MONTHYEARML0205805262002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Security Compensatory Measures Project stage: Approval ML0205103332002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0205006202002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0205005562002-02-25025 February 2002 Issuance of Order for Compensatory Security Measures Project stage: Approval ML0205004012002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0205001952002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Security Compensatory Measures Project stage: Approval ML0205002072002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0205001842002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Security Compensatory Measures Project stage: Approval ML0204900772002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Compensatory Security Measures Project stage: Approval ML0204900742002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Security Compensatory Measures Project stage: Approval ML0213002552002-05-20020 May 2002 Meeting Summary with Exelon Generation Company, LLC to Discuss Exelon'S Response to Interim Compensatory Measure Project stage: Meeting ML0213002162002-05-23023 May 2002 Amergen Energy Co, LLC - Reply to Response to Order for Interim Safeguards and Security Compensatory Measures Project stage: Other ML0217108392002-07-18018 July 2002 Alternative Proposal for Compliance with Interim Compensatory Measure B.4.e Pertaining to Owner Controlled Area Patrols at Exelon Sites Project stage: Other ML0223208932002-08-29029 August 2002 Reply to Response to Order for Interim Safeguards and Security Compensatory Measures at Exelon Sites Project stage: Other 2002-05-23
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 ML23354A2902024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0028 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23360A6082023-12-27027 December 2023 County Station Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000373/2024010 and 05000374/2024010 ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums RS-23-120, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information IR 05000373/20230032023-11-0909 November 2023 County Station Integrated Inspection Report 05000373/2023003, 05000374/2023003, and 07200070/2023001 ML23286A2602023-11-0808 November 2023 Issuance of Amendment Nos. 260 and 245 to Renewed Facility Operating Licenses Relocation of Pressure and Temperature Limit Curves to the Pressure Temperature Report IR 05000373/20234012023-11-0707 November 2023 County Station Security Baseline Inspection Report 05000373/2023401 and 05000374/2023401 RS-23-103, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans IR 05000374/20230102023-10-11011 October 2023 NRC Inspection Report 05000374/2023010 IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor ML23212A9012023-08-0303 August 2023 Regulatory Audit Report to Support the Review of the Amendments to Relocation of the Pressure Temperature Limit Curves to the Pressure and Temperature Limits Report IR 05000373/20230022023-08-0101 August 2023 County Station - Integrated Inspection Report 05000373/2023002 and 05000374/2023002 ML23208A3182023-07-27027 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI RS-23-084, Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis2023-07-24024 July 2023 Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis ML23192A5272023-07-12012 July 2023 NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 ML23186A2062023-07-0606 July 2023 Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000374/2023010 ML23181A1502023-06-30030 June 2023 Combined Response to Request for Additional Information and Supplemental Information in Support of LAR to Relocate Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000373/20230112023-06-26026 June 2023 County Station - Quadrennial Fire Protection Team Inspection Report 05000373/2023011 and 05000374/2023011 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23167A0352023-06-16016 June 2023 Registration of Use of Cask to Store Spent Fuel ML23171A9562023-06-12012 June 2023 Post Exam Ltr RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling IR 05000373/20230012023-05-10010 May 2023 County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001 ML23123A2202023-05-0303 May 2023 Relief Request I4R-14 for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23121A1612023-05-0101 May 2023 Information Meeting (Open House) with a Question-and-Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of LaSalle County Station, Units 1 and 2 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23107A1822023-04-18018 April 2023 Operator Licensing Examination Approval Lasalle County Station, May 2023 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23073A2182023-03-22022 March 2023 Issuance of Amendment No. 258 to Renewed Facility Operating Licenses Exigent Amendment to Revise Design Basis Related to Seismic Requirements RS-23-048, Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements2023-03-0707 March 2023 Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000373/20220062023-03-0101 March 2023 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2022006 and 05000374/2022006) RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-037, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station2023-02-22022 February 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station ML23024A1372023-02-0303 February 2023 Request for Withholding Information from Public Disclosure for LaSalle County Station, Unit Nos. 1 and 2 ML23031A1972023-01-31031 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information, Inspection Report Nos. 05000373/2023011 and 05000374/2023011 IR 05000373/20220042023-01-31031 January 2023 County Station - Integrated Inspection Report 05000373/2022004 and 05000374/2022004 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 2024-01-05
[Table view] |
Text
SAFEGUARDS INFORMATION February 25, 2002 Oliver D. Kingsley, Jr.
President and Chief Nuclear Officer LaSalle County Station, Units 1 & 2 Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
ISSUANCE OF ORDER FOR INTERIM SAFEGUARDS AND SECURITY COMPENSATORY MEASURES FOR - LASALLE COUNTY STATION, UNITS 1
&2
Dear Mr. Kingsley:
The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Order that modifies the current operating license for your facility to require compliance with the specified interim safeguards and security compensatory measures. The Order applies to all Addressees listed in to the enclosed Order. These interim compensatory measures are listed in (contains Safeguards Information) to the enclosed Order. The Commission recognizes that you have voluntarily and responsibly implemented additional security measures following the events of September 11, 2001, but, in light of the continuing generalized high-level threat environment, the Commission concludes that the security measures should be embodied in an Order, consistent with the established regulatory framework. The Commission has determined that the generalized high-level threat environment requires that the enclosed Order be effective immediately.
These actions are interim and the basis for the Order is the need to take prudent actions to address security requirements in the present generalized high-level threat environment. This Order does not obviate the need for licensees to continue to meet the objectives of Security Level III described in NRC Information Notice 98-35, and maintain the effectiveness of existing security measures taken in response to the events of September 11, 2001. The requirements will remain in effect pending notification from the Commission that a significant change in the threat environment has occurred, or until the Commission determines that other changes are needed following a more comprehensive re-evaluation of current safeguards and security programs.
