Category:License-Application for (Amend/Renewal/New) for DKT 30
MONTHYEARRS-21-063, Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2021-06-30030 June 2021 Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RS-20-016, County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems2020-04-13013 April 2020 County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems RS-19-022, License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs)2019-03-0101 March 2019 License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs) RS-02-152, . Request for Technical Specifications Surveillance Requirement 3.3.4.1.2 Change Related to Anticipated Transient Without Scram- Recirculation Pump Trip Instrumentation2002-08-22022 August 2002 . Request for Technical Specifications Surveillance Requirement 3.3.4.1.2 Change Related to Anticipated Transient Without Scram- Recirculation Pump Trip Instrumentation 2021-06-30
[Table view] Category:40
MONTHYEARML23090A1702023-03-29029 March 2023 Midamerican Nuclear Energy Co., Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(l), Including ISFSI Decommissioning Funding (10 CFR 72.30) RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-21-063, Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2021-06-30030 June 2021 Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements ML21091A0362021-03-30030 March 2021 Midamerican Energy Company, Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1), Including ISFSI Decommissioning Funding (10 CFR 72.30) RS-21-032, Amended Decommissioning Trust Agreements2021-02-25025 February 2021 Amended Decommissioning Trust Agreements RS-21-030, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2021-02-24024 February 2021 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations NMP1L3371, Summary of Changes, Quality Assurance Topical Report, NO-AA-10 & Decommissioning Quality Assurance Program, NO-DC-102021-02-10010 February 2021 Summary of Changes, Quality Assurance Topical Report, NO-AA-10 & Decommissioning Quality Assurance Program, NO-DC-10 RS-20-016, County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems2020-04-13013 April 2020 County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems RS-19-045, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2019-04-0101 April 2019 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML19091A0572019-03-28028 March 2019 Midamerican Energy Company Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1), Including ISFSI Decommissioning Funding (10 CFR 72.30) RS-19-022, License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs)2019-03-0101 March 2019 License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs) RS-15-094, (EGC) - Submittal of Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2015-03-31031 March 2015 (EGC) - Submittal of Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML15090A1152015-03-27027 March 2015 Midamerican Energy Co., Submittal of Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1), Including ISFSI Decommissioning Funding (10 CFR 72.30) ML14314A0702014-11-0606 November 2014 Proposed Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Plan for Quad Cities Nuclear Power Station RS-13-106, (EGC) Amended 2011 Report on Status of Decommissioning Funding for Reactors and Correction to July 27, 2011 RAI Response2013-04-12012 April 2013 (EGC) Amended 2011 Report on Status of Decommissioning Funding for Reactors and Correction to July 27, 2011 RAI Response RS-13-100, Report on Status of Decommissioning Funding for Reactors2013-04-0101 April 2013 Report on Status of Decommissioning Funding for Reactors ML13091A0112013-03-27027 March 2013 Midamerican Energy Company'S Decommissioning Funding Status Report for Their Twenty-Five Percent Share of Quad Cities, Units 1 and 2, Pursuant to 10 CFR 50.75(f)(1) RS-09-041, Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC2009-03-31031 March 2009 Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC ML0909106132009-03-30030 March 2009 Submittal of Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1) ML0309100242003-03-28028 March 2003 Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1) RS-02-152, . Request for Technical Specifications Surveillance Requirement 3.3.4.1.2 Change Related to Anticipated Transient Without Scram- Recirculation Pump Trip Instrumentation2002-08-22022 August 2002 . Request for Technical Specifications Surveillance Requirement 3.3.4.1.2 Change Related to Anticipated Transient Without Scram- Recirculation Pump Trip Instrumentation 2023-03-29
[Table view] Category:70
MONTHYEARML23090A1702023-03-29029 March 2023 Midamerican Nuclear Energy Co., Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(l), Including ISFSI Decommissioning Funding (10 CFR 72.30) RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-21-063, Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2021-06-30030 June 2021 Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements ML21091A0362021-03-30030 March 2021 Midamerican Energy Company, Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1), Including ISFSI Decommissioning Funding (10 CFR 72.30) RS-21-032, Amended Decommissioning Trust Agreements2021-02-25025 February 2021 Amended Decommissioning Trust Agreements RS-21-030, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2021-02-24024 February 2021 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations NMP1L3371, Summary of Changes, Quality Assurance Topical Report, NO-AA-10 & Decommissioning Quality Assurance Program, NO-DC-102021-02-10010 February 2021 Summary of Changes, Quality Assurance Topical Report, NO-AA-10 & Decommissioning Quality Assurance Program, NO-DC-10 RS-20-016, County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems2020-04-13013 April 2020 County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems RS-19-045, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2019-04-0101 April 2019 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML19091A0572019-03-28028 March 2019 Midamerican Energy Company Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1), Including ISFSI Decommissioning Funding (10 CFR 72.30) RS-19-022, License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs)2019-03-0101 March 2019 License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs) RS-15-094, (EGC) - Submittal of Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2015-03-31031 March 2015 (EGC) - Submittal of Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML15090A1152015-03-27027 March 2015 Midamerican Energy Co., Submittal of Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1), Including ISFSI Decommissioning Funding (10 CFR 72.30) ML14314A0702014-11-0606 November 2014 Proposed Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Plan for Quad Cities Nuclear Power Station RS-13-106, (EGC) Amended 2011 Report on Status of Decommissioning Funding for Reactors and Correction to July 27, 2011 RAI Response2013-04-12012 April 2013 (EGC) Amended 2011 Report on Status of Decommissioning Funding for Reactors and Correction to July 27, 2011 RAI Response RS-13-100, Report on Status of Decommissioning Funding for Reactors2013-04-0101 April 2013 Report on Status of Decommissioning Funding for Reactors ML13091A0112013-03-27027 March 2013 Midamerican Energy Company'S Decommissioning Funding Status Report for Their Twenty-Five Percent Share of Quad Cities, Units 1 and 2, Pursuant to 10 CFR 50.75(f)(1) RS-09-041, Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC2009-03-31031 March 2009 Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC ML0909106132009-03-30030 March 2009 Submittal of Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1) ML0309100242003-03-28028 March 2003 Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1) RS-02-152, . Request for Technical Specifications Surveillance Requirement 3.3.4.1.2 Change Related to Anticipated Transient Without Scram- Recirculation Pump Trip Instrumentation2002-08-22022 August 2002 . Request for Technical Specifications Surveillance Requirement 3.3.4.1.2 Change Related to Anticipated Transient Without Scram- Recirculation Pump Trip Instrumentation 2023-03-29
