Safety Evaluation Report Re Peach Bottom, Units 2 & 3, Chapters 5, 6, and Appendices License Renewal, Section 5, Page 5-1 - Appendix C
ML030370678
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 02/05/2003
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Solorio, D L, NRR/DRIP/RLEP, 415-1973
References
Download: ML030370678 (19)


Text

5-1 5 REVIEW BY THE ADVISORY COMMITTEE ON REACTOR SAFEGUARDS On September 13, 2002, the staff issued its safety evaluation report (SER) with open and confirmatory items. Since that time, the Advisory Committee on Reactor Safeguards (ACRS) has conducted a review of the 10 CFR Part 54 portion of the Peach Bottom license renewal application. On October 30, 2002, the applicant presented its license renewal application, and the staff presented its review findings to the ACRS Plant License Renewal Subcommittee. The ACRS Subcommittee will continue its detailed review of the Peach Bottom license renewal application after the final SER is issued. Exelon Corporation and the staff will meet with the full committee to discuss issues associated with the review of the application on March 6, 2003.

The meeting will be open to the public.

After the ACRS completes its review of the Peach Bottom license renewal application, the full committee will issue a report discussing the results of its review. This report will be included in this SER when it is issued as a NUREG. The staff will address any issues and concerns identified in that report.

6-1 6 CONCLUSIONS The staff reviewed the Peach Bottom Atomic Power Station, Units 2 and 3, license renewal application in accordance with Commission regulations and the NRC Standard Review Plan for the Review of License Renewal Applications for Nuclear Power Plants, dated July 2001.

The Commissions regulatory standards for issuance of a renewed license are in 10 CFR 54.29.

In a safety evaluation report (SER) issued on September 13, 2002, the staff identified a number of open and confirmatory items. All of those items have been resolved, as discussed in this SER. On the basis of its evaluation of the application, as discussed above, the staff concludes that: (1) actions have been identified and have been or will be taken with respect to managing the effects of aging during the period of extended operation on the functionality of structures and components that have been identified to require an aging management review under 10 CFR 54.21(a)(1), and (2) actions have been identified and have been or will be taken with respect to time-limited aging analyses that have been identified to require review under 10 CFR 54.21(c). Accordingly, the staff finds that there is reasonable assurance that the activities authorized by the renewed license will continue to be conducted in accordance with the current licensing basis for the Peach Bottom Atomic Power Station, Units 2 and 3. The staff notes that the requirements of subpart A of 10 CFR Part 51 are documented in the final plant-specific supplement to the Generic Environmental Impact Statement issued on January 22, 2003.

A-1 APPENDIX A CHRONOLOGY This appendix contains a chronological listing of routine licensing correspondence between the U.S. Nuclear Regulatory Commission (NRC) staff and Exelon Generation Company, LLC (Exelon), regarding the NRC staffs review of the Peach Bottom Atomic Power Station (PBAPS), Unit 2 and 3, license renewal application (LRA) (Docket Nos. 50-277 and 50-278).

July 2, 2001 In a letter signed by J. Benjamin, Exelon submitted its application to renew the operating licenses of Peach Bottom Atomic Power Station, Units 2 and 3. In its submittal, Exelon provided the original of the application, 17 paper copies and 30 copies of the application on CD-ROM.

July 2, 2001 In a letter signed by J. Benjamin, Exelon submitted four sets of boundary drawings to the NRC.

July 18, 2001 In a letter signed by D. Matthews, NRC informed Exelon that the NRC had received its application to renew the operating licenses of Peach Bottom Atomic Power Station, Units 2 and 3, on July 2, 2001, and that Mr. Raj Anand was appointed as the project manager for the Peach Bottom LRA.

July 25, 2001 NRC published a Federal Register notice (FRN) of the receipt of the Peach Bottom Atomic license renewal application.

August 27, 2001 In a letter signed by R. Anand, NRC issued a summary of the public meeting held on August 14, 2001. In this meeting, Exelon made a presentation to the NRC staff and members of the public regarding information contained in the Peach Bottom LRA.

August 31, 2001 NRC published an acceptance for docketing and opportunity for hearing Federal Register notice (FRN) regarding the Peach Bottom LRA.