The enclosed Order calls for responses and actions within specified time frames. Please contact your Licensing Project Manager to facilitate resolution of any issues related to compliance with the requirements in the enclosed Order, or if you have any other questions.
NOTICE: Attachment 2 to the Order (Interim Compensatory Measures) contains "Safeguards Information." Upon separation of Attachment 2 to the Order, this letter, the enclosed Order, and Attachment 1 to the Order (Address List) are "DECONTROLLED."
SAFEGUARDS INFORMATION
O. Kingsley The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page
LaSalle, Units 1 and 2 cc:
Exelon Generation Company, LLC U.S. Nuclear Regulatory Commission Site Vice President - Dresden LaSalle Resident Inspectors Office 6500 N. Dresden Road 2605 N. 21st Road Morris, Illinois 60450-9765 Marseilles, Illinois 61341-9756 Exelon Generation Company, LLC Phillip P. Steptoe, Esquire Station Manager - Dresden Sidley and Austin 6500 N. Dresden Road One First National Plaza Morris, Illinois 60450-9765 Chicago, Illinois 60603 Exelon Generation Company, LLC Assistant Attorney General Regulatory Assurance Manager - Dresden 100 W. Randolph St. Suite 12 6500 N. Dresden Road Chicago, Illinois 60601 Morris, Illinois 60450-9765 Chairman U.S. Nuclear Regulatory Commission LaSalle County Board Dresden Resident Inspectors Office 707 Etna Road 6500 N. Dresden Road Ottawa, Illinois 61350 Morris, Illinois 60450-9766 Attorney General Chairman 500 S. Second Street Grundy County Board Springfield, Illinois 62701 Administration Building 1320 Union Street Chairman Morris, Illinois 60450 Illinois Commerce Commission 527 E. Capitol Avenue, Leland Building Exelon Generation Company, LLC Springfield, Illinois 62706 Site Vice President - LaSalle 22710 206th Avenue N. Robert Cushing, Chief, Public Utilities Division Cordova, Illinois 61242-9740 Illinois Attorney General's Office 100 W. Randolph Street Exelon Generation Company, LLC Chicago, Illinois 60601 Station Manager - LaSalle 22710 206th Avenue N. Exelon Generation Company, LLC Cordova, Illinois 61242-9740 Site Vice President - Quad Cities 22710 206th Avenue N.
Exelon Generation Company, LLC Cordova, Illinois 61242-9740 Regulatory Assurance Manager - LaSalle 22710 206th Avenue N. Exelon Generation Company, LLC Cordova, Illinois 61242-9740 Station Manager - Quad Cities 22710 206th Avenue N.
Cordova, Illinois 61242-9740
LaSalle, Units 1 and 2 cc:
Exelon Generation Company, LLC Document Control Desk-Licensing Regulatory Assurance Manager - Quad Exelon Generation Company, LLC Cities 4300 Winfield Road 22710 206th Avenue N. Warrenville, Illinois 60555 Cordova, Illinois 61242-9740 Mr. John Skolds U.S. Nuclear Regulatory Commission Chief Operating Officer Quad Cities Resident Inspectors Office Exelon Generation Company, LLC 22712 206th Avenue N. 4300 Winfield Road Cordova, Illinois 61242 Warrenville, Illinois 60555 William D. Leech Mr. John Cotton Manager - Nuclear Senior Vice President, Operations Support MidAmerican Energy Company Exelon Generation Company, LLC P.O. Box 657 4300 Winfield Road Des Moines, Iowa 50303 Warrenville, Illinois 60555 Vice President - Law and Regulatory Affairs Mr. William Bohlke MidAmerican Energy Company Senior Vice President, Nuclear Services One River Center Place Exelon Generation Company, LLC 106 E. Second Street 4300 Winfield Road P.O. Box 4350 Warrenville, Illinois 60555 Davenport, Iowa 52808 Mr. Robert J. Hovey Chairman Operations Vice President Rock Island County Board Mid-West Regional Operating Group of Supervisors Exelon Generation Company, LLC 1504 3rd Avenue 4300 Winfield Road Rock Island County Office Bldg. Warrenville, Illinois 60555 Rock Island, Illinois 61201 Mr. Christopher Crane Regional Administrator Senior Vice President U.S. NRC, Region III Mid-West Regional Operating Group 801 Warrenville Road Exelon Generation Company, LLC Lisle, Illinois 60532-4351 4300 Winfield Road Warrenville, Illinois 60555 Illinois Department of Nuclear Safety Office of Nuclear Facility Safety Mr. Jeffrey Benjamin 1035 Outer Park Drive Vice President - Licensing and Regulatory Springfield, Illinois 62704 Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, Illinois 60555
LaSalle, Units 1 and 2 cc:
Mr. K. A. Ainger Director - Licensing Mid-West Regional Operating Group Exelon Generation Company, LLC 4300 Winfield Road Warrenville, Illinois 60555 Mr. Robert Helfrich Senior Counsel, Nuclear Mid-West Regional Operating Group Exelon Generation Company, LLC 4300 Winfield Road Warrenville, Illinois 60555
O. Kingsley February 25, 2002 The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD3-2 WMacon CRosenberg SBajwa AMendiola RidsRgn3MailCenter Accession No. ML020490062 (Package)
Accession No. ML020 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY
CNO Heading The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No(s).
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD Reading Project Director Section Chief Project Manager Licensing Assistant Region Contact Accession No. ML020520754 (Package)
Accession No. ML020510637 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY