itri~rr rQa RCOR 6NUCLEAR REGULATORY COMMISSIO'I" NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001

kC ORM U90, .......

TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR IMMEDIATE PLACEMENT IN THE PUBLIC DOMAIN This form is to be filled out (typed orhand-printed)by the person who announcedthe meeting (i.e., the person who issued the meeting notice). The completed form, and the attachedcopy of meeting handout materials, will be sent to the Document ControlDesk on the same day of the meeting; under no circumstanceswill this be done later than the working day after the meeting.

Do not include proprietarymaterials.

DATE OF MEE7ING The attached document(s), which was/were handed out in this meeting, is/are to be placed 01/22/2003 in the public domain as soon as possible. The minutes of the meeting will be issued in the near future. Following are administrative details regarding this meeting:

Docket Number(s) 50-325 AND 50-324 Plant/Facility Name BRUNSWICK, UNITS 1 AND 2 TAC Number(s) (ifavailable) MB6692 AND MB6693 Reference Meeting Notice JANUARY 7,2003 (ML030070625)

Purpose of Meeting (copy from meeting notice) TO DISCUSS 11/12/02 AMENDMENT REQUEST FOR CORE OPERATING RANGE EXTENSION KNOWN AS MELLLA+

NAME OF PERSON WHO ISSUED MEETING NOTICE [TITLE SL. N. OLSHAN PROJECT MANAGER OFFICE NRR DIVISION DLPM BRANCH PD 11-1 Distribution of this form and attachments:

Docket File/Central File PUBLIC NRC FORM 658 (9-1999) PRINTED ON RECYCLED PAPER This form was designed using InForms

January 22, 2003

&4Progress Energy 1

Agenda I Bob Kitchen- EPU Project Manger PIntroductions P Current EPU Status o Licensing Requirements P MELLLA+ Overview

  • Mark Grantham - Superintendent EPU Design P Plant Impacts of MELLLA+
  • Tom Dresser - Lead Engineer Fuels P Core Design and Timeline Requirements
  • Mark Turkal - Lead Engineer Licensing o Interface/RAI Logistics
  • Questions/Discussion SProgress Energy 2

MELLLA+ Overview Brunswick EPU - Plant Status I9 Unit 1 - 94.3% (2755 MWt) o EPU Implemented June 1, 2002 o Implementation Testing Completed Satisfactorily o Full Uprate in March 2004 0 Unit 2 - 100% (2558 MWt - Pre-EPU RTP) o EPU Implementation in March 2003 o Expect to Achieve 2800 MWt o Full Uprate in March 2005 SProgress Energy 3

MELLLA+ Overview Licensing Submittal Status I Topic Submittal Date Needed Approval Date Impact

",T Oplo n II nt, 2),, -June26,2001- o pee..< Unit 1 tartUP",

Alternative S 3ude W"Y',,'-'"

U iiIiilU rt A,2)-, 9'*..st,l;2001 1:'i C m lt Y"'

Po .e(Ufl~tb'(Uit&2)j2 '\'""' ,,A qus di 999i 99,9 9e, i t Li (U9~),: -a Sep.9... 8, 2001. .9.9. -Unit Power (U

~

nit e L.

2}>9' " tdAugust 9, 2001 .: d

,'ompletei6, ni tntalUrtf' t29 N66 b&7 20029- ., U9 hit 2 9~~~~~~U ,,,.9 .. 9,9 i, Core,, Design-,.,9,.,9 SaetyA. MCPR!§, (Uni 1) oepember 18, 2001, Ctbmpete0 1Sta,"

99., 99 ' .9 9 *(xp49' .9.

AST

~ ~ ~ ~ '"9","~ ~ ~ ~ ~ ' Fo 9 WicindCoWdiiE

, 9 . n

&6~lProgressEnergy 4

MELLLA+ Overview I "*MELLLA+ Is an Extension of the Existing Power Flow Map

"*At Full Uprate Conditions, the Existing Flow Window Is Very Restrictive I 3.0% Unit 2 o 5.5% Unit 1 e MELLLA+ Provides Flow Window for Sustained Operation at 120% OLTP

&4 Progress Energy 5

MELLLA+ Overview Expanded Power Flow Map Core Flow (Mlb/hr) 10 20 30 40 50 60 70 80 90 0

3500 3000 2500 2000 m

1500

  • 1000 500 0

60 70 80 90 100 110 120 0 10 20 30 40 50 Core Flow (%) & Progress Energy 6

MELLLA+ Overview Advantages of MELLLA+/Confirmation Density Ie Operational Flexibility

. Fewer Required Reactivity Maneuvers

  • Resolution of Option III (THI) Issues SProgress Energy 7

MELLLA+ Overview Licensing Requirements I MELLLA+ Licensing Topical Report (NEDC-33006P) o In NRC Review e Detect & Suppress Solution - Confirmation Density LTR (NEDC-33075P) o In NRC Review

P NRC Approved

  • BNP Amendment Request o In NRC Review

&5 Progress Energy 8

Mark Grantham - Superintendent EPU Design

& Progress Energy 9

MELLLA+ Overview Areas of Minimal Impact Ie MELLLA+ Effect on Balance of Plant

) Moisture Carryover

  • Minimal Hardware Modifications i EPROM/Card Change

+ New Oscillation Power Range Monitor (OPRM)

Algorithm Progress Energy 10

MELLLA+ Overview Significant Impacts I. Moisture Carryover e Equipment Out of Service

"*ATWS Analysis

"*LOCA Analysis e Thermal-hydraulic Stability Progress Energy 11

MELLLA+ Overview Moisture Carryover "I Original Design- 0.1% Moisture

" MELLLA+ Analysis - 0.14% Moisture o Conservatively Assumes High Water Level, High Radial Peaking Factors, AND Worst Case Power/flow

"* Technical Evaluation - 0.2% Moisture

"*No Equipment Impact

"*Potential Impact o Higher Loading of Condensate Polishing Versus RWCU o Higher BOP Shutdown Doses

& Progress Energy 12

MELLLA+ Overview Equipment Out of Service

  • FW Heater Out of Service

) Not Allowed in MELLLA+ Region e Single Loop Operation and Main Steamline Valve Out of Service

) Not Allowed in MELLLA+ Region

  • Safety/Relief Valve Out of Service
  • Not Allowed in MELLLA+ Region

+ Required to Meet ATWS Overpressure Limits

  • 10% Setpoint Tolerance on One SRV Evaluated Progress Energy 13

MELLLA+ Overview ATWS Analysis I

Ie All SRVs Required to Meet ATWS

. Results Progress Energy 14

Tom Dresser - Lead Engineer Fuels

& Progress Energy 15

MELLLA+ Overview LOCA Analysis I

I. Upper Bound PCT Limit o 16000F SER Restriction Exceeded o GE Provides Unrestricted Licensing Basis

. Licensing Basis PCT Does Not Increase 5 Progress Energy 16

MELLLA+ Overview Thermal-Hydraulic Stability I* Stability Solutions Evolution o Unit 1 ElA Replaced With Option III for EPU P 10CFR21: Option III DIVOM Not Bounding o Option III Inadequate for MELLLA+

  • Confirmation Density o MELLLA+ Stability Solution o LTR Submitted August 2002 SjProgress Energy 17

MELLLA+ Overview Instability Detection - Comparison of Trips I 1.5 -

1.4 I.. ..

1.3 1.2 1.1

  • s. 4vr C, QZ 0 , , I C.I N 0.9 0

0.8 z 0.7 0.6 0.5 0 5 10 15 20 25 30 35 40 45 50 Time (see)

Earlier Suppression = Increased MCPR Margin,

  • Progress Energy 18

MELLLA+ Overview Core Design Milestones I January 2003

  • Energy Utilization Plan March 2003
  • Fuel Management Study August 2003
  • Fuel Loading Pattern September 2003
  • Decision for Reload Analysis e NRC Approval of MELLLA+ Amendment January 2004
  • Complete Reload Analysis March 2004
  • BNP Unit 1 Refuel Outage Progress Energy 19

Mark Turkal - Lead Engineer Licensing 0 Progress Energy 20

MELLLA+ Overview Review Support Ie RAI Responses < 3 Weeks

. Weekly Status Calls I Revie*w RAI Status o Update Milestone Lists P Discuss Non-RAI Actions

  • NRC Audits

Questions/Discussion

& Progress Energy 22

MELLLA+ General Information What is MELLLA+?

MELLLA+ stands for Maximum Extended Load Line Limit Analysis Plus, and is an extension of the current power-flow map. The area highlighted in the power flow map below is the MELLLA+ region, which is being added to the power-flow map by this licensing action.

Care Fow (M*b/hr) 2M 30 40 50 90 7 83o s 0 10 35W ki 9

a.

2oo b a*

103 Care now (%)

Why does BNP need MELLLA+?

