IR 05000361-02-013, IR 05000362-02-013; 10/07-11/2/2002; Southern California Edison, San Onofre Nuclear Generating Station, Units 2 &3; Ti 2515/148. Verification of Compliance with Interim Compensatory Measures Order
ML023570491
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 12/20/2002
From: Troy Pruett
Plant Support Branch Region IV
To: Ray H
Southern California Edison Co
References
IR-02-013
Download: ML023570491 (7)


See also: IR 05000361/2002013

Text

December 20, 2002

Harold B. Ray, Executive Vice President

Southern California Edison Co.

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, California 92674-0128

SUBJECT: NRC SAFEGUARDS INSPECTION OF COMPLIANCE WITH ORDER

INSPECTION REPORT 50-361/02-013; 50-362/02-013

Dear Mr. Ray:

On October 11, 2002, the NRC completed an inspection at your San Onofre Nuclear

Generating Station, Units 2 and 3, facility. The enclosed report documents the inspection

findings which were discussed on October 11, 2002, with Mr. Dwight Nunn and other members

of your staff.

This inspection examined activities conducted under your license as they relate to safety and

compliance with an Order issued on February 25, 2002, which required your site to implement

specific measures related to security of your facility. The inspection utilized Temporary

Instruction 2515/148, Inspection of Nuclear Reactor Safeguards Interim Compensatory

Measures, to verify implementation of the Order as clarified in your responses dated

March 18, 2002, and May 14, 2002. Within these areas, the inspection consisted of selected

examination of procedures and representative records, observations of activities, and interviews

with personnel.

As discussed during the inspection and at the exit meeting, the Federal Bureau of Investigation

provides the primary law enforcement interface for San Onofre Nuclear Generating Station.

Although the Federal Bureau of Investigation is the local law enforcement agency of record, the

licensee had established additional verbal agreements with the Orange and San Diego County

Sheriff departments and other members of the Critical Incident Response Group. The

agreements are not formalized since a federal agency is responsible.

DOCUMENT CONTAINS ENCLOSURE(S) CONTAIN(S)

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION

UPON SEPARATION THIS

PAGE IS DECONTROLLED

Southern California Edison Co. -2-

The material enclosed herewith contains Safeguards Information as defined by 10 CFR 73.21

and its disclosure to unauthorized individuals is prohibited by Section 147 of the Atomic Energy

Act of 1954, as amended. Therefore, the material will not be placed in the Public Document

Room.

In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter, its

enclosure, and your response will be made available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this inspection, we will be pleased to discuss them

with you.

Sincerely,

//RA//

Troy W. Pruett, Chief

Plant Support Branch

Division of Reactor Safety

Dockets: 50-361

50-362

Licenses: NPF-10

NPF-15

Enclosure:

NRC Inspection Report

50-361/02-013; 50-362/02-013

cc Without safeguards enclosures:

Chairman, Board of Supervisors

County of San Diego

1600 Pacific Highway, Room 335

San Diego, California 92101

Gary L. Nolff

Power Projects/Contracts Manager

Riverside Public Utilities

2911 Adams Street

Riverside, California 92504

DOCUMENT CONTAINS ENCLOSURE(S) CONTAIN(S)

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION

UPON SEPARATION THIS

PAGE IS DECONTROLLED

Southern California Edison Co. -3-

Eileen M. Teichert, Esq.

Supervising Deputy City Attorney

City of Riverside

3900 Main Street

Riverside, California 92522

Joseph J. Wambold, Vice President

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, California 92674-0128

Dr. Raymond Waldo, Plant Manager,

Nuclear Generation

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, California 92674-0128

David Spath, Chief

Division of Drinking Water and

Environmental Management

P.O. Box 942732

Sacramento, California 94234-7320

Michael R. Olson

San Onofre Liaison

San Diego Gas & Electric Company

P.O. Box 1831

San Diego, California 92112-4150

Ed Bailey, Radiation Control Program Director

Radiologic Health Branch

State Department of Health Services

P.O. Box 942732 (MS 178)

Sacramento, California 94234-7320

Steve Hsu

Radiologic Health Branch

State Department of Health Services

P.O. Box 942732

Sacramento, California 94327-7320

DOCUMENT CONTAINS ENCLOSURE(S) CONTAIN(S)

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION

UPON SEPARATION THIS

PAGE IS DECONTROLLED

Southern California Edison Co. -4-

Mayor

City of San Clemente

100 Avenida Presidio

San Clemente, California 92672

Robert A. Laurie, Commissioner

California Energy Commission

1516 Ninth Street (MS 31)

Sacramento, California 95814

Douglas K. Porter, Esq.

Southern California Edison Company

2244 Walnut Grove Avenue

Rosemead, California 91770

Dwight E. Nunn, Vice President

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, California 92674-0128

A. Edward Scherer, Manager, Nuclear

Oversight and Regulatory Affairs

Southern California Edison

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, California 92674-0128

Technical Services Branch Chief

FEMA Region IX

1111 Broadway, Suite 1200

Oakland, California 94607-4052

DOCUMENT CONTAINS ENCLOSURE(S) CONTAIN(S)

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION

UPON SEPARATION THIS

PAGE IS DECONTROLLED

Southern California Edison Co. -5-

cc with safeguards enclosure:

Vonna Ordaz (NRR/NSIR/DNS/RSPS) (MS 4A8)

Alan Madison (NRR/NSIR/DNS/RSOS) (MS 06H-02)

Elaine McNeil (NRR/NRIR/DNS/RSPS) (MS 06H-02)

RIV Docket File - File Room Custodian

Security Inspector (Pick)

Electronic distribution by RIV without safeguards enclosure:

Regional Administrator (EWM)

DRP Director (ATH)

DRS Director (DDC)

Senior Resident Inspector (CCO1)

Branch Chief, DRP/C (CEJ1)

Senior Project Engineer, DRP/C (WCW)

Staff Chief, DRP/TSS (PHH)

RITS Coordinator (NBH)

Scott Morris (SAM1)

SONGS Site Secretary (SFN1)

Dale Thatcher (DFT)

W. A. Maier, RSLO (WAM)

DOCUMENT: R:\SO2002-013gapSGI.wpd

RIV:PSB PSB C:PBS NRR/NSIR DRP/C

  • GAPick:jlh *TLKlug TWPruett GMTracy CEJohnson

/RA/ /RA/ via T WCWalker for

11/ 13 /02 11/ 13 /02 11/26 /02 12/13 /02 12/13 /02

D/DRS C:PSB

DDChamberlain TWPruett

/RA/ /RA/

12/19 /02 12/ 19 /02

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

  • Previously concurred

DOCUMENT CONTAINS ENCLOSURE(S) CONTAIN(S)

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION

UPON SEPARATION THIS

PAGE IS DECONTROLLED

Southern California Edison Co.

DOCUMENT CONTAINS ENCLOSURE(S) CONTAIN(S)

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION

UPON SEPARATION THIS

PAGE IS DECONTROLLED