Technical Specificaton Pages for River Bend, for Amendment 125, for License NPF- 47
ML022700441
Person / Time
Site: River Bend Entergy icon.png
Issue date: 09/25/2002
From: Michael Webb
NRC/NRR/DLPM/LPD4
To:
References
TAC MB3041
Download: ML022700441 (2)


Text

AC Sources-Operating 3.8.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A.

(continued)

A.2 Restore required offsite 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> circuit to OPERABLE status.

AND 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> from discovery of two divisions with no offsite power AND 17 days from discovery of failure to meet LCO B.

One required DG B.1 Perform SR 3.8.1.1 for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable.

OPERABLE required offsite circuit(s).

AND Once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter AND B.2 Declare required 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> from discovery feature(s), supported by of Condition B the inoperable DG, concurrent with inoperable when the inoperability of redundant required redundant required feature(s) are feature(s) inoperable.

AND (continued)

Amendment No.94-125 I

RIVER BEND 3.8-2

AC Sources-Operating 3.8.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME B.

(continued)

B.3.1 Determine OPERABLE 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> DG(s) are not inoperable due to common cause failure.

OR B.3.2 Perform SR 3.8.1.2 for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> OPERABLE DG(s).

AND B.4 Restore required DG to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from OPERABLE status.

discovery of an inoperable Division III DG AND 14 days AND 17 days from discovery of failure to meet LCO C.

Two required offsite circuits C.1 Declare required 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> from inoperable, feature(s) inoperable discovery of when the redundant Condition C required feature(s) are concurrent with inoperable.

inoperability of redundant required feature(s)

AND 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> C.2 Restore one required offsite circuit to OPERABLE status.

(continued)

Amendment No. 84 125 I

RIVER BEND 3.8-3