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARRS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2023-06-0808 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors RS-23-059, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0808 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-23-007, Application to Adopt TSTF-564, Safety Limit MCPR2023-03-0303 March 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-032, Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location2023-02-0303 February 2023 Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration RS-22-004, Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2022-01-0404 January 2022 Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements ML21277A1932021-11-16016 November 2021 Enclosure 2, Draft Conforming License Amendments RS-21-108, Application to Revise Technical Specification 3.1.4, Control Rod Scam Times2021-11-16016 November 2021 Application to Revise Technical Specification 3.1.4, Control Rod Scam Times RS-21-065, License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies with Proposed Change to Technical Specifications Section 4.3.12021-10-25025 October 2021 License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies with Proposed Change to Technical Specifications Section 4.3.1 JAFP-21-0089, Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2021-09-27027 September 2021 Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21257A4202021-09-14014 September 2021 Request for Licensing Amendment Regarding Transition to GNF3 Fuel RS-21-039, Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments2021-03-25025 March 2021 Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments ML21057A2732021-02-25025 February 2021 Application for Order Approving License Transfers and Proposed Conforming License Amendments RS-20-115, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2020-11-18018 November 2020 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements RS-20-031, License Amendment Request - Application to Adopt Technical Specification Task Force (TSTF) Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2 .5 and TS 3.6 .3.2, Using the Consolidated Line Item Improvement Process2020-04-30030 April 2020 License Amendment Request - Application to Adopt Technical Specification Task Force (TSTF) Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2 .5 and TS 3.6 .3.2, Using the Consolidated Line Item Improvement Process RS-20-046, Emergency License Amendment Request - Increase Technical Specifications Allowable MSIV Leakage Rates in TS 3.6.1.32020-04-0101 April 2020 Emergency License Amendment Request - Increase Technical Specifications Allowable MSIV Leakage Rates in TS 3.6.1.3 RS-19-044, License Amendment Request - Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions2019-08-28028 August 2019 License Amendment Request - Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions RS-19-069, License Amendment Request Supporting Emergency Plan Emergency Action Level Change (EAL RAL3)2019-08-23023 August 2019 License Amendment Request Supporting Emergency Plan Emergency Action Level Change (EAL RAL3) JAFP-19-0067, Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability2019-06-27027 June 2019 Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability RS-19-040, Application to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2019-06-25025 June 2019 Application to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML19036A5862019-03-21021 March 2019 Issuance of Amendments to Revise the Emergency Response Organization Staffing Requirements RS-18-134, Request to Revise Technical Specifications 2.1.1 for Minimum Critical Power Ratio Safety Limits2018-12-0505 December 2018 Request to Revise Technical Specifications 2.1.1 for Minimum Critical Power Ratio Safety Limits RS-18-130, Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO2018-11-0101 November 2018 Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO RS-18-020, Application to Revise Technical Specifications to Modify the APRM Channel Adjustment Surveillance Requirement2018-06-15015 June 2018 Application to Revise Technical Specifications to Modify the APRM Channel Adjustment Surveillance Requirement RS-18-032, Application to Adopt TSTF-372, Addition of LCO 3.0.8, Inoperability of Snubbers2018-04-25025 April 2018 Application to Adopt TSTF-372, Addition of LCO 3.0.8, Inoperability of Snubbers RS-17-161, Fleet License Amendment Request to Relocate Technical Specification Unit/Facility/Plant Staff Qualification ANSI N18.1-1971 and ANSl/ANS-3.1-1978 Requirements to the Exelon Quality Assurance Topical Report (QATR)2018-03-0101 March 2018 Fleet License Amendment Request to Relocate Technical Specification Unit/Facility/Plant Staff Qualification ANSI N18.1-1971 and ANSl/ANS-3.1-1978 Requirements to the Exelon Quality Assurance Topical Report (QATR) RS-18-006, Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control.2018-02-26026 February 2018 Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control. ML18053A1902018-01-31031 January 2018 Enclosure 9 - Information Related to Review of Proposed Changes by the State ML18053A1852018-01-31031 January 2018 Enclosure 6 - Quad Cities - Evaluation of Proposed Changes ML18053A1782018-01-31031 January 2018 Attachment 6B - Quad Cities Clean Emergency Plan EP-AA-1000 Pages ML18053A1772018-01-31031 January 2018 Attachment 6A - Quad Cities - Marked-up Emergency Plan EP-AA-1000 Pages RS-18-021, License Amendment Request for Approval of Changes to Emergency Plan EP-AA-1000 Staffing Requirements2018-01-31031 January 2018 License Amendment Request for Approval of Changes to Emergency Plan EP-AA-1000 Staffing Requirements RS-18-021, Exelon Generation Co, LLC - License Amendment Request for Approval of Changes to Emergency Plan EP-AA-1000 Staffing Requirements2018-01-31031 January 2018 Exelon Generation Co, LLC - License Amendment Request for Approval of Changes to Emergency Plan EP-AA-1000 Staffing Requirements RS-17-137, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2017-11-0808 November 2017 Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements RS-17-051, Request for License Amendment to Revise Technical Specifications Section 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2017-04-27027 April 2017 Request for License Amendment to Revise Technical Specifications Section 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies RS-17-049, Application to Revise Technical Specifications to Adopt TSTF-529 Clarify Use and Application Rules, Revision 4, Using the Consolidated Line Item Improvement Process2017-03-28028 March 2017 Application to Revise Technical Specifications to Adopt TSTF-529 Clarify Use and Application Rules, Revision 4, Using the Consolidated Line Item Improvement Process RS-16-201, Quad Cities Nuclear Power Station, Units 1 and 2 - License Amendment Request- Proposed Changes to Technical Specifications Section 5.0 Administrative Controls for Permanently Defueled Condition2016-10-20020 October 2016 Quad Cities Nuclear Power Station, Units 1 and 2 - License Amendment Request- Proposed Changes to Technical Specifications Section 5.0 Administrative Controls for Permanently Defueled Condition RS-16-201, License Amendment Request- Proposed Changes to Technical Specifications Section 5.0 Administrative Controls for Permanently Defueled Condition2016-10-20020 October 2016 License Amendment Request- Proposed Changes to Technical Specifications Section 5.0 Administrative Controls for Permanently Defueled Condition ML16280A4022016-10-0606 October 2016 License Amendment Request - Supplement Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing. RS-16-199, Supplement to Request for License Amendment Regarding Transition to Areva Fuel2016-09-28028 September 2016 Supplement to Request for License Amendment Regarding Transition to Areva Fuel RS-16-187, Request for License Amendment to Revise Technical Specifications Section 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2016-09-19019 September 2016 Request for License Amendment to Revise Technical Specifications Section 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies RS-16-162, Request for License Amendment to Revise Loss of Voltage Relay Settings2016-09-12012 September 2016 Request for License Amendment to Revise Loss of Voltage Relay Settings ML16209A2182016-07-26026 July 2016 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Lnservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing. RS-16-105, Supplemental Information in Support of Request for License Amendment Regarding Transition to Areva Fuel2016-04-26026 April 2016 Supplemental Information in Support of Request for License Amendment Regarding Transition to Areva Fuel RS-16-035, County, and Quad Cities - Request for License Amendment to Address Secondary Containment Access Openings2016-02-0303 February 2016 County, and Quad Cities - Request for License Amendment to Address Secondary Containment Access Openings RS-16-016, Supplement to Request for License Amendment Regarding Transition to Areva Fuel2016-01-20020 January 2016 Supplement to Request for License Amendment Regarding Transition to Areva Fuel RS-15-326, Request for License Amendment Regarding Spent Fuel Storage Pool Criticality Methodology for Fuel Channel Bow/Bulge2015-12-14014 December 2015 Request for License Amendment Regarding Spent Fuel Storage Pool Criticality Methodology for Fuel Channel Bow/Bulge ML16258A1522015-11-20020 November 2015 Design Analysis QDC-6700-E-0939, Loss of Voltage Relay Set Point for Buses 13-1, 14-1, 23-1, and 24-1, Revision 001 2023-06-08
[Table view] Category:Technical Specification
MONTHYEARRS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-23-007, Application to Adopt TSTF-564, Safety Limit MCPR2023-03-0303 March 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-032, Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location2023-02-0303 February 2023 Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML21300A3392021-10-21021 October 2021 Revised Technical Specification Bases RS-20-115, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2020-11-18018 November 2020 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements JAFP-20-0049, Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability2020-06-22022 June 2020 Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability RS-20-046, Emergency License Amendment Request - Increase Technical Specifications Allowable MSIV Leakage Rates in TS 3.6.1.32020-04-0101 April 2020 Emergency License Amendment Request - Increase Technical Specifications Allowable MSIV Leakage Rates in TS 3.6.1.3 JAFP-19-0067, Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability2019-06-27027 June 2019 Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability RS-19-039, Fleet License Amendment Request - Common Language for Technical Specification High Radiation Area Administrative Controls2019-06-26026 June 2019 Fleet License Amendment Request - Common Language for Technical Specification High Radiation Area Administrative Controls RS-19-023, Application to Increase Technical Specifications Allowable MSIV Leakage Rates and Revise Secondary Containment Surveillance Requirement 3.6.4.1.12019-03-0505 March 2019 Application to Increase Technical Specifications Allowable MSIV Leakage Rates and Revise Secondary Containment Surveillance Requirement 3.6.4.1.1 RS-18-134, Request to Revise Technical Specifications 2.1.1 for Minimum Critical Power Ratio Safety Limits2018-12-0505 December 2018 Request to Revise Technical Specifications 2.1.1 for Minimum Critical Power Ratio Safety Limits RS-17-126, Technical Specification Bases2017-10-19019 October 2017 Technical Specification Bases RS-16-199, Supplement to Request for License Amendment Regarding Transition to Areva Fuel2016-09-28028 September 2016 Supplement to Request for License Amendment Regarding Transition to Areva Fuel RS-16-187, Request for License Amendment to Revise Technical Specifications Section 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2016-09-19019 September 2016 Request for License Amendment to Revise Technical Specifications Section 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML16209A2182016-07-26026 July 2016 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Lnservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing. RS-14-322, License Amendment Request for Addition of New LCO 3.10.8 for Reactor Vessel Hydrostatic and Leak Testing Requirements and for Adoption of TSTF-484, Revision 0, Use Of.2014-12-22022 December 2014 License Amendment Request for Addition of New LCO 3.10.8 for Reactor Vessel Hydrostatic and Leak Testing Requirements and for Adoption of TSTF-484, Revision 0, Use Of. RS-14-192, Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Revision 2, Using the Consolidated Line Item Improvement Process2014-07-14014 July 2014 Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Revision 2, Using the Consolidated Line Item Improvement Process RS-12-036, License Amendment Request to Technical Specifications Section 5.6.5, Core Operating Limits Report (Colr).2012-04-0303 April 2012 License Amendment Request to Technical Specifications Section 5.6.5, Core Operating Limits Report (Colr). ML11305A1472011-10-19019 October 2011 Technical Specifications Bases Affected Page List ML11305A1352011-10-19019 October 2011 Technical Specification Bases RS-11-159, Quad Cities, Units 1 and 2 - Technical Specifications Bases Affected Page List2011-10-19019 October 2011 Quad Cities, Units 1 and 2 - Technical Specifications Bases Affected Page List RS-11-159, Quad Cities, Units 1 and 2 - Technical Specification Bases2011-10-19019 October 2011 Quad Cities, Units 1 and 2 - Technical Specification Bases RS-11-022, Request for Technical Specification Change for Minimum Critical Power Ratio Safety Limit2011-06-0707 June 2011 Request for Technical Specification Change for Minimum Critical Power Ratio Safety Limit RS-10-028, Request for Amendment to Technical Specification 3.1.7, Standby Liquid Control (SLC) System.2010-03-0303 March 2010 Request for Amendment to Technical Specification 3.1.7, Standby Liquid Control (SLC) System. RS-10-032, Application for Technical Specification Change Regarding Risk-informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3)2010-02-16016 February 2010 Application for Technical Specification Change Regarding Risk-informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) RS-09-152, Request for Amendment to Technical Specification 3.1 .7, Standby Liquid Control (SLC) System2009-11-10010 November 2009 Request for Amendment to Technical Specification 3.1 .7, Standby Liquid Control (SLC) System RS-09-104, Request for License Amendment to Revise Technical Specification 3.4.5, RCS Leakage Detection Instrumentation, to Allow Alternate Method of Verifying Drywell Leakage2009-08-28028 August 2009 Request for License Amendment to Revise Technical Specification 3.4.5, RCS Leakage Detection Instrumentation, to Allow Alternate Method of Verifying Drywell Leakage RS-08-155, Additional Information Supporting Request for License Amendment to Establish Total Battery Connector Resistance Acceptance Criteria in Technical Specifications Surveillance Requirements 3.8.4.2 and 3.8.4.52008-12-0909 December 2008 Additional Information Supporting Request for License Amendment to Establish Total Battery Connector Resistance Acceptance Criteria in Technical Specifications Surveillance Requirements 3.8.4.2 and 3.8.4.5 ML0823907072008-08-21021 August 2008 Revised T.S. Pages Oyster Creek Nuclear Generating Station and Peach Bottom Atomic Power Station, Unit 3-Correction to Facility Operating Licenses RA-08-047, Application for Technical Specification Change Regarding Revision of Control Rod Notch Surveillance Test Frequency, Clarification of SRM Insert Control Rod Action and Clarification of a Frequency Example Using the Consolidation Line Item I2008-06-0909 June 2008 Application for Technical Specification Change Regarding Revision of Control Rod Notch Surveillance Test Frequency, Clarification of SRM Insert Control Rod Action and Clarification of a Frequency Example Using the Consolidation Line Item Im ML0735400492007-12-19019 December 2007 Letter to C. Pardee Correction of Administrative Error in Amendment - the Consistency of TSs to Exelon Generation Company Quality Assurance TR (Tac. MD3937 Thru MD3940 and MD3943 Thru MD3948). - Rplacement Pages RS-07-044, Amergen Energy Company, LLC, Request for Amendment to Technical Specifications Section for the Inservice Testing Program2007-08-0808 August 2007 Amergen Energy Company, LLC, Request for Amendment to Technical Specifications Section for the Inservice Testing Program RS-07-066, Request for License Amendment to Revise Turbine Condenser Vacuum - Low Scram Instrumentation Function2007-08-0101 August 2007 Request for License Amendment to Revise Turbine Condenser Vacuum - Low Scram Instrumentation Function RS-07-020, Exelon/Amergen Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process2007-04-12012 April 2007 Exelon/Amergen Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process ML0702305402007-01-16016 January 2007 NF-BEX-06-281, Rev 0, Quad Cities, Unit 1 Cycle 20 SLMCPR, NP-Attachement RS-06-181, Byron, Dresden, LaSalle, Peach Bottom, and Quad Cities Nuclear Plants, Request for Technical Specification Change to Provide Consistency with EGC Quality Assurance Topical Report2006-12-15015 December 2006 Byron, Dresden, LaSalle, Peach Bottom, and Quad Cities Nuclear Plants, Request for Technical Specification Change to Provide Consistency with EGC Quality Assurance Topical Report RS-06-147, Quad, Units 1 & 2 - Request for License Amendment to Increase Main Steam Safety Valve Lift Setpoint Tolerance and Standby Liquid Control System Enrichment2006-11-0707 November 2006 Quad, Units 1 & 2 - Request for License Amendment to Increase Main Steam Safety Valve Lift Setpoint Tolerance and Standby Liquid Control System Enrichment ML0613103962006-05-10010 May 2006 Correction of Typographical Errors in Issuance of Amendments Dated March 9, 2006 ML0531301922005-10-17017 October 2005 Technical Specification Pages Pressure and Temperature Limits RS-05-075, Request for Amendment to Technical Specifications Associated with Feedwater System and Main Turbine High Water Level Trip Instrumentation2005-06-15015 June 2005 Request for Amendment to Technical Specifications Associated with Feedwater System and Main Turbine High Water Level Trip Instrumentation RS-04-125, Exelon/Amergen Request for Amendment to Technical Specifications Administrative Controls to Incorporate Requirement for Control Room Envelope Integrity Program2004-11-29029 November 2004 Exelon/Amergen Request for Amendment to Technical Specifications Administrative Controls to Incorporate Requirement for Control Room Envelope Integrity Program SVP-04-099, Renewal of National Pollutant Discharge Elimination System (NPDES) Permit No. Il 00050372004-11-17017 November 2004 Renewal of National Pollutant Discharge Elimination System (NPDES) Permit No. Il 0005037 RS-04-133, Request for Changes Related to Technical Specifications Section 3.4.9, Reactor Coolant System Pressure-and Temperature (Pit) Limits.2004-11-0404 November 2004 Request for Changes Related to Technical Specifications Section 3.4.9, Reactor Coolant System Pressure-and Temperature (Pit) Limits. RS-04-067, Amergen, Request for Amendment to Technical Specifications Regarding Mode Change Limitations Using the Consolidated Line Item Improvement Process2004-04-30030 April 2004 Amergen, Request for Amendment to Technical Specifications Regarding Mode Change Limitations Using the Consolidated Line Item Improvement Process RS-03-165, Additional Information Supporting the Request for Technical Specifications Surveillance Requirement 3.6.1.3.8 Change Related to Excess Flow Check Valve Testing2003-08-0808 August 2003 Additional Information Supporting the Request for Technical Specifications Surveillance Requirement 3.6.1.3.8 Change Related to Excess Flow Check Valve Testing RS-03-087, Request for Amendment to Technical Specifications Surveillance Requirements for the Main Steam Line Relief Valves and Relief Request RV-30D2003-04-25025 April 2003 Request for Amendment to Technical Specifications Surveillance Requirements for the Main Steam Line Relief Valves and Relief Request RV-30D RS-03-038, Request for Amendment to TS for Main Steam Line Low Pressure Isolation Function2003-03-28028 March 2003 Request for Amendment to TS for Main Steam Line Low Pressure Isolation Function ML0234505702002-11-27027 November 2002 Request for Technical Specifications Change to Eliminate Requirements for Post Accident Sampling System Using the Consolidated Line Item Improvement Process 2023-05-25
[Table view] Category:Amendment
MONTHYEARRS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration JAFP-20-0049, Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability2020-06-22022 June 2020 Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability RS-19-039, Fleet License Amendment Request - Common Language for Technical Specification High Radiation Area Administrative Controls2019-06-26026 June 2019 Fleet License Amendment Request - Common Language for Technical Specification High Radiation Area Administrative Controls RS-19-023, Application to Increase Technical Specifications Allowable MSIV Leakage Rates and Revise Secondary Containment Surveillance Requirement 3.6.4.1.12019-03-0505 March 2019 Application to Increase Technical Specifications Allowable MSIV Leakage Rates and Revise Secondary Containment Surveillance Requirement 3.6.4.1.1 RS-16-187, Request for License Amendment to Revise Technical Specifications Section 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2016-09-19019 September 2016 Request for License Amendment to Revise Technical Specifications Section 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies RS-11-022, Request for Technical Specification Change for Minimum Critical Power Ratio Safety Limit2011-06-0707 June 2011 Request for Technical Specification Change for Minimum Critical Power Ratio Safety Limit RS-10-028, Request for Amendment to Technical Specification 3.1.7, Standby Liquid Control (SLC) System.2010-03-0303 March 2010 Request for Amendment to Technical Specification 3.1.7, Standby Liquid Control (SLC) System. RS-10-032, Application for Technical Specification Change Regarding Risk-informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3)2010-02-16016 February 2010 Application for Technical Specification Change Regarding Risk-informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) RS-09-152, Request for Amendment to Technical Specification 3.1 .7, Standby Liquid Control (SLC) System2009-11-10010 November 2009 Request for Amendment to Technical Specification 3.1 .7, Standby Liquid Control (SLC) System RS-09-104, Request for License Amendment to Revise Technical Specification 3.4.5, RCS Leakage Detection Instrumentation, to Allow Alternate Method of Verifying Drywell Leakage2009-08-28028 August 2009 Request for License Amendment to Revise Technical Specification 3.4.5, RCS Leakage Detection Instrumentation, to Allow Alternate Method of Verifying Drywell Leakage ML0823907072008-08-21021 August 2008 Revised T.S. Pages Oyster Creek Nuclear Generating Station and Peach Bottom Atomic Power Station, Unit 3-Correction to Facility Operating Licenses RA-08-047, Application for Technical Specification Change Regarding Revision of Control Rod Notch Surveillance Test Frequency, Clarification of SRM Insert Control Rod Action and Clarification of a Frequency Example Using the Consolidation Line Item I2008-06-0909 June 2008 Application for Technical Specification Change Regarding Revision of Control Rod Notch Surveillance Test Frequency, Clarification of SRM Insert Control Rod Action and Clarification of a Frequency Example Using the Consolidation Line Item Im ML0735400492007-12-19019 December 2007 Letter to C. Pardee Correction of Administrative Error in Amendment - the Consistency of TSs to Exelon Generation Company Quality Assurance TR (Tac. MD3937 Thru MD3940 and MD3943 Thru MD3948). - Rplacement Pages RS-06-181, Byron, Dresden, LaSalle, Peach Bottom, and Quad Cities Nuclear Plants, Request for Technical Specification Change to Provide Consistency with EGC Quality Assurance Topical Report2006-12-15015 December 2006 Byron, Dresden, LaSalle, Peach Bottom, and Quad Cities Nuclear Plants, Request for Technical Specification Change to Provide Consistency with EGC Quality Assurance Topical Report RS-06-147, Quad, Units 1 & 2 - Request for License Amendment to Increase Main Steam Safety Valve Lift Setpoint Tolerance and Standby Liquid Control System Enrichment2006-11-0707 November 2006 Quad, Units 1 & 2 - Request for License Amendment to Increase Main Steam Safety Valve Lift Setpoint Tolerance and Standby Liquid Control System Enrichment ML0613103962006-05-10010 May 2006 Correction of Typographical Errors in Issuance of Amendments Dated March 9, 2006 ML0531301922005-10-17017 October 2005 Technical Specification Pages Pressure and Temperature Limits RS-05-075, Request for Amendment to Technical Specifications Associated with Feedwater System and Main Turbine High Water Level Trip Instrumentation2005-06-15015 June 2005 Request for Amendment to Technical Specifications Associated with Feedwater System and Main Turbine High Water Level Trip Instrumentation RS-04-125, Exelon/Amergen Request for Amendment to Technical Specifications Administrative Controls to Incorporate Requirement for Control Room Envelope Integrity Program2004-11-29029 November 2004 Exelon/Amergen Request for Amendment to Technical Specifications Administrative Controls to Incorporate Requirement for Control Room Envelope Integrity Program SVP-04-099, Renewal of National Pollutant Discharge Elimination System (NPDES) Permit No. Il 00050372004-11-17017 November 2004 Renewal of National Pollutant Discharge Elimination System (NPDES) Permit No. Il 0005037 RS-04-133, Request for Changes Related to Technical Specifications Section 3.4.9, Reactor Coolant System Pressure-and Temperature (Pit) Limits.2004-11-0404 November 2004 Request for Changes Related to Technical Specifications Section 3.4.9, Reactor Coolant System Pressure-and Temperature (Pit) Limits. RS-04-067, Amergen, Request for Amendment to Technical Specifications Regarding Mode Change Limitations Using the Consolidated Line Item Improvement Process2004-04-30030 April 2004 Amergen, Request for Amendment to Technical Specifications Regarding Mode Change Limitations Using the Consolidated Line Item Improvement Process RS-03-165, Additional Information Supporting the Request for Technical Specifications Surveillance Requirement 3.6.1.3.8 Change Related to Excess Flow Check Valve Testing2003-08-0808 August 2003 Additional Information Supporting the Request for Technical Specifications Surveillance Requirement 3.6.1.3.8 Change Related to Excess Flow Check Valve Testing RS-03-087, Request for Amendment to Technical Specifications Surveillance Requirements for the Main Steam Line Relief Valves and Relief Request RV-30D2003-04-25025 April 2003 Request for Amendment to Technical Specifications Surveillance Requirements for the Main Steam Line Relief Valves and Relief Request RV-30D RS-03-038, Request for Amendment to TS for Main Steam Line Low Pressure Isolation Function2003-03-28028 March 2003 Request for Amendment to TS for Main Steam Line Low Pressure Isolation Function ML0234505702002-11-27027 November 2002 Request for Technical Specifications Change to Eliminate Requirements for Post Accident Sampling System Using the Consolidated Line Item Improvement Process RS-02-152, . Request for Technical Specifications Surveillance Requirement 3.3.4.1.2 Change Related to Anticipated Transient Without Scram- Recirculation Pump Trip Instrumentation2002-08-22022 August 2002 . Request for Technical Specifications Surveillance Requirement 3.3.4.1.2 Change Related to Anticipated Transient Without Scram- Recirculation Pump Trip Instrumentation ML0219903882002-07-17017 July 2002 Quad-Cities Units 1 & 2, Technical Specification Pages Re AC Sources - Operation 3.8.1 Surviellance Requirements ML0211400152002-04-19019 April 2002 Technical Specification Pages for Amendment No. 205 and 201 - Revise Surveillance Requirement 3.0.3 to Extend the Delay Period, Before Entering a Limiting Condition for Operation, Following a Missed Surveillance ML17037B7791974-02-0707 February 1974 Letter Regarding Petition for Derating of Certain Boiling Water Reactors and Enclosed Before the Atomic Safety and Licensing Appeal Board in the Matter of Vermont Yankee Nuclear Power Corporation - Vermont Yankee Nuclear ... 2023-05-25
[Table view] |
Text
SExelkn.
Exelon Generation wwwexeloncorpcorn NucleaT 4300 Winfield Road Warrenville, IL60555 10 CFR 50.90 RS-02-152 August 22, 2002 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265
Subject:
Request for Technical Specifications Surveillance Requirement 3.3.4.1.2 Change Related to Anticipated Transient Without Scram - Recirculation Pump Trip Instrumentation
References:
- 1) Letter from R. M. Krich (Commonwealth Edison Company) to U. S. NRC, "Proposed Technical Specifications Change - Surveillance Test Intervals and Allowable Outage Times for Protective Instrumentation," dated December 27, 1999
- 2) Letter from U. S. NRC to 0. D. Kingsley (Exelon Generation Company, LLC), "Quad Cities Nuclear Power Station, Units 1 and 2 - Issuance of Amendments," dated March 28, 2001 Pursuant to 10 CFR 50.90, "Application for amendment of license or construction permit,"
Exelon Generation Company, LLC (EGC) requests a change to Appendix A, Technical Specifications (TS), of Facility Operating License Nos. DPR-29 and DPR-30 for the Quad Cities Nuclear Power Station (QCNPS), Units 1 and 2. The proposed change is to TS Section 3.3.4.1, "Anticipated Transient Without Scram Recirculation Pump Trip (ATWS-RPT)
Instrumentation," Surveillance Requirement (SR) 3.3.4.1.2. This SR specifies calibration of the trip units associated with the instrumentation channels of the ATWS-RPT System. The proposed change modifies the required surveillance test interval for performance of SR 3.3.4.1.2 from monthly to quarterly.
The proposed change in trip unit calibration frequency is consistent with the recommendations specified in General Electric (GE) Company licensing topical reports that evaluated increasing allowed out-of-service times (AOTs) and surveillance test intervals (STIs) for boiling water reactor plants. The GE licensing topical reports were developed by the Boiling Water Reactor Owners' Group and subsequently approved by the NRC. The rationale used in this requested change is similar to that used in a license amendment request submitted for QCNPS (Reference 1) on AOTs and STIs for protective instrumentation, which was subsequently AoDl
August 22, 2002 U. S. Nuclear Regulatory Commission Page 2 approved by the NRC (Reference 2). In addition, the proposed change is consistent with the instrument AOTs and STIs found in the Improved Standard Technical Specifications (i.e.,
NUREG-1433, Revision 2, "Standard Technical Specifications, General Electric Plants, BWR/4").
EGC requests approval of the proposed TS change by May 30, 2003, with a 90-day implementation period.
This request is subdivided as follows.
- 1. Attachment A contains a description and safety analysis of the proposed change.
- 2. Attachment B provides the marked-up TS page indicating the proposed change.
- 3. Attachment C provides the revised TS page incorporating the proposed change. The revised page of the affected TS Bases is also included for informational purposes.
- 4. Attachment D describes our evaluation performed using the criteria in 10 CFR 50.91 (a),
"Notice for public comment," paragraph (1), which provides information supporting a finding of no significant hazards consideration using the standards in 10 CFR 50.92, "Issuance of amendment," paragraph (c).
- 5. Attachment E provides information supporting an Environmental Assessment.
This proposed TS change has been reviewed by the QCNPS Plant Operations Review Committee and the Nuclear Safety Review Board in accordance with the requirements of the EGC Quality Assurance Program.
EGC is notifying the State of Illinois of this request for a change to the TS by transmitting a copy of this letter and its attachments to the designated State Official.
Should you have any questions concerning this letter, please contact Mr. Kenneth Nicely at (630) 657-2803.
Respectfully, Keith R. Jury Director - Licensing Mid-West Regional Operating Group
August 22, 2002 U. S. Nuclear Regulatory Commission Page 3 Attachments: Affidavit Attachment A: Description and Safety Analysis for Proposed Change Attachment B: Marked-Up Technical Specifications Page for Proposed Change Attachment C: Typed Pages for Technical Specifications and Bases Changes Attachment D: Information Supporting a Finding of No Significant Hazards Consideration Attachment E: Information Supporting an Environmental Assessment cc: Regional Administrator - NRC Region III NRC Senior Resident Inspector - Quad Cities Nuclear Power Station Office of Nuclear Facility Safety - Illinois Department of Nuclear Safety
STATE OF ILLINOIS )
)
COUNTY OF DUPAGE
)
IN THE MATTER OF EXELON GENERATION COMPANY, LLC ) Docket Numbers QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 ) 50-254 and 50-265
SUBJECT:
Request for Technical Specifications Surveillance Requirement 3.3.4.1.2 Change Related to Anticipated Transient Without Scram - Recirculation Pump Trip Instrumentation AFFIDAVIT I affirm that the content of this transmittal is true and correct to the best of my knowledge, information and belief.
Keith R. Jury Director - Licensing Mid-West Regional Operating Group Subscribed and sworn to before me, a Notary Public in and for the State above named, this no--.hday of
,2000 I OFFICIAL SEAL ANESE L. GRIGSBY NOTARY PUBUC, STATE OF ILLINOIS MY COMMISSION EXPIRES 3-13%2005 NotayPbi
Attachment A DESCRIPTION AND SAFETY ANALYSIS FOR PROPOSED CHANGE A.
SUMMARY
OF PROPOSED CHANGE In accordance with 10 CFR 50.90, "Application for amendment of license or construction permit," Exelon Generation Company, LLC (EGC) requests a change to Appendix A, Technical Specifications (TS), of Facility Operating License Nos. DPR-29 and DPR-30 for the Quad Cities Nuclear Power Station (QCNPS), Units 1 and 2. The proposed change is to TS Section 3.3.4.1, "Anticipated Transient Without Scram Recirculation Pump Trip (ATWS RPT) Instrumentation." Specifically, the proposed change increases the surveillance test interval (STI) specified for Surveillance Requirement (SR) 3.3.4.1.2 from monthly (i.e.,
31 days) to quarterly (i.e., 92 days). SR 3.3.4.1.2 specifies calibration of the trip units associated with the instrumentation channels of the ATWS-RPT System. The proposed change in frequency of trip unit calibration is consistent with the recommendations specified in General Electric (GE) Company Licensing Topical Reports (LTRs) GENE-770-06-1-A and NEDC-30851 P-A (References 1.1 and 1.2), which have been reviewed and approved by the NRC. In addition, the rationale used in this requested change is similar to that used in a license amendment request (LAR) submitted for QCNPS (Reference 1.3) on extended STIs and Allowable Outage Times (AOTs) for protective instrumentation, which was subsequently approved by the NRC (Reference 1.4). The proposed change is also consistent with the applicable STI specified in NUREG-1433, Revision 2, "Standard Technical Specifications, General Electric Plants, BWR/4."
A description of the proposed change is provided in detail in Section E, "Description of the Proposed Change," of this Attachment. Attachment B provides the marked-up TS page indicating the proposed change. Attachment C provides typed TS and Bases pages incorporating the proposed change.
B. DESCRIPTION OF THE CURRENT REQUIREMENTS TS Section 3.3.4.1 provides the operability requirements applicable to the protection and monitoring functions of the ATWS-RPT instrumentation. As part of these operability requirements, SR 3.3.4.1.2 specifies performance of trip unit calibrations on the electronic analog trip units associated with the ATWS-RPT reactor vessel water level and reactor vessel steam dome pressure instrumentation channels. The specified frequency for SR 3.3.4.1.2 is at least once every 31 days.
C. BASES FOR THE CURRENT REQUIREMENTS The protection and monitoring functions of the ATWS-RPT instrumentation have been designed to ensure safe operation of the reactor by lessening the effects of an ATWS event.
The ATWS-RPT instrumentation initiates an RPT, when reactor vessel water level and/or reactor vessel steam dome pressure exceed their specified limits, to insert negative reactivity to the reactor. RPT actuation aids in preserving the integrity of the fuel cladding following events in which a Reactor Protection System (RPS) scram does not occur, but should have occurred.
Page 1 of 6
Attachment A DESCRIPTION AND SAFETY ANALYSIS FOR PROPOSED CHANGE The ATWS-RPT System includes sensors, relays, bypass capability circuit breakers, and switches that are necessary to cause initiation of an RPT. The ATWS-RPT instrument channels include electronic equipment (e.g., trip units) that compare measured input signals with pre-established setpoints. When the setpoint is exceeded, the channel output relay actuates, which then outputs an ATWS-RPT signal to the trip logic.
The ATWS-RPT consists of two independent trip systems, with two channels of reactor vessel steam dome pressure - high and two channels of reactor vessel water level - low low in each trip system. Each ATWS-RPT trip system is a two-out-of-two logic for each function.
Thus, either two reactor vessel water level - low low or two reactor vessel steam dome pressure - high signals are needed to actuate a trip system. The outputs of the channels in a trip system are combined in a logic so that either trip system will trip both recirculation pumps (by tripping the respective motor generator drive motor field breakers).
The operability of the ATWS-RPT instrumentation is dependent on the operability of the individual instrumentation channel functions. Each function must have a required number of operable channels in each trip system, with their setpoints within their specified Allowable Values. The actual setpoint is calibrated consistent with applicable setpoint methodology assumptions.
The TS require instrumentation important to safety, including the ATWS-RPT System, to be tested at a specified interval to ensure a high degree of safety system reliability. SR 3.3.4.1.2 provides assurance that the ATWS-RPT instrumentation channels will perform as required to initiate an RPT should a low-low reactor vessel water level or high reactor vessel steam dome pressure condition occur during reactor power operations (i.e., Mode 1).
D. NEED FOR REVISION OF THE REQUIREMENTS In 1983 the Boiling Water Reactor Owners' Group (BWROG) formed a Technical Specification Improvement (TSI) Committee. This committee established a program to identify improvements to AOTs and STIs specified in Boiling Water Reactor (BWR) Standard TS. The primary objective was to minimize unnecessary testing and restrictive out-of service times that could potentially degrade overall plant safety and availability. Examples of some of the problems experienced at QCNPS with SR 3.3.4.1.2 performance are excessive actuation of equipment contributing to component wear-out and unavailability of system equipment during surveillance testing. In addition, the allocation of plant resources required to perform excessive surveillance testing prevents plant personnel from performing other activities that may have a more significant contribution to plant safety.
During April 1984, the TSI Committee met with the NRC and outlined the BWR TS Improvement Program. The NRC expressed agreement with the overall approach.
Subsequently, the BWROG developed a series of LTRs (including References 1.1 and 1.2) which provided the bases for extending the AOTs and STIs for key actuation instrumentation, including that associated with ATWS-RPT. These GE LTRs were subsequently reviewed and approved by the NRC.
Page 2 of 6
Attachment A DESCRIPTION AND SAFETY ANALYSIS FOR PROPOSED CHANGE In 1999, QCNPS initiated a TS improvement project to extend the functional test frequency for certain plant instruments (primarily the actuation instruments such as the RPS and Emergency Core Cooling System (ECCS)). This project supported extending the functional test interval from monthly to quarterly and was patterned after the BWROG developed GE LTRs on AOT/STI TS enhancements. QCNPS applied for AOT/STI TS enhancements in a license amendment request (Reference 1.3), which was subsequently approved by the NRC (Reference 1.4). At the time, the setpoint calculations for most of the instrument channel trip units utilized at QCNPS (i.e., Rosemount analog trip units) were based on a quarterly calibration interval, thus allowing the extension of calibration related STIs for such instrumentation to quarterly. However, the analog trip units utilized for ATWS-RPT functions at QCNPS are manufactured by the GE Company and their calibration interval was intentionally retained at monthly. Since that time, the supporting calculations, using NRC approved methodology, for the ATWS-RPT reactor vessel level and pressure instruments have been revised and now support a quarterly calibration STI for ATWS-RPT instrumentation related trip units.
E. DESCRIPTION OF THE PROPOSED CHANGE The following TS change is proposed:
- Revise the required frequency for SR 3.3.4.1.2 from "31 days" to "92 days."
The proposed TS change is reflected on a marked-up copy of the affected TS page in Attachment B. Revised TS and Bases pages affected by the proposed change are also provided as information in Attachment C. Following NRC approval of this request, EGC will revise the TS Bases, in accordance with the TS Bases Control Program of TS Section 5.5.10, "Technical Specifications (TS) Bases Control Program," to incorporate the change identified in Attachment C.
F. SAFETY ANALYSIS OF THE PROPOSED CHANGE As described in Section 15.8, "Anticipated Transients Without Scram," of the QCNPS Updated Final Safety Analysis Report (UFSAR), ATWS events are not design basis accidents. ATWS events are low probability events in which an anticipated transient occurs and is not followed by an automatic reactor shutdown (scram) when required. The failure of the reactor to scram quickly during these transients can lead to unacceptable reactor coolant system pressures and to fuel damage. The closure of all main steam isolation valves would be the most severe event from virtually all aspects when accompanied by lack of a scram.
The GE LTR developed by the BWROG that pertains to ATWS-RPT actuation instrumentation is GENE-770-06-1-A (Reference 1.1). GENE-770-06-1-A provides the justification for TS improvements for selected instrumentation functions at BWR plants.
Included in this LTR are proposed changes to STIs and AOTs for the applicable instrumentation including the calibration extension from monthly to quarterly for ATWS-RPT Page 3 of 6
Attachment A DESCRIPTION AND SAFETY ANALYSIS FOR PROPOSED CHANGE instrument related trip units. The report concluded that extending functional test frequencies and AOTs for certain instruments was appropriate. A NRC Safety Evaluation for GENE-770-06-1 was provided in a letter from C. Rossi (USNRC) to R. Binz (BWROG),
dated July 21, 1992. As stated within this NRC Safety Evaluation, the NRC required that plant specific applications confirm the applicability of the generic analyses to the specific plant, and confirm that setpoint drift, which could be expected under the extended test intervals, is within the existing allowances in the respective instrument setpoint calculations.
The following discussion provides the information requested by the NRC in plant-specific submittals.
NRC Condition No. 1 Confirm the applicability of the generic analyses to the plant.
Response to NRC Condition No. 1 EGC has reviewed LTR GENE-770-06-1-A and completed the necessary plant-specific evaluations to confirm that the generic results and conclusions of the LTR apply to QCNPS, Units 1 and 2. QCNPS instrumentation for ATWS-RPT actuation consists of four low-low reactor vessel water level instruments and four high reactor vessel steam dome pressure instruments. The signals are combined in a two-out-of-two taken once logic scheme. The LTR analysis for ATWS-RPT System instrumentation (Section 3.3) evaluated the following logic schemes: one-out-of-two taken twice and two-out-of-two taken once. Thus, the LTR analyzed logic schemes encompass the ATWS-RPT design of QCNPS. The LTR evaluation concluded that the proposed changes to ATWS-RPT instrumentation STIs have a negligible effect on the reactivity shutdown failure frequency. For these reasons, the applicability of the generic analyses to QCNPS for the proposed change has been confirmed.
NRC Condition No. 2 Confirm that setpoint drift, which could be expected under the extended test intervals, is within the existing allowances in the respective instrument setpoint calculations.
Response to NRC Condition No. 2 The setpoint methodology at QCNPS uses the instrument calibration frequency to account for potential instrument drift. The reactor vessel water level instrument loops of the ATWS RPT System contain GE Model 184C5988G131 analog trip units with Rosemount Model 1151 DP4 transmitters. The reactor vessel steam dome pressure instrument loops of the ATWS-RPT System contain the same GE model analog trip units with Rosemount Model 1151 GP9 transmitters. The analog trip unit devices are calibrated every 31 days in accordance with the current TS. However, EGC has explicitly evaluated the setpoint drift associated with these GE analog trip units. The results of the drift analysis have been utilized to demonstrate that extending the current calibration frequency from 31 days to 92 days is acceptable and within existing setpoint allowances. This rationale is consistent with the evaluation of analog trip units provided in GE LTR NEDC-30851 P-A (Reference 1.2).
(NOTE: Appendix L of NEDC-30851 P-A identifies Commonwealth Edison Company Page 4 of 6
Attachment A DESCRIPTION AND SAFETY ANALYSIS FOR PROPOSED CHANGE (including QCNPS) as a participating utility in contributing to the development of this LTR.)
LTR NEDC-30851 P-A has been NRC-approved (NRC Safety Evaluation for NEDC-30851P A was transmitted in a letter from A. Thadani (USNRC) to T. Pickens (BWROG), dated July 15, 1987). NEDC-30851P-A evaluated the impact of extending functional testing requirements from monthly to quarterly for RPS instrumentation. Although NEDC-30851 P-A pertains to RPS instrumentation, Section 5.7.3 of the LTR includes a general discussion on the acceptability of extending testing requirements for analog trip unit devices that would also apply to ATWS-RPT instrumentation analog trip units. This LTR section states "Current vendor drift information on analog trip units indicate that the calibration interval could be extended to 6 months." Therefore, increasing the GE analog trip unit calibration intervals from 31 days to 92 days is consistent with the general requirements of this LTR and is explicitly demonstrated as acceptable per our current setpoint methodology. The frequency of 92 days is consistent with the frequency for existing trip units on RPS and ECCS level channels at QCNPS. In addition, the 92-day frequency is also consistent with the applicable STI specified in NUREG-1433, Revision 2, "Standard Technical Specifications, General Electric Plants, BWRI4." Therefore, we have confirmed that the setpoint drift, which could be expected under the proposed extended STI, is within the existing allowances of the associated ATWS-RPT instrumentation setpoint calculations.
For the above reasons, the proposed change is acceptable and does not involve a reduction in plant safety.
G. IMPACT ON PREVIOUS SUBMITTALS EGC has reviewed the proposed change for impact on previous submittals awaiting NRC approval, and has determined that there is no impact on any of them.
H. SCHEDULE REQUIREMENTS We request approval of the proposed change by May 30, 2003, with a 90-day implementation period.
I. REFERENCES 1.1 General Electric Licensing Topical Report GENE-770-06-1-A, "Bases for Changes to Surveillance Test Intervals and Allowed Out-of-Service Times for Selected Instrumentation Technical Specifications," December 1992 1.2 General Electric Licensing Topical Report NEDC-30851 P-A, "Technical Specification Improvement Analyses for BWR Reactor Protection System," March 1988 1.3 Letter from R. M. Krich (Commonwealth Edison Company) to U. S. NRC, "Proposed Technical Specifications Change - Surveillance Test Intervals and Allowable Outage Times for Protective Instrumentation," dated December 27, 1999 Page 5 of 6
Attachment A DESCRIPTION AND SAFETY ANALYSIS FOR PROPOSED CHANGE 1.4 Letter from U. S. NRC to 0. D. Kingsley (Exelon Generation Company, LLC), "Quad Cities Nuclear Power Station, Units 1 and 2 - Issuance of Amendments," dated March 28, 2001 Page 6 of 6
Attachment B MARKED-UP TECHNICAL SPECIFICATIONS PAGE FOR PROPOSED CHANGE REVISED TS PAGE 3.3.4.1-3
ATWS-RPT Instrumentation 3.3.4.1 SURVEILLANCE REQUIREMENTS
NOTE -------------------------------------
When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> provided the associated Function maintains ATWS-RPT trip capability.
.. . . . . . . . o . . . . ..-------------------
SURVEILLANCE FREQUENCY SR 3.3.4.1.1 Perform CHANNEL CHECK. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> SR 3.3.4.1.2 Calibrate the trip units, days SR 3.3.4.1.3 Perform CHANNEL FUNCTIONAL TEST. 92 days SR 3.3.4.1.4 Perform CHANNEL CALIBRATION. The 24 months
... Allowable Values shall be:
- a. Reactor Vessel Water Level-Low Low:
>-56.3 inches with time delay set to
>7.2 seconds and ( 10.8 seconds; and
- b. Reactor Vessel Steam Dome Pressure-High: < 1219 psig.
SR 3.3.4.1.5 Perform LOGIC SYSTEM FUNCTIONAL TEST 24 months including breaker actuation.
Quad Cities I and 2 3.3.4.1-3 Amendment No. 199/195
Attachment C TYPED PAGES FOR TECHNICAL SPECIFICATIONS AND BASES CHANGES REVISED TS PAGE 3.3.4.1-3 REVISED BASES PAGE (PROVIDED FOR INFORMATION ONLY)
B 3.3.4.1-9
ATWS-RPT Instrumentation 3.3.4.1 SURVEILLANCE REQUIREMENTS
NOTE .......................
When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> provided the associated Function maintains ATWS-RPT trip capability.
SURVEILLANCE FREQUENCY SR 3.3.4.1.1 Perform CHANNEL CHECK. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> SR 3.3.4.1.2 Calibrate the trip units. 92 days I SR 3.3.4.1.3 Perform CHANNEL FUNCTIONAL TEST. 92 days SR 3.3.4.1.4 Perform CHANNEL CALIBRATION. The 24 months Allowable Values shall be:
- a. Reactor Vessel Water Level-Low Low:
Ž-56.3 inches with time delay set to S7.2 seconds and
- b. Reactor Vessel Steam Dome Pressure-High:
SR 3.3.4.1.5 Perform LOGIC SYSTEM FUNCTIONAL TEST 24 months including breaker actuation.
Quad Cities 1 and 2 3.3.4.1-3 Amendment No.
ATWS-RPT Instrumentation B 3.3.4.1 BASES SURVEILLANCE SR 3.3.4.1.2 REQUIREMENTS (continued) Calibration of trip units provides a check of the actual trip setpoints. The channel must be declared inoperable if the trip setting is discovered to be less conservative than the Allowable Value specified in SR 3.3.4.1.4. If the trip setting is discovered to be less conservative than the setting accounted for in the appropriate setpoint methodology, but is not beyond the Allowable Value, the channel performance is still within the requirements of the ATWS analysis. Under these conditions, the setpoint must be readjusted to be equal to or more conservative than accounted for in the appropriate setpoint methodology.
The Frequency of 92 days is based on the reliability analysis of Reference 3.
SR 3.3.4.1.3 A CHANNEL FUNCTIONAL TEST is performed on each required channel to ensure that the channel will perform the intended function. A successful test of the required contact(s) of a channel relay may be performed by the verification of the change of state of a single contact of the relay. This clarifies what is an acceptable CHANNEL FUNCTIONAL TEST of a relay. This is acceptable because all of the other required contacts of the relay are verified by other Technical Specifications and non-Technical Specifications tests at least once per refueling interval with applicable extensions. Any setpoint adjustment shall be consistent with the assumptions of the current plant specific setpoint methodology.
The Frequency of 92 days is based on the reliability analysis of Reference 3.
SR 3.3.4.1.4 A CHANNEL CALIBRATION is a complete check of the instrument loop and the sensor, including the time delay relays associated with the Reactor Vessel Water Level-Low Low Function. This test verifies the channel responds to the (continued)
Quad Cities 1 and 2 B 3.3.4.1-9 Revi si on
Attachment D INFORMATION SUPPORTING A FINDING OF NO SIGNIFICANT HAZARDS CONSIDERATION According to 10 CFR 50.92, "Issuance of amendment," paragraph (c) a proposed amendment to an operating license involves a no significant hazards consideration if operation of the facility in accordance with the proposed amendment would not:
(1) Involve a significant increase in the probability or consequences of an accident previously evaluated; or (2) Create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) Involve a significant reduction in a margin of safety.
