0 100.0 103.8 102.3 0.0 Cumulative 144913.0 121220.9 0.0 119796.8 0.0 418891561 140388600 132643453 82.7 82.7 81.0 79.9 6.8 Achieved 3A - 3/13/2003

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-414 UNIT NAME: Catawba 2 DATE: March 13,2003 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: February, 2003 (1) Reason A - Equipment failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)

H - Other (Explain)

(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3C-2/13/2003 No.

Date:

Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

No Outages for the Month Summary:

MONTHLY REFUELING INFORMATION RE(OUEST

1.

Facility name:

Catawba Unit 2

2.

Scheduled next refueling shutdown: March 2003

3.

Scheduled restart following refueling: March 2003 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.

4.

Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

6.

Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).

7.

Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 836

8.

Present licensed fuel pool capacity: 1418 Size of requested or planned increase: -

9.

Projected date of last refueling which can be accommodated by present license capacity:

May 2012 DUKE POWER COMPANY DATE: March 13,2003 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

CATAWBA NUCLEAR STATION MONTHLY OPERATING STATUS REPORT JANUARY 2003

1.

Personnel Exposure The total station liquid release for JANUARY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.

The total station gaseous release for JANUARY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.