September 5, 2001 In a letter signed by D. Matthews, NRC informed Exelon that the NRC staff determined that the contained information in the Peach Bottom LRA submitted on July 2, 2001, was acceptable for docketing and sufficient for the staff to begin its review.

October 26, 2001 In a letter signed by R. Anand, NRC issued the summary of a public meeting between the staff and Exelon representatives. The meeting was held on September 24 and 25, 2001, to discuss the scoping and screening methodology and electrical sections of the PBAPS LRA.

October 30, 2001 In a letter to Exelon signed by R. Anand, the NRC staff requested additional information regarding the scoping and screening methodology discussed in Section 2.1 of the Peach Bottom LRA.

A-2 November 5, 2001 In a letter to Exelon signed by R. Anand, the NRC staff issued a summary of the public meeting held on October 22, 2001. In this meeting Exelon provided clarifications of the scoping and screening process discussed in the Peach Bottom LRA.

November 16, 2001 In a letter to Exelon signed by R. Anand, the NRC staff provided the schedule for the review of the Peach Bottom Atomic Power Station, Unit 2 and 3, LRA.

November 16, 2001 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs request for additional information (RAI) dated October 30, 2001, regarding Section 2.1-1 of the Peach Bottom LRA.

December 14, 2001 In a letter signed by R. Anand to Exelon, the NRC staff provided the findings of its audit of the scoping and screening methodology use in the Peach Bottom LRA.

January 23, 2002 In a letter to Exelon signed by R. Anand, the NRC staff requested additional information regarding the scoping and screening methodology discussed in Section 2.1.2 of the Peach Bottom LRA.

January 23, 2002 In a letter to Exelon signed by R. Anand, the NRC staff requested additional information regarding the aging management of electrical and instrument and control discussed in Section 3.6 of the Peach Bottom LRA.

January 23, 2002 In a letter signed by R. Anand, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on December 26, 2001, to clarify information provided by Exelon in Section 3.2 of the Peach Bottom LRA.

January 28, 2002 In a letter signed by R. Anand, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on January 16, 2002, to clarify information provided by Exelon in Section 3.5 of the Peach Bottom LRA.

January 30, 2002 In a letter signed by R. Anand, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on January 3, 2002, to clarify information provided by Exelon in Section 4.3 of the Peach Bottom LRA.

February 6, 2002 In a letter signed by R. Anand, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on February 4, 2002 to clarify information provided by Exelon in Section 2.3 of the Peach Bottom LRA.

February 6, 2002 In a letter to Exelon signed by R. Anand, the NRC staff requested additional information regarding the aging management of the reactor

A-3 coolant system, the engineered safety feature systems, the auxiliary systems, and the steam and power conversion systems as discussed in Sections 3.1, 3.2, 3.3, and 3.4 of the Peach Bottom LRA.

February 7, 2002 In a letter to Exelon signed by R. Anand, the NRC staff requested additional information regarding time-limited aging analyses, identification of TLAAs, reactor vessel embrittlement, metal fatigue, and reactor vessel main steam nozzle cladding removal corrosion allowance as discussed in Sections 4.0, 4.1, 4.2, 4.3, and 4.7.1 of the Peach Bottom LRA.

February 28, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAI dated January 23, 2002, regarding Section 2.1.2 of the Peach Bottom LRA.

March 1, 2002 In a letter to Exelon signed by R. Anand, the NRC staff requested additional information regarding the aging management of containment, structure, and component supports as discussed in Section 3.5 of the Peach Bottom LRA.

March 1, 2002 In a letter to Exelon signed by R. Anand, the NRC staff requested additional information regarding the scoping and screening results for reactor coolant system, engineered safety features systems, and auxiliary systems as discussed in Sections 2.3.1, 2.3.2, and 2.3.3 of the Peach Bottom LRA.

March 6, 2002 In a letter to Exelon signed by R. Anand, the NRC staff requested additional information regarding the aging management activities as discussed in Appendix B of the Peach Bottom LRA.

March 12, 2002 In a letter to Exelon signed by R. Anand, the NRC staff requested additional information regarding the aging management activities as discussed in Appendix B of the Peach Bottom LRA.