In support of this determination, an evaluation of each of the three criteria set forth in 10 CFR 50.92 is provided below regarding the proposed license amendment.
Overview In accordance with 10 CFR 50.90, "Application for amendment of license or construction permit," Exelon Generation Company, LLC (EGC) requests a change to Appendix A, Technical Specifications (TS), of Facility Operating License Nos. DPR-29 and DPR-30 for the Quad Cities Nuclear Power Station (QCNPS), Units I and 2. The proposed change modifies the TS section involving operability requirements for Anticipated Transient Without Scram Recirculation Pump Trip (ATWS-RPT) instrumentation. Specifically, the proposed change modifies the required frequency for performance of a Surveillance Requirement involving calibration of the trip units associated with the instrumentation channels of the ATWS-RPT System. The proposed change in trip unit calibration frequency is consistent with the recommendations specified in General Electric (GE) Company licensing topical reports which justified extending allowed out-of-service times (AOTs) and surveillance test intervals (STIs) for key actuation instrumentation. These GE licensing topical reports have been previously reviewed and approved by the NRC.
The proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.
The proposed TS change increases a STI for ATWS-RPT System actuation instrumentation based on generic analyses completed by the Boiling Water Reactor Owners' Group (BWROG). The NRC has reviewed and approved these generic analyses and has concurred with the BWROG that the proposed changes do not significantly affect the probability of failure or availability of the affected instrumentation systems. EGC has determined these studies are applicable to QCNPS, Units 1 and 2.
TS requirements that govern operability or routine testing of plant instruments are not assumed to be initiators of any analyzed event because these instruments are intended to prevent, detect, or mitigate accidents. Therefore, this change will not involve an increase in the probability of occurrence of an accident previously evaluated. Additionally, this change will not increase the consequences of an accident previously evaluated because the proposed change does not involve any physical changes to ATWS-RPT System Page 1 of 2
Attachment D INFORMATION SUPPORTING A FINDING OF NO SIGNIFICANT HAZARDS CONSIDERATION components or the manner in which the ATWS-RPT System is operated. This change will not alter the operation of equipment assumed to be available for the mitigation of accidents or transients specified in the ATWS analysis contained in the QCNPS Updated Final Safety Analysis Report (UFSAR). As justified and approved in licensing topical reports endorsing extended AOTs and STIs, the proposed change establishes or maintains adequate assurance that components are operable when necessary for the prevention or mitigation of accidents or transients, and that plant variables are maintained within limits necessary to satisfy the assumptions for initial conditions in the safety analyses. Furthermore, there will be no change in the types or significant increase in the amounts of any effluents released offsite.
For these reasons, the proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.
The proposed change does not create the possibility of a new or different kind of accident from any accident previously evaluated?
The proposed change does not involve any physical changes to the ATWS-RPT System or associated components, or the manner in which the ATWS-RPT System functions.
Therefore, this change will not create the possibility of a new or different kind of accident from any accident previously evaluated. There is no change being made to the parameters within which the plant is operated. There are no setpoints at which protective or mitigative actions are initiated that are affected by the proposed change. This proposed change will not alter the manner in which equipment operation is initiated nor will the function demands on credited equipment be changed. The change in methods governing normal plant operation is consistent with the current ATWS analysis assumptions specified in the UFSAR.
Therefore, this change will not create the possibility of a new or different kind of accident from any accident previously evaluated.
Does the proposed change involve a significant reduction in a margin of safety?
Margins of safety are established in the design of components, the configuration of components to meet certain performance parameters, and in the establishment of setpoints to initiate alarms or actions. The proposed change increases a STI for ATWS-RPT System actuation instrumentation based on generic analyses completed by the BWROG. The analyses determined that there is no significant change in the availability and/or reliability of ATWS-RPT instrumentation as a result of the proposed change in STI. The extended STI does not result in significant changes in the probability of ATWS-RPT instrument failure.
Furthermore, the proposed change will not reduce the probability of test-induced ATWS RPT transients and equipment failures. Therefore, it is concluded that the proposed change will not result in a reduction in the margin of safety.
Conclusion Based upon the above evaluation, EGC has concluded that the criteria of 10 CFR 50.92(c) are satisfied and that the proposed TS change involves no significant hazards consideration.
Page 2 of 2
Attachment E INFORMATION SUPPORTING AN ENVIRONMENTAL ASSESSMENT In accordance with 10 CFR 50.90, "Application for amendment of license or construction permit," Exelon Generation Company, LLC (EGC) requests a change to Appendix A, Technical Specifications (TS), of Facility Operating License Nos. DPR-29 and DPR-30 for the Quad Cities Nuclear Power Station (QCNPS), Units I and 2. The proposed change is to TS Section 3.3.4.1, "Anticipated Transient Without Scram Recirculation Pump Trip (ATWS RPT) Instrumentation," Surveillance Requirement (SR) 3.3.4.1.2. Specifically, the proposed change modifies the required surveillance test interval for performance of SR 3.3.4.1.2 from monthly to quarterly. SR 3.3.4.1.2 specifies calibration of the trip units associated with the instrumentation channels of the ATWS-RPT System. The proposed change in trip unit calibration frequency is consistent with the recommendations specified in General Electric Company Licensing Topical Reports GENE-770-06-1 -A, "Bases for Changes to Surveillance Test Intervals and Allowed Out-of-Service Times for Selected Instrumentation Technical Specifications," and NEDC-30851 P-A, "Technical Specification Improvement Analyses for BWR Reactor Protection System," which were developed by the Boiling Water Reactor Owners' Group and approved by the NRC.
EGC has evaluated this proposed change against the criteria for identification of licensing and regulatory actions requiring environmental assessment in accordance with 10 CFR 51.21, "Criteria for and identification of licensing and regulatory actions requiring environmental assessments." EGC has determined that this proposed change meets the criteria for a categorical exclusion set forth in 10 CFR 51.22, "Criterion for categorical exclusion; identification of licensing and regulatory actions eligible for categorical exclusion or otherwise not requiring environmental review," paragraph (c)(9), and as such, has determined that no irreversible consequences exist in accordance with 10 CFR 50.92, "Issuance of amendment," paragraph (b). This determination is based on the fact that this change is being proposed as an amendment to a license issued pursuant to 10 CFR 50, "Domestic Licensing of Production and Utilization Facilities," which changes a requirement with respect to installation or use of a facility component located within the restricted area, as defined in 10 CFR 20, "Standards for Protection Against Radiation," or that changes an inspection or a surveillance requirement, and the amendment meets the following specific criteria:
(i) The amendment involves no significant hazards consideration.
As demonstrated in Attachment D, the proposed change does not involve a significant hazards consideration.
(ii) There is no significant change in the types or significant increase in the amounts of any effluent that may be released offsite.
The proposed change only revises the required frequency for a Surveillance Requirement that calls for calibration of the trip units associated with the ATWS RPT instrumentation channels. This proposed change does not affect the amounts of effluents released offsite. The proposed change does not allow for an increase in the unit power level, does not increase the production, nor alter the flow path or method of disposal of radioactive waste or byproducts. Therefore, the proposed change does not affect actual unit effluents.
Page 1 of 2
Attachment E INFORMATION SUPPORTING AN ENVIRONMENTAL ASSESSMENT (iii) There is no significant increase in individual or cumulative occupational radiation exposure.
The proposed change will not result in changes in the operation of the facility. The proposed change only changes the required frequency in which trip unit calibrations are performed for the ATWS - RPT instrumentation channels. There will be no change in the level of controls or methodology used for processing of radioactive effluents or handling of solid radioactive waste. The proposed change will not result in any change in the normal radiation levels within the plant. Therefore, there will be no increase in individual or cumulative occupational radiation exposure resulting from this change.
Page 2 of 2