Special Report 1-SR-2002-002
ML023090325
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 10/29/2002
From: Ide W
Arizona Public Service Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
192-01111-WEI/TNW/DFH
Download: ML023090325 (3)


Text

LAMS Technical Specification 5.6.8 William E. Ide Mail Station 7602 Palo Verde Nuclear Vice President TEL (623) 393-6116 P.O. Box 52034 Generating Station Nuclear Production FAX (623) 393-6077 Phoenix, AZ 85072-2034 192-01111 -WEI/TNW/DFH October 29, 2002 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-37 Washington, D.C. 20555-0001

Dear Sirs:

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Unit 1 Docket No. STN 50-528 Special Report 1-SR-2002-002 Attached please find Special Report 1-SR-2002-002 prepared and submitted pursuant to Technical Specifications (TS) Reporting Requirement 5.6.8. This report discusses steam generator tube plugging in Unit 1. Pursuant to Technical Specification 5.6.8, the complete results of the steam generator tube inservice inspection will be submitted by October 21, 2003. Copies of the Special Report are being forwarded to the Regional Administrator, NRC Region IV and the PVNGS Resident Inspector.

No commitments are being made to the NRC by this letter.

If you have any questions, please contact Thomas N. Weber at (623) 393-5764.

Sincerely, WEI/TNW/DFH/Eg

/

/'..

Attachment cc:

E. W. Merschoff (all with attachment)

J. N. Donohew M. B. Fields N. L. Salgado A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway 9 Comanche Peak 0 Diablo Canyon 0 Palo Verde 9 South Texas Project

  • Wolf Creek A041

Attachment Special Report No. 1-SR-2002-002

Palo Verde Nuclear Generating Station Unit I Steam Generator Tube Plugging Docket No. STN 50-528 Special Report No. I-SR-2002-002 This Special Report is being provided pursuant to Palo Verde Unit 1 Technical Specifications (TS) Reporting Requirement 5.6.8 to report the number of steam generator tubes plugged and/or repaired as a result of inservice inspection activities.

On October 21, 2002, Unit I was defueled during a refueling outage when an inservice inspection of both steam generators was completed. The inspection resulted in the plugging of 236 tubes in Steam Generator No. 1 and 234 tubes in Steam Generator No.

2.

Pursuant to Technical Specification 5.6.8, the complete results of the steam generator tube inservice inspection will be submitted by October 21, 2003.

  • P