March 12, 2002 In a letter to Exelon signed by R. Anand, the NRC staff requested additional information regarding the plant-level scoping, and screening results for mechanical, structures, component supports, and electrical and instrumentation and controls as discussed in the Sections 2.2, 2.3, 2.4, and 2.5 of the Peach Bottom LRA.

March 12, 2002 In a letter to Exelon signed by R. Anand, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on January 22, 2002, to clarify information provided by Exelon in Sections 3.3 and 3.4 of the Peach Bottom LRA.

March 13, 2002 In a letter to Exelon signed by R. Anand, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on January 22, 2002, to clarify information provided by Exelon in Sections 3.1and 4.1 of the Peach Bottom LRA.

A-4 April 5, 2002 In a letter to Exelon signed by R. Anand, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on February 20, 2002, to clarify information provided by Exelon in Section 2.0 of the Peach Bottom LRA.

April 29, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAIs dated January 23, 2002, regarding Section 3.6 of the Peach Bottom LRA.

April 29, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAIs dated March 12, 2002, regarding the Appendix B aging management activities discussed in the Peach Bottom LRA.

May 01, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAIs dated February 7, 2002, regarding Section 4.0 of the Peach Bottom LRA.

May 06, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAIs dated March 1, 2002, regarding Section 2.3 of the Peach Bottom LRA.

May 06, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAIs dated February 6, 2002, regarding Sections 3.1, 3.2, 3.3, and 3.4 of the Peach Bottom LRA.

May 14, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAIs dated March 6, 2002, regarding Appendix B aging management activities discussed in the Peach Bottom LRA.

May 21, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAIs dated March 1, 2002, regarding Section 3.5 of the Peach Bottom LRA.

May 21, 2002 In a letter signed by M. Gallagher, Exelon submitted its response to the NRC staffs RAIs dated January 23, February 6, 2002, regarding RAI 2.1.2-3, 2.1.2-4, and 3.3-1.

May 22, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAIs dated March 12, 2002, regarding Section 2.0 of the Peach Bottom LRA.

May 31, 2002 In a NRC Region I letter to Exelon, signed by W. Lanning, the staff submitted Inspection Report 50-277/02-09, 50-278/02-09 concerning the scoping and screening of systems, structures, and components discussed in the Peach Bottom LRA.

A-5 June 10, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAIs dated March 12, 2002, regarding Section 4.2-7 of the Peach Bottom LRA.

July 18, 2002 In a letter to Exelon signed by R. Anand, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on June 17, 2002 to clarify information provided by Exelon concerning reactor vessel internals fatigue and embrittlement in Section 4.3.2 of the Peach Bottom LRA.

July 18, 2002 In a letter to Exelon signed by R. Anand, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on January 23 and March 12, 2002, to clarify information provided by Exelon concerning scoping and aging management of electrical and instrumentation and controls in Sections 2.5 and 3.6 of the Peach Bottom LRA.

July 30, 2002 In a letter signed by M.P. Gallagher, Exelon submitted its response to the NRC staffs RAI concerning fire protection activities, aging effects for carbon steel piping in an outdoor environment, and recovery path during station blackout system (SBO).

August 6, 2002 In a letter signed by P. Kuo, NRC informed Exelon that David L. Solorio was appointed Project Manager for the Peach Bottom LRA.

September 20, 2002 In a letter to Exelon signed by W. Dam, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on August 6 & 8, 2002, to clarify information provided by Exelon of the Peach Bottom LRA.

September 24, 2002 In a letter to Exelon signed by D. Solorio, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on July 23, August 19, and September 5 & 6, 2002, to clarify information provided by Exelon of the Peach Bottom LRA.

November 26, 2002 In a letter signed by M.P. Gallagher, Exelon submitted the response to Open Items and Confirmatory Items and Verification of Accuracy for Safety Evaluation Report (SER) Related to the License Renewal of Peach Bottom Atomic Power Station, Units 2 & 3.

December 19, 2002 In a letter signed by M.P. Gallagher, Exelon submitted the Amendment 1 to the Application for Renewal Operating License.

January 14, 2003 In a letter signed by M.P. Gallagher, Exelon submitted response to request for additional information related to license renewal.

January 29, 2003 In a letter signed by M.P. Gallagher, Exelon submitted the response to Teleconference Request to Modify Fuse Holder Inspection Program.

A-6 January 29, 2003 In a letter signed by M.P. Gallagher, Exelon submitted the response to Teleconference Request for Additional Clarification Related to SER Open Item 4.5.2-1 Response for Top Guide Inspection.

January 31, 2003 In a letter signed by M.P. Gallagher, Exelon submitted the response to request for additional information related to license renewal.

January 31, 2003 In a letter signed by M.P. Gallagher, Exelon submitted a list of future actions and a revision to the UFSAR Supplement for the Peach Bottom LRA.

February 3, 2003 In a letter to Exelon signed by R. Anand, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on November 14, 2002 to discuss information in Section 4.3.2, Reactor Vessel Internals Fatigue and Embrittlement of the Peach Bottom LRA.

February 4, 2003 In a letter to Exelon signed by D. Solorio, NRC issued a summary of a conference call between the staff and Exelon representatives. This conference call was held on December 4, 2002 to discuss matters related to the NRC staff review of the Peach Bottom Atomic Power Station LRA.

February 4, 2003 In a letter to Exelon signed by D. Solorio, NRC issued a summary of a teleconference between the staff and Exelon representatives. This teleconference was held on November 5, 2002 to discuss matters related to the NRC staff review of the Peach Bottom LRA.

February 5, 2003 In a letter signed by M.P. Gallagher, Exelon submitted a revised list of future actions and a revision to the UFSAR Supplement for the Peach Bottom LRA.

February 5, 2003, In a letter to Exelon signed by D. Solorio, NRC issued a summary of a to documented the receipt of draft responses to open and confirmatory Items for the Safety Evaluation Report for the Peach Bottom Atomic Power Station License Renewal Application.

February 6, 2003 In a letter to Exelon signed by D. Solorio, NRC issued a summary of discussions regarding a draft list of future commitments related to the safety evaluation report for the Peach Bottom Atomic Power Station license renewal application.

B - 1 APPENDIX B REFERENCES This appendix lists the references used in preparing the safety evaluation report on the review of the license renewal application for Peach Bottom Atomic Power Station, Units 2 and 3, under Docket Numbers 50-277 and 50-278.

AMERICAN CONCRETE INSTITUTE (ACI)

ACI 301, Specifications for Structural Concrete for Buildings ACI 318-63, Building Code Requirements for Reinforced Concrete AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

ASME Boiler and Pressure Vessel Code, July 1989 ASME Boiler and Pressure Vessel Code,Section III, Rules for Construction of Nuclear Power Plant Components (through Summer 1979 addenda)

ASME Boiler and Pressure Vessel Code,Section XI, Rules for Inservice Inspection of Nuclear Power Plant Components ASME Boiler and Pressure Vessel Code,Section XI, Appendix G (1995 edition through 1996 addenda)

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

ASTM A307, Standard Specification for Carbon Steel Bolts and Steels, 60,000 psi Tensile Strength ASTM A325, Standard Specification for Structural Bolts, Steel, Heat-Treated, 120 ksi and 105 ksi Minimum Tensile Strength ASTM A490, Standard Specification for Heat-Treated Steel Structural Bolts, 150ksi Minimum Tensile Strength ASTM D975-1981, Standard Specification for Diesel Fuel Oils AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA C203, AWWA Standard for Coal-Tar Protective Coatings and Linings for Steel Water Pipelines - Enamel and Tape - Hot Applied, 1966 BOILING WATER REACTOR VESSEL AND INTERNALS PROJECT (BWRVIP)

BWRVIP-05, BWR RPV Shell Weld Inspection Recommendations, September 1995

B - 2 BWRVIP-18, Core Spray Internals Inspection and Flaw Evaluation Guidelines, July 1996 BWRVIP-25, BWR Core Plate Inspection and Flaw Evaluation Guidelines, October 1999 BWRVIP-26, Top Guide Inspection and Flaw Evaluation Guidelines, December 1996 BWRVIP-27, Standby Liquid Control System/Core Plate P Inspection and Flaw Evaluation Guidelines, April 1997 BWRVIP-38, Shroud Support Inspection and Flaw Evaluation Guidelines, September 1997 BWRVIP-41, BWR Jet Pump Assembly Inspection and Flaw Evaluation Guidelines, October 1997 BWRVIP-47, BWR Lower Plenum Inspection and Flaw Evaluation Guidelines, December 1997 BWRVIP-48, Vessel ID Attachment Weld Inspection and Flaw Evaluation Guidelines, March 1998 BWRVIP-49, Instrument Penetration Inspection and Flaw Evaluation Guidelines, March 1998 BWRVIP-74, BWR Reactor Pressure Vessel Inspection and Flaw Evaluation Guidelines, September 1999.

BWRVIP-75, Technical Basis for Revisions to Generic Letter 88-01 Inspection Schedules (NUREG-0313), October 1999 BWRVIP-76, BWR Core Shroud Inspection and Flaw Evaluation Guidelines, December 1999 BULLETINS (BL)

NRC BL-80-11, Masonry Wall Design, May 1980 CODE OF FEDERAL REGULATIONS 10 CFR 50.34, Contents of application; technical information, Section (a)(1) 10 CFR 50.48, Fire Protection 10 CFR 50.49, Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power Plants 10 CFR 50.55a, Codes and Standards 10 CFR 50.60, Acceptance Criteria for Fracture Prevention Measures for Light water Nuclear Power Reactors for Normal Operation

B - 3 10 CFR 50.61, Fracture Toughness Requirements for Protection Against Pressurized Thermal Shock Events 10 CFR 50.62, Requirements for Reduction of Risk from Anticipated Transients Without Scram (ATWS) Events for Light-Water-Cooled Nuclear Power Plants 10 CFR 50.63, Loss of All Alternating Current Power 10 CFR 50.65, Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants 10 CFR Part 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants 10 CFR Part 50, Appendix G, Fracture Toughness Requirements 10 CFR Part 50, Appendix H, Reactor Vessel Material Surveillance Program Requirements 10 CFR Part 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions 10 CFR Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants 10 CFR Part 100, Reactor Site Criteria ELECTRIC POWER RESEARCH INSTITUTE (EPRI)

EPRI NP-5461, Component Life Estimation: LWR Structural Materials Degradation Mechanisms, September 1987 EPRI NP-5769, Degradation and Failure of Bolting in Nuclear Power Plants, Vols. 1 and 2, Project 2520-7, 1998 EPRI NSAC/202-L, Recommendations for an Effective Flow-Accelerated Corrosion Program EPRI TR-103515, BWR Water Chemistry Guidelines, BWRVIP-29 EPRI TR-103840 BWR Containment License Renewal Industry Report; Revision 1 July 1994 EPRI TR-103842, Class I Structures Industry Report EPRI TR-104873, Methodologies and Processes to Optimize Environmental Qualification Replacement Internals, February 1996 EPRI TR-105747, Guidelines for Reinspection of BWR Core Shrouds, BWRVIP-07, February 1996

