ML022610102
| ML022610102 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 09/17/2002 |
| From: | NRC/NRR/DLPM/LPD3 |
| To: | |
| Shared Package | |
| ML022610687 | List: |
| References | |
| TAC MA9694 | |
| Download: ML022610102 (4) | |
Text
EMERGENCY CORE COOLING SYSTEMS ECCS SUBSYSTEMS - T..
280F LIMITING CONDITION FOR OPERATION 3.5.2 Two independent ECCS subsystems shall be OPERABLE with each subsystem comprised of:
- c.
One OPERABLE decay heat cooler, and
- d. An OPERABLE flow path capable of taking suction from the borated water storage tank (BWST) on a safety injection signal and manually transferring suction to the containment sump during the recirculation phase of operation.
APPLICABILITY: MODES 1, 2 and 3.
ACTION:
- a. With one HPI train inoperable, restore the inoperable HPI train to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
- b. With one LPI train or its associated decay heat cooler inoperable, restore the inoperable equipment to OPERABLE status within 7 days or be in HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
- c.
In the event the ECCS is actuated and injects water into the Reactor Coolant System, a Special Report shall be prepared and submitted to the Commission pursuant to Specification 6.9.2 within 90 days describing the circumstances of the actuation and the total accumulated actuation cycles to date.
SURVEILLANCE REQUIREMENTS 4.5.2 Each ECCS subsystem shall be demonstrated OPERABLE:
- a.
At least once per 31 days by verifying that each valve (manual, power operated or automatic) in the flow path that is not locked, sealed or otherwise secured in position, is in its correct position.
Amendment No. 36,182, 253 DAVIS-BESSE, UNIT I 3/4 5-3
CONTAINMENT SYSTEMS 3/4.6.2 DEPRESSURIZATION AND COOLING SYSTEMS CONTAINMENT SPRAY SYSTEM LIMITING CONDITION FOR OPERATION 3.6.2.1 Two independent containment spray systems shall be OPERABLE with each spray system capable of taking suction from the BWST on a containment spray actuation signal and manually transferring suction to the containment emergency sump during the recirculation phase of operation.
APPLICABILITY: MODES 1, 2,3 and 4.
ACTION:
With one containment spray system inoperable, restore the inoperable spray system to OPERABLE status within 7 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />; restore the inoperable spray system to OPERABLE status within the next 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> or be in COLD SHUTDOWN within the next 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
SURVEILLANCE REQUIREMENTS 4.6.2.1 Each containment spray system shall be demonstrated OPERABLE:
- a. At least once per 31 days by verifying that each valve (manual, power operated or automatic) in the flow path that is not locked, sealed or otherwise secured in position, is in its correct position.
- b. At least once each REFUELING INTERVAL, by:
- 1. Verifying that each automatic valve in the flow path actuates to its correct position on a containment spray test signal.
- 2. Verifying that each spray pump starts automatically on a SFAS test signal.
Amendment No. 36, 213, 253 DAVIS-BESSE, UNIT I 3/4 6-11
3/4.5 EMERGENCY CORE COOLING SYSTEMS (ECCS)
BASES 3/4.5.1 CORE FLOODING TANKS The OPERABILITY of each core flooding tank ensures that a sufficient volume of borated water will be immediately forced into the reactor vessel in the event the RCS pressure falls below the pressure of the tanks. This initial surge of water into the vessel provides the initial cooling mechanism during large RCS pipe ruptures.
The limits on volume, boron concentration and pressure ensure that the assumptions used for core flooding tank injection in the safety analysis are met.
The tank power operated isolation valves are considered to be "operating bypasses" in the context of IEEE Std. 279-1971, which requires that bypasses of a protective function be removed automatically whenever permissive conditions are not met. In addition, as these tank isolation valves fail to meet single failure criteria, removal of power to the valves is required.
The one hour limit for operation with a core flooding tank (CFT) inoperable for reasons other than boron concentration not within limits minimizes the time the plant is exposed to a possible LOCA event occurring with failure of a CFT, which may result in unacceptable peak cladding temperatures.
With boron concentration for one CFT not within limits, the condition must be corrected within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> limit was developed considering that the effects of reduced boron concentration on core subcriticality during reflood are minor. Boiling of the ECCS water in the core during reflood concentrates the boron in the saturated liquid that remains in the core. In addition, the volume of the CFTs is still available for injection. Since the boron requirements are based on the average boron concentration of the total volume of both CFTs, the consequences are less severe than they would be if the contents of a CFT were not available for injection.
The completion times to bring the plant to a MODE in which the Limiting Condition for Operation (LCO) does not apply are reasonable based on operating experience. The completion times allow plant conditions to be changed in an orderly manner and without challenging plant systems.
CFT boron concentration sampling within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> after an 80 gallon volume increase will identify whether inleakage from the RCS has caused a reduction in boron concentration to below the required limit. It is not necessary to verify boron concentration if the added water inventory is from the borated water storage tank (BWST), because the water contained in the BWST is within CFT boron concentration requirements.
3/4.5.2 and 3/4.5.3 ECCS SUBSYSTEMS The operability of two independent ECCS subsystems with RCS average temperature
> 280'F ensures that sufficient emergency core cooling capability will be available in the event of a LOCA assuming the loss of one subsystem through any single failure consideration. Each ECCS subsystem consists of one High Pressure Injection (HPI) train, one Low Pressure Injection (LPI) train (including the associated decay heat cooler), and the necessary piping, valves, instrumentation and controls to provide the required flowpaths from the Borated Water Storage AmendmentNo. 20, 191, 253 DAVIS-BESSE, UNIT I B 3/4 5-1
4 3/4.5 EMERGENCY CORE COOLING SYSTEMS (ECCS)
BASES (Continued)
Tank (BWST) or the Containment Emergency Sump to the reactor vessel. Either subsystem operating in conjunction with the core flooding tanks is capable of supplying sufficient core cooling to maintain the peak cladding temperatures within acceptable limits for all postulated break sizes ranging from the double ended break of the largest RCS cold leg pipe downward.
With RCS average temperature Ž_ 2801F, the Limiting Condition for Operation (LCO) requires the OPERABILITY of a number of independent trains, the inoperability of one component in a train does not necessarily render the ECCS incapable of performing its function. Neither does the inoperability of two different components, each in a different train, necessarily result in a loss of function for the ECCS. The intent of this LCO is to maintain a combination of equipment such that 100% of the safety injection flow equivalent to 100% of a single subsystem remains available. This allows increased flexibility in plant operations under circumstances when components in opposite subsystems are inoperable.
With one or more components inoperable such that 100% of the flow equivalent to a single OPERABLE ECCS subsystem is not available, the facility is in a condition outside the accident analyses. Therefore, LCO 3.0.3 must be immediately entered.
In addition, each ECCS subsystem provides long term core cooling capability in the recirculation mode during the accident recovery period.
Amendment No. 20, 191, 253 1
DAVIS-BESSE, UNIT I B 3/4 5-1 a