BNP is currently licensed to 2923 MWt, or 120% of the original licensed thermal power. At 120% power, the currently licensed core flow window is from 99% to 104.5% (points D to F on the power-flow map above). Given the current Reactor Recirculation system, the maximum core flow that could be obtained on Unit 2 is approximately 102%. This only provides a 3% flow window (i.e. 99% to 102%) at full uprate conditions for Unit 2. Due to slightly larger core orificing, Unit 1 currently has a 5.5% flow window. These core flow windows are not adequate to maintain operation at 120% power for any significant length of time. In order to effectively deal with Xenon transients and normal power decay, a core flow band of at least 10% is needed.

Based on the currently licensed power-flow map, this 10% core flow window would only support reliable operation at approximately 115% of original licensed thermal power. In order to effectively operate at the full 120% power allowed by EPU, an extension to the power-flow map is needed to provide a larger core flow range. The MELLLA+ license submittal will provide a core flow window of approximately 18%, which will support operation at the full EPU power.

Page 1 of 3

What are the plant impacts from MELLLA+?

The impact of MELLLA+ is essentially limited to the NSSS side of the plant. The only BOP impact is a potential increase in moisture carryover in the steam leaving the vessel, which is discussed below. The impacts of MELLLA+ on plant design and operation are detailed below:

"* MELLLA+ will allow operation at higher rod lines, which will affect plant response to an ATWS event. During an ATWS, the reactor power following the Recirculation Pump Trip will be approximately 10% higher under MELLLA+ than for the current licensed condition. As a result, BNP will not be allowed to have an SRV out-of-service while operating in the MELLLA+ region.

" In addition to the SRV out-of-service change, Single Loop Operation, MSIV Out-of Service, FW Heater Out-of-Service, and Final Feedwater Temperature Reduction will not be allowed while operating in the MELLLA+ region. If plant/equipment issues dictate operation under any of these out-of-service conditions, the plant will have to exit the MELLLA+ region.

" The Recirculation System runback associated with a single Reactor feed water pump trip will result in a greater demand on the operating FW pump. This is due to operation at higher rod lines while in the MELLLA+ region. The new FW pumps, being installed as part of EPU, will support single FW pump operation at approximately 84% of uprated power, which is adequate for scram avoidance under the single FW pump trip scenario.

This represents an actual improvement in FW pump margin over what is currently available today.

"* LOCA analyses are normally performed at rated conditions (rated flow and power). For MiELLLA+, a sensitivity review at the lower core flows was performed which identified that the Upper Bound Peak Clad Temperature (PCT) would be higher than the NRC SER acceptance limit of 1600 'F for the SAFER-GESTAR code. As a result, the MELLLA+

licensing submittal is taking advantage of a GE licensing topic report which eliminates the 1600 TF Upper Bound PCT limit. The GE topical for elimination of the 1600 TF limit has been approved by the NRC, and will provide significant future benefit (e.g. analysis error evaluations) to BNP.

" Operation in the MELLLA+ region results in greater subcooling at the core inlet which has a negative impact on thermal hydraulic stability. As a result, a new stability solution is required. A new stability solution has been developed by GE and is being licensed as part of the MELLLA+ submittal. This stability solution is Detect and Suppress Solution

- Confirmation Density (DSS-CD). The DSS-CD solution uses the same hardware as the existing Option mII solution, but will require an E-PROM/card change to support the new algorithm. The DSS-CD solution detects the inception of power oscillations and generates an early power suppression trip (scram), whereas, the existing Option mI solution generates a suppression trip based on oscillations AND a specific oscillation amplitude.

Page 2 of 3

BNP was originally designed for a moisture carryover of up to 0.1%. The MELLLA+

analysis predicts that under the extreme conditions of high reactor water level (at alarm point), high radial peaking factor, AND the 85% rated core flow, the moisture carryover could approach 0.14%. An analysis was performed as part of MELLLA+ which demonstrates moisture values up to 0.2% are acceptable. The only impact of higher moisture carryover is the increased transport of fission products to the BOP side of the plant. This would result in a minor change in the percentage of fission products processed by RWCU and the Condensate filters/demineralizers (RWCU percentage goes down while Condensate goes up). Since operating dose rates in the BOP systems are dominated by N-16, there is not expected to be any increase in the normal operation dose levels as a result of MELLLA+. Shutdown doses could potentially be higher in some BOP systems. Due to the combination of extreme conditions required to achieve the highest predicted moisture carryover levels, the overall impact on the plant is expected to be minimal.

What modifications are required for MELLLA+?

There are no significant hardware modifications required for the implementation of MELLLA+.

The only required change is an E-PROM/card change in the PRNM system to support the DSS CD stability solution algorithm.

Page 3 of 3