B - 4 EPRI TR-105759, An Environmental Factor Approach to Account for Reactor Water Effects in Light Water Reactor Pressure Vessel and Piping Evaluations EPRI TR-106092, Evaluation of Thermal Aging Embrittlement for Cast Austenitic Stainless Steel Components in LWR Coolant Systems, September 1997 EPRI TR-106740, BWR Core Spray Internals and Flaw Evaluation Guidelines, BWRIVP-18, July 1996 EPRI TR-107079, BWR Core Shroud Inspection and Flaw Evaluation Guidelines, Revision 2, BWRVIP-01, October 1996 EPRI TR-107285, BWR Top Guide Inspection and Flaw Evaluation Guidelines, BWRVIP-26, December 1996 EPRI TR-107286, BWR Standby Liquid Control System/Core Plate P Inspection and Flaw Evaluation Guidelines, BWRVIP-27, April 1997 EPRI TR-107396, Closed Cooling Water Chemistry Guidelines, October 1997 EPRI TR-107515, Evaluation of Thermal Fatigue Effects on Systems Requiring Aging Management Review for License Renewal for the Calvert Cliffs Nuclear Power Plant EPRI TR-107521 related to void swelling EPRI TR-107943, Environmental Fatigue Evaluations of Representative BWR Components EPRI TR-108705, BWR Vessel and Internals Project, Technical Basis for Inspection Relief for BWR Internal Components with Hydrogen Injection EPRI TR-108727, BWR Lower Plenum Inspection and Flaw Evaluation Guidelines, BWRVIP-47, December 1997 EPRI TR-108728, BWR Jet Pump Assembly Inspection and Flaw Evaluation Guidelines, BWRVIP-41, October 1997 EPRI TR-108823, BWR Shroud Support Inspection and Flaw Evaluation Guidelines, BWRVIP-38, September 1997 EPRI TR-108724, Bessel ID Attachment Weld Inspection and Flaw Evaluation Guidelines, BWRVIP-48, February 1998 EPRI TR-110356, Evaluation of Environmental Thermal Fatigue Effects on Selected Components in a Boiling Water Reactor Plant EPRI TR-112214, BWR Vessel and Internals Project, Proceedings: BWRVIP Symposium, November 12-13, 1998 EPRI TR-113596, BWR Vessel and Internals Project BWR Reactor Pressure Vessel Inspection and Flaw Evaluation Guidelines

B - 5 EPRI TR-114232, BWR Core Shroud Inspection and Flaw Evaluation Guidelines, BWRVIP-76, November 1999 EPRI TR-113596, BWR Vessel and Internals Project BWR Reactor Pressure Vessel Inspection and Flaw Evaluation Guidelines, BWRVIP-74, September 1999 EPRI TR-107396, Closed Cooling Water Chemistry Guidelines GENERIC LETTERS (GLs)

NRC GL 79-20, Information Requested on PVR Feedwater Lines NRC GL 85-20, Resolution of Generic Issue 69: High Pressure Injection/Makeup Nozzle Cracking in Babcock and Wilcox Plants, November 11,1985 NRC GL 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping, 1989 NRC GL 88-11, NRC Position on Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations NRC GL 88-14, Instrument Air Supply System Problems Affecting Safety-Related Equipment NRC GL 89-13, Service Water System Problems Affecting Safety-Related Equipment NRC GL 90-05, Guidance for Performing Temporary Non-Code Repair of ASME Code Class 1, 2, and 3 Piping, June 1990 NRC GL 91-17, Resolution of Generic Safety Issue 29: Bolting Degradation or Failure in Nuclear Power Plants, October 1991 NRC GL 92-01, Revision 1, Supplement 1, Reactor Vessel Structural Integrity, May 18, 1995 NRC GL 92-08, Thermo-Lag 330-1 Fire Barriers, December 1992 NRC GL 96-04, Boraflex Degradation in Spent Fuel Pool Storage Racks GENERIC SAFETY ISSUES (GSIs)

GSI-166, Adequacy of the Fatigue Life of Metal Components GSI-168, Environmental Qualification of Electrical Components GSI-190, Fatigue Evaluation of Metal Components for 60-year Plant Life INFORMATION NOTICES (INs)

NRC IN 87-65, Lesson Learned from Regional Inspection of Applicant Actions in Response to IE Bulletin 80-11, Masonry Wall Design

B - 6 NRC IN 91-46, Degradation of Emergency Diesel Generator Fuel Oil Deliver Systems, July 1991 NRC IN 92-20, Inadequate Local Leak Rate Testing, March 1992 INSPECTION AND AUDIT REPORTS Peach Bottom Atomic Power StationNRC Inspection Report Nos. 50-277/02-09 and 50-278/02-09, May 31, 2002 Peach Bottom Atomic Power StationNRC Inspection Report Nos. 50-277/02-10 and 50-278/02-10, September 27, 2002.

Peach Bottom Atomic Power StationNRC Inspection Report Nos. 50-277/02-12 and 50-278/02-12, January 8, 2003.

Peach Bottom License Renewal Project Position Paper LR-P-002, Systems and Structures Relied On To Demonstrate Compliance with 10 CFR 50.48, " Revision 1, Peach Bottom Atomic Power Station.

Peach Bottom License Renewal Project Position Paper LR-P-003, Systems and Structures Required for Station Blackout, Revision 0, Peach Bottom Atomic Power Station.

Peach Bottom License Renewal Project Position Paper LR-P-005, Identification of Nonsafety-Related SSCs Whose Failure Prevents Safety-Related SSCs From Fulfilling Their Safety-Related Function (Seismic II/I), Revision 0, Peach Bottom Atomic Power Station.

Peach Bottom Procedure LR-C-14, License Renewal Process, Revision 3, Peach Bottom Atomic Power Station.

Peach Bottom Procedure LR-C-14-3, License Renewal Scoping and Screening Form, Revision 3, Peach Bottom Atomic Power Station.

Peach Bottom Procedure LR-C-14-3, License Renewal SS Scoping Form: System 40 B, Reactor Building Ventilation System, Peach Bottom Atomic Power Station.

Peach Bottom Procedure LR-C-14-3, License Renewal Scoping Form: System 70, StructuresReactor Building, Peach Bottom Atomic Power Station.

Peach Bottom Procedure LR-C-14-3, License Renewal SS Scoping Form: System 70, StructuresTurbine Building and Control Room Complex, Peach Bottom Atomic Power Station.

Peach Bottom, License Renewal Component Screening Form for System 70, Structures Structural Commodities and Seals, Peach Bottom Atomic Power Station, July 26, 2001.

Peach Bottom License Renewal Project-Level Instruction (PLI) 001, System Scoping and Realignment of CRL Components, Revision 0, Peach Bottom Atomic Power Station, April 18, 2001.

B - 7 Peach Bottom License Renewal PLI-002, License Renewal Drawings, Revision 1, Peach Bottom Atomic Power Station, September 4, 2001.

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

ANS/IEEE Std. 450-1980, IEEE Recommended Practice for Maintenance, Testing, and Replacement of Large Storage Batteries for Generating Stations and Substations IEEE Std. 323-1974, Qualifying Class 1E Equipment for Nuclear Power Generating Stations, 1974 IEEE 43-1974, Recommended Practice for Testing Insulation Resistance of Rotating Machinery IEEE 95-1977, Recommended Practice for Insulation Testing of Large AC Rotating Machinery with High Direct Voltage NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA-25, "Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems" NUCLEAR ENERGY INSTITUTE NEI 95-10, Industry Guideline for Implementing the Requirements of 10 CFR Part 54The License Renewal Rule, Revision 0, March 1996 NEI 95-10, Industry Guideline for Implementing the Requirements of 10 CFR Part 54The License Renewal Rule, Revision 1, January 2000 NEI/NRC License Renewal Work Shop, Reference Documents, October 29, 1997 NUREG REPORTS NUREG-1800, Standard Review Plan for the Review of License Renewal Applications for Nuclear Power Plan July 2001 NUREG-1801, Generic Aging Lessons Learned Report, July 2001 NUREG-0588, Interim Staff Position on Environmental Qualification of Safety-Related Electrical Equipment NUREG-0612, Control of Heavy Loads at Nuclear Power Plants NUREG-0619, BWR Feedwater Nozzle and Control Rod Drive Return Line Nozzle Cracking, Resolution of Generic Technical Activity A 10, November 1980 NUREG-0737, Clarification of TMI Action Plan Requirements

B - 8 NUREG-1275, Volume 3, Operating Experience Feedback ReportService Water System Failure and Degradations NUREG-1339, Resolution of Generic Safety Issue 29: Bolting Degradation or Failure in Nuclear Power Plants, 1990 NUREG-1526, Lessons Learned from Early Implementation of Maintenance Rule at Nine Nuclear Power Plants NUREG-1568, License Renewal Demonstration Program: NRC Observations and Lessons Learned, December 1996 NUREG/CR-5704, Effects of LWR Coolant Environment on Fatigue Design Curves of Austenitic Stainless Steels, April 1999 NUREG/CR-6260, Application of NUREG/CR-5999, Interim Fatigue Curves to Selected Nuclear Power Plant Components NUREG/CR-6335, Fatigue Strain-Life Behavior of Carbon and Low-Alloy Steels, Austenitic Stainless Steels, and Alloy 600 in LRA Environments, August 1995 NUREG/CR-6384, Literature Review of Environmental Qualification of Safety-Related Electric Cables, Vol. 1, April 1996, (Brookhaven National Laboratory, Prepared for U. S. Nuclear Regulatory Commission)

NUREG/CR-6583, Effects of LWR Coolant Environments in Fatigue Design Curves of Carbon and Low-Alloy Steels REGULATORY GUIDES (RGs)

NRC RG DG 1.188, Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses NRC RG 1.154, Format and Content of Plant-Specific Pressurized Thermal Shock Safety Analysis Reports for Pressurized Water Reactors NRC RG 1.46, Revision 0, Protection Against Pipe Whip Inside Containment, withdrawn August 11, 1985 NRC RG 1.89, Rev. 1, Environmental Qualification of Certain Electrical Equipment Important to Safety for Nuclear Power Plants NRC RG1.99, Revision 2, Radiation Embrittlement of Reactor Vessel Materials, May 1988 STRUCTURAL INTEGRITY ASSOCIATES SIR-99-078, Revision A, Development of Class 1 Piping Fatigue Formulas and Fatigue Usage Estimates for the Hatch Nuclear Power Plant, Units 1 and 2, June 1999

B - 9 U.S. DEPARTMENT OF ENERGY (DOE)

SAND 93-7070.UC-523, Aging Management Guideline for Commercial Nuclear Power Plants -

Heat Exchangers (July 1984)

SAND 96-0344, Aging Management Guideline for Commercial Nuclear Power Plants -

Electrical Cables and Terminations, United States Department of Energy USA STANDARDS INSTITUTE (USAS)

ANSI USAS B31.1.0, USA Standard Code for Pressure Piping, 1968 ANSI USAS B31.7, USA Standard Code for Pressure Piping, Nuclear Power Piping, 1968 USAS B31.7, Nuclear Power Piping

C - 1 APPENDIX C PRINCIPAL CONTRIBUTORS NAME RESPONSIBILITY E. Andruszkiewcz Structural Engineering R. Architzel Plant Systems H. Ashar Structural Engineering G. Bagchi Management Oversight S. Bailey Structural Engineering R. Barrett Management Oversight W. Bateman Management Oversight L. Bell Administrative Support B. Boger Management Oversight R. Hoefing Legal Counsel W. Burton Technical Support J. Calvo Management Oversight C. Casto Management Oversight S. Chey Administrative Support D. Cullison Plant Systems B. Elliot Structural Engineering Z. Fu Chemical Engineering J. Fair Mechanical Engineering D. Frumkin Plant Systems G. Galletti Technical Support G. Georgiev Structural Engineering P. Gill Electrical Engineering J. Guo Plant Systems J. Hannon Management Oversight G. Hatchett Plant Systems M. Hartzman Structural Engineering A. Henry Technical Support R. Hoefing Legal Counsel S. Hoffman Technical Support G. Holahan Management Oversight N. Iqbal Plant Systems M. Khanna Materials Engineering A. Kiem Materials Engineering P. Kleene Technical Editing P.T. Kuo Management Oversight P. Lain Plant Systems A. Lee Mechanical Engineering J. Lehning Plant Systems C. Li Plant Systems Y. Li Mechanical Engineering J. Ma Structural Engineering K. Manoly Management Oversight J. Medoff Materials Engineering M. Mitchell Mechanical Engineering

C - 2 J. Moore Legal Counsel C. Munson Structural Engineering D. Nguyen Electrical Engineering K. Parczewski Chemical Engineering R. Pettis Reactor Systems J. Pulsipher Plant Systems T. Quay Management Oversight J. Rajan Mechanical Engineering J. Raval Plant Systems M. Razzaque Reactor Systems P. Shemanski Electrical Engineering A. Smith Chemical Engineering T. Terry Technical Support D. Thatcher Management Oversight A. Smith Materials Engineering S. Weerakkody Management Oversight A. Williamson Technical Support J. Wermiel Management Oversight CONTRACTORS Contractor Technical Area Argonne National Laboratory (ANL)

Aging Management Reviews Information Systems Laboratory (ISL)

Plant-Level Scoping Results