SAFEGUARDS INFORMATION February 25, 2002 Oliver D. Kingsley, Jr.
President and Chief Nuclear Officer Limerick Generating Station, Units 1 & 2 Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
ISSUANCE OF ORDER FOR INTERIM SAFEGUARDS AND SECURITY COMPENSATORY MEASURES FOR - LIMERICK GENERATING STATION, UNITS 1 & 2
Dear Mr. Kingsley:
The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Order that modifies the current operating license for your facility to require compliance with the specified interim safeguards and security compensatory measures. The Order applies to all Addressees listed in to the enclosed Order. These interim compensatory measures are listed in (contains Safeguards Information) to the enclosed Order. The Commission recognizes that you have voluntarily and responsibly implemented additional security measures following the events of September 11, 2001, but, in light of the continuing generalized high-level threat environment, the Commission concludes that the security measures should be embodied in an Order, consistent with the established regulatory framework. The Commission has determined that the generalized high-level threat environment requires that the enclosed Order be effective immediately.
These actions are interim and the basis for the Order is the need to take prudent actions to address security requirements in the present generalized high-level threat environment. This Order does not obviate the need for licensees to continue to meet the objectives of Security Level III described in NRC Information Notice 98-35, and maintain the effectiveness of existing security measures taken in response to the events of September 11, 2001. The requirements will remain in effect pending notification from the Commission that a significant change in the threat environment has occurred, or until the Commission determines that other changes are needed following a more comprehensive re-evaluation of current safeguards and security programs.
The enclosed Order calls for responses and actions within specified time frames. Please contact your Licensing Project Manager to facilitate resolution of any issues related to compliance with the requirements in the enclosed Order, or if you have any other questions.
NOTICE: Attachment 2 to the Order (Interim Compensatory Measures) contains "Safeguards Information." Upon separation of Attachment 2 to the Order, this letter, the enclosed Order, and Attachment 1 to the Order (Address List) are "DECONTROLLED."
SAFEGUARDS INFORMATION
O. Kingsley The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page
Limerick Generating Station, Units 1 & 2 cc:
Edward J. Cullen, Jr.
Vice President & General Counsel Exelon Generation Company, LLC 300 Exelon Way Kennett Square, PA 19348 Manager-Limerick Licensing Exelon Generation Company, LLC Nuclear Group Headquarters Correspondence Control P.O. Box 160 Kennett Square, PA 19348 Mr. William Levis, Site Vice President Limerick Generating Station P.O. Box 2300 Sanatoga, PA 19464 Mr. R. Braun Plant Manager Limerick Generating Station P.O. Box 2300 Sanatoga, PA 19464 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Senior Resident Inspector U.S. Nuclear Regulatory Commission Limerick Generating Station P.O. Box 596 Pottstown, PA 19464 Chairman Board of Supervisors of Limerick Township 646 West Ridge Pike Linfield, PA 19468 Chief-Division of Nuclear Safety PA Dept. of Environmental Resources P.O. Box 8469 Harrisburg, PA 17105-8469 Library U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803 Mr. Jeffrey A. Benjamin Licensing - Vice President Exelon Corporation 1400 Opus Place, Suite 900 Downers Grove, IL 60515 Mr. Michael P. Gallagher Director-Licensing Exelon Generation Company, LLC Nuclear Group Headquarters Correspondence Control P. O. Box 160 Kennett Square, PA 19348 Correspondence Control Desk Exelon Generation Company, LLC 200 Exelon Way, KSA 1-N-1 Kennett Square, PA 19348 Mr. John Skolds Chief Operating Officer Exelon Generation Company, LLC 1400 Opus Place, Suite 900 Downers Grove, IL 60515 Mr. William Bohlke Senior Vice President, Nuclear Services Exelon Generation Company, LLC 1400 Opus Place, Suite 900 Downers Grove, IL 60515
Limerick Generating Station, Units 1 & 2 cc:
Mr. John Cotton Senior Vice President, Operations Support Exelon Generation Company, LLC 1400 Opus Place, Suite 900 Downers Grove, IL 60515 Mr. Joseph Hagan Senior Vice President Mid-Atlantic Regional Operating Group Exelon Generation Company, LLC 200 Exelon Way, KSA 3-N Kennett Square, PA 19348 Ms. K. Gallogly Regulatory Assurance Manager Limerick Generating Station P.O. Box 2300 Sanatoga, PA 19464
O. Kingsley February 25, 2002 The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD1-2 CGratton MO'Brien EAdensam JClifford RidsRgn1MailCenter Accession No. ML020490015 (Package)
Accession No. ML020 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY
CNO Heading The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No(s).
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD Reading Project Director Section Chief Project Manager Licensing Assistant Region Contact Accession No. ML020520754 (Package)
Accession No. ML020510637 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY