2002 2003 2004 2005 2006 2007 2008 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 BOARD APPROVAL AWARD MAJOR CONTRACTS ENGINEERING PROGRAMS REQ'D FOR MODS ENGINEERING ISSUE DRYWELL DCN'S NRC BRIEF MOBILIZE MODIFICATIONS SUPPORT TEAM LONG LEAD MATERIAL - ORDER MODIFICATIONS - DEMOLITION & NON DCN ACTIVITIES PREPARE & ISSUE BULK MATERIAL ORDER LONG LEAD MATERIAL - DELIVER ENGINEERING ISSUE REACTOR BUILDING DCN'S DESIGN ENGINEERING SUPPORT ENGINEERING ISSUE CONTROL BUILDING DCN'S MODIFICATIONS IMPLEMENT DRYWELL DCN'S CRDR ENGINEERING COMPLETE MODIFICATIONS IMPLEMENT REACTOR BUILDING DCN'S ENGINEERING ISSUE TURBINE BUILDING DCN'S OPERATIONS PROGRAMS LICENSE RENEWAL SUBMITTAL MODIFICATIONS IMPLEMENT CONTROL BUILDING DCN'S MODIFICATIONS IMPLEMENT TURBINE BUILDING DCN'S RESTART TEST PROGRAM MAINTENANCE CM's & PM's EPU SUBMITTAL RISK INFORMED ISI SUBMITTAL OPERATOR TRAINING SPAE/SPOC TURNOVER AREA TURNOVER PLANT ACCEPTANCE OPERATIONAL READINESS REVIEW NRC TESTING NOTIFICATION LICENSING TO NOTIFY NRC OF FUEL LOAD FUEL LOAD TURBINE GENERATOR ON TURNING GEAR NCR APPROVAL FOR RESTART POWER ASCENSION TESTING BREAKER CLOSURE 1CUR Sheet 1 of 1 Project Start 26NOV01 Early Bar Project Finish 02JUL07 Progress Bar Data Date 01AUG02 Critical Activity TVA BFN UNIT 1 Run Date 05AUG02 MAJOR MILESTONES

© Primavera Systems, Inc.