ML022340450

From kanterella
Jump to navigation Jump to search
Agenda for Tennessee Valley Authority Browns Ferry Nuclear Plant, Unit 1 Restart
ML022340450
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 08/07/2002
From:
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
Shared Package
ML022340431 List:
References
Download: ML022340450 (14)


Text

Agenda

  • Introduction/Meeting Objectives - Jon Rupert
  • Regulatory History - Tim Abney
  • Overview and Schedule - Jon Rupert/Joe Valente
  • Nuclear Assurance Assessment Activities - Steve Tanner
  • Commitment Closure - Tim Abney
  • Unit 1 Regulatory Framework - Tim Abney
  • Summary and Conclusion - Jon Rupert 1

Unit 1 Restart - Introduction/Meeting Objectives

  • Objectives of this meeting are:

- Provide overview of Unit 1 Restart Project

- Provide schedule of Unit 1 Restart Activities Jon Rupert 2

Regulatory History

  • Unit 2 Restart

- All 3 BFN units voluntarily shutdown by TVA in March 1985, because of regulatory and management issues

- TVA committed to obtain NRC approval prior to restart of any BFN unit

- NRC issued a show cause letter for all TVA nuclear plants in September 1985, under 10 CFR 50.54 (f), and requested TVA to specify corrective actions

- TVA submitted the Nuclear Performance Plan, Volume 3, in August 1986, outlining the steps needed to recover the BFN units, specifically directed to Unit 2

- TVA and NRC conducted several meetings and TVA made several submittals to fully define the regulatory actions needed to restart BFN Unit 2

- NRC issued NUREG 1232, Volume 3, Supplement 2 in January 1991, concluding that TVAs actions acceptably addressed BFN deficiencies

- NRC approved Unit 2 restart on May 23, 1991

- Unit 2 restarted on May 24, 1991 Tim Abney 3

Regulatory History

  • Unit 3 Restart

- TVA proposed regulatory framework for restart of Units 1 and 3 in July 1991, outlining improvements from the Unit 2 precedent

- NRC approved framework proposed by TVA in April 1992

- Unit 3 restart effort dealt primarily with resolving Special Programs, as the management issues had been resolved for Unit 2 restart

- NRC staff issued SECY-95-264 recommending restart of Unit 3 on November 1, 1995

- NRC approved Unit 3 restart on November 15, 1995

- Unit 3 restarted on November 19, 1995 Tim Abney 4

Regulatory History

  • Unit 1

- Based on Energy Vision 2020 recommendations, TVA decided to delay decision on Unit 1 restart

- Unit 1 was removed from the NRCs problem plant list on June 21,1996 based on commitments from an April 16, 1996 TVA letter to:

  • Implement same Special Programs on Unit 1 that were done for Unit 3
  • Not restart Unit 1 without prior approval of NRC Tim Abney 5

Overview and Schedule

  • Detailed Scoping, Estimate and Planning (DSEP)

- Extensive effort to support Unit 1 restart decision

- Utilized key TVA personnel with both discipline expertise and experience on restart of Units 2 and 3

- Results in organizational structure and strong team in place for recovery effort

  • Unit 1 Restart Principles

- BFN units will be operationally the same at completion of Unit 1 restart

- Unit 1 restart activities will use plant processes and procedures when available Jon Rupert 6

Overview and Schedule

  • Workscope Required for Unit 1 Restart

- Special Programs using criteria consistent with Unit 3 Restart

- Design changes since Units 2/3 restart

- Future design changes in 5 year BFN Project Plan

- Corrective/Preventive Maintenance

- Regulatory Issues

- Licensing Actions

- Inservice Inspection Joe Valente 7

Overview and Schedule Special Programs Special Program Differences in Unit 1 vs. Unit 3 Approach Configuration Management None Design Calculations None Equipment Qualification None Seismic Design None Fire Protection Improvement None Instrument Sensing Lines None Wall Thinning None PRA Not Required Component & Piece Part Qualification None Electrical Issues None Q-List None MELB None Platform Thermal Growth None IGSCC Complete replacement of recirculation piping Coatings None Restart Test None Plant Welding Not Required Heat Code Traceability Not Required Joe Valente 8

Current Activities

  • Current Activities

- Engineering

- Modifications Joe Valente 9

Overview and Schedule Level 1 Schedule will go here Joe Valente 10

Nuclear Assurance - Assessment Activities

  • Line Ownership of Quality
  • Nuclear Assurance Oversight

- Observations

- Assessments and Audits

- Evaluation and Analysis

  • Current Status

- Corrective Action Program

- Self-Assessment Program

- Work Performance Steve Tanner 11

Commitment Closure

  • 268 total open Unit 1 commitments
  • 68 associated with Generic Communications
  • 70 from LERs, violations and inspections
  • 130 from other miscellaneous sources
  • These will be evaluated in accordance with NEI 99-04 for potential decommitments Tim Abney 12

Unit 1 Regulatory Framework

  • Unit 1 and Unit 3 Regulatory Framework was approved by NRC in April, 1992
  • Regulatory Framework for Unit 1 to be reviewed and revised
  • Unit 1 Regulatory Framework will include:

- Summary of Special Programs

- Submittals required

- Concurrent licensing actions for all 3 units, where applicable

- Commitment closure process, consistent with NEI 99-04 and TVA SPP 3.3

- Actions needed for NRC restart approval

- Format, structure and frequency of periodic meetings

  • TVA intends to submit proposed Regulatory Framework document by December 31, 2002 Tim Abney 13

Summary and Conclusion Jon Rupert 14