ML022340450

From kanterella
Jump to navigation Jump to search
Agenda for Tennessee Valley Authority Browns Ferry Nuclear Plant, Unit 1 Restart
ML022340450
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 08/07/2002
From:
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
Shared Package
ML022340431 List:
References
Download: ML022340450 (14)


Text

1 Agenda Introduction/Meeting Objectives

- Jon Rupert Regulatory History

- Tim Abney Overview and Schedule

- Jon Rupert/Joe Valente Nuclear Assurance Assessment Activities

- Steve Tanner Commitment Closure

- Tim Abney Unit 1 Regulatory Framework

- Tim Abney Summary and Conclusion

- Jon Rupert

Jon Rupert 2

Unit 1 Restart - Introduction/Meeting Objectives Objectives of this meeting are:

Provide overview of Unit 1 Restart Project Provide schedule of Unit 1 Restart Activities

Tim Abney 3

Regulatory History Unit 2 Restart All 3 BFN units voluntarily shutdown by TVA in March 1985, because of regulatory and management issues TVA committed to obtain NRC approval prior to restart of any BFN unit NRC issued a show cause letter for all TVA nuclear plants in September 1985, under 10 CFR 50.54 (f), and requested TVA to specify corrective actions TVA submitted the Nuclear Performance Plan, Volume 3, in August 1986, outlining the steps needed to recover the BFN units, specifically directed to Unit 2 TVA and NRC conducted several meetings and TVA made several submittals to fully define the regulatory actions needed to restart BFN Unit 2 NRC issued NUREG 1232, Volume 3, Supplement 2 in January 1991, concluding that TVAs actions acceptably addressed BFN deficiencies NRC approved Unit 2 restart on May 23, 1991 Unit 2 restarted on May 24, 1991

Tim Abney 4

Regulatory History Unit 3 Restart TVA proposed regulatory framework for restart of Units 1 and 3 in July 1991, outlining improvements from the Unit 2 precedent NRC approved framework proposed by TVA in April 1992 Unit 3 restart effort dealt primarily with resolving Special Programs, as the management issues had been resolved for Unit 2 restart NRC staff issued SECY-95-264 recommending restart of Unit 3 on November 1, 1995 NRC approved Unit 3 restart on November 15, 1995 Unit 3 restarted on November 19, 1995

Tim Abney 5

Regulatory History Unit 1 Based on Energy Vision 2020 recommendations, TVA decided to delay decision on Unit 1 restart Unit 1 was removed from the NRCs problem plant list on June 21,1996 based on commitments from an April 16, 1996 TVA letter to:

  • Implement same Special Programs on Unit 1 that were done for Unit 3
  • Not restart Unit 1 without prior approval of NRC

Jon Rupert 6

Overview and Schedule Detailed Scoping, Estimate and Planning (DSEP)

Extensive effort to support Unit 1 restart decision Utilized key TVA personnel with both discipline expertise and experience on restart of Units 2 and 3 Results in organizational structure and strong team in place for recovery effort Unit 1 Restart Principles BFN units will be operationally the same at completion of Unit 1 restart Unit 1 restart activities will use plant processes and procedures when available

Joe Valente 7

Overview and Schedule Workscope Required for Unit 1 Restart Special Programs using criteria consistent with Unit 3 Restart Design changes since Units 2/3 restart Future design changes in 5 year BFN Project Plan Corrective/Preventive Maintenance Regulatory Issues Licensing Actions Inservice Inspection

Joe Valente 8

Special Program Differences in Unit 1 vs. Unit 3 Approach Configuration Management None Design Calculations None Equipment Qualification None Seismic Design None Fire Protection Improvement None Instrument Sensing Lines None Wall Thinning None PRA Not Required Component & Piece Part Qualification None Electrical Issues None Q-List None MELB None Platform Thermal Growth None IGSCC Complete replacement of recirculation piping Coatings None Restart Test None Plant Welding Not Required Heat Code Traceability Not Required Overview and Schedule Special Programs

Joe Valente 9

Current Activities Current Activities Engineering Modifications

Joe Valente 10 Overview and Schedule Level 1 Schedule will go here

Steve Tanner 11 Nuclear Assurance - Assessment Activities Line Ownership of Quality Nuclear Assurance Oversight Observations Assessments and Audits Evaluation and Analysis Current Status Corrective Action Program Self-Assessment Program Work Performance

Tim Abney 12 Commitment Closure 268 total open Unit 1 commitments 68 associated with Generic Communications 70 from LERs, violations and inspections 130 from other miscellaneous sources These will be evaluated in accordance with NEI 99-04 for potential decommitments

Tim Abney 13 Unit 1 Regulatory Framework Unit 1 and Unit 3 Regulatory Framework was approved by NRC in April, 1992 Regulatory Framework for Unit 1 to be reviewed and revised Unit 1 Regulatory Framework will include:

Summary of Special Programs Submittals required Concurrent licensing actions for all 3 units, where applicable Commitment closure process, consistent with NEI 99-04 and TVA SPP 3.3 Actions needed for NRC restart approval Format, structure and frequency of periodic meetings TVA intends to submit proposed Regulatory Framework document by December 31, 2002

Jon Rupert 14 Summary and Conclusion