Letter Sequence Approval |
---|
|
|
MONTHYEARML0205805262002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Security Compensatory Measures Project stage: Approval ML0205103332002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0205006202002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0205005562002-02-25025 February 2002 Issuance of Order for Compensatory Security Measures Project stage: Approval ML0205004012002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0205001952002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Security Compensatory Measures Project stage: Approval ML0205002072002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0205001842002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Security Compensatory Measures Project stage: Approval ML0204900772002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Compensatory Security Measures Project stage: Approval ML0204900742002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Security Compensatory Measures Project stage: Approval ML0213002552002-05-20020 May 2002 Meeting Summary with Exelon Generation Company, LLC to Discuss Exelon'S Response to Interim Compensatory Measure Project stage: Meeting ML0213002162002-05-23023 May 2002 Amergen Energy Co, LLC - Reply to Response to Order for Interim Safeguards and Security Compensatory Measures Project stage: Other ML0217108392002-07-18018 July 2002 Alternative Proposal for Compliance with Interim Compensatory Measure B.4.e Pertaining to Owner Controlled Area Patrols at Exelon Sites Project stage: Other ML0223208932002-08-29029 August 2002 Reply to Response to Order for Interim Safeguards and Security Compensatory Measures at Exelon Sites Project stage: Other 2002-05-23
[Table View] |
Similar Documents at Byron |
---|
Category:Letter
MONTHYEARIR 05000454/20230042024-02-0202 February 2024 Integrated Inspection Report 05000454/2023004 and 05000455/2023004 ML24022A2722024-01-23023 January 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000454/2024011 ML24018A0362024-01-17017 January 2024 Paragon Energy Solutions, Defect with Detroit Diesel/Mtu Fuel Injectors P/N R5229660 Cat Id 0001390618 ML23320A1762023-12-13013 December 2023 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0027 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23277A0032023-12-11011 December 2023 Issuance of Amendments Regarding Adoption of TSTF-370 ML23318A5102023-12-0101 December 2023 Relief from the Requirements of the ASME Code IR 05000454/20233012023-11-27027 November 2023 NRC Initial License Examination Report 05000454/2023301 and 05000455/2023301 BYRON 2023-0065, Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline2023-11-17017 November 2023 Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline BYRON 2023-0063, Day Inservice Inspection Report for Interval 4, Period 3, (B2R24)2023-11-16016 November 2023 Day Inservice Inspection Report for Interval 4, Period 3, (B2R24) IR 05000454/20230032023-11-13013 November 2023 Integrated Inspection Report 05000454/2023003 and 05000455/2023003 and Exercise of Enforcement Discretion RS-23-117, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23313A0852023-11-0909 November 2023 Submittal of 2023-301 Byron Initial License Examination Post-Examination Comments RS-23-114, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2023-11-0101 November 2023 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML23297A2352023-10-26026 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection RS-23-100, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23278A0272023-10-0505 October 2023 Operator Licensing Examination Approval - Byron Station, October 2023 RS-23-093, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel.2023-09-29029 September 2023 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel. ML23251A1622023-09-29029 September 2023 Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements RS-23-094, Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 752023-09-29029 September 2023 Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 75 RS-23-091, Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals2023-09-26026 September 2023 Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals ML23226A0062023-09-19019 September 2023 Review of License Renewal Commitment Number 10 Submittal ML23180A1692023-09-11011 September 2023 Calvert Cliff Units 1 & 2, and R.E. Ginna Plant - Withdrawal of Proposed Alternatives to American Society of Mechanical Engineers (ASME) Requirements (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23242A3282023-09-0101 September 2023 Amendment No. 233 Correction IR 05000454/20235012023-08-31031 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000454/2023501 and 05000455/2023501 IR 05000454/20230052023-08-30030 August 2023 Updated Inspection Plan for Byron Station (Report 05000454/2023005 and 05000455/2023005) IR 05000454/20230022023-08-0303 August 2023 Integrated Inspection Report 05000454/2023002 and 05000455/2023002 ML23209A7242023-07-31031 July 2023 Request for Information on the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000454/2024010 and 05000455/2024010 ML23192A0362023-07-25025 July 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report ML23122A3022023-07-20020 July 2023 Issuance of Amendments Technical Specifications 2.1.1 and 4.2.1 to Allow a Previously Irradiated Accident Tolerant Fuel Lead Test Assembly to Be Further Irradiated in Unit No. 2 IR 05000454/20234022023-07-18018 July 2023 Baseline Security Inspection Document; 05000454/2023402; 05000455/2023402 ML23198A0372023-07-17017 July 2023 Information Request to Support Upcoming Problem Identification and Resolution (PIR) Inspection at Byron Nuclear Plant ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators ML23172A1172023-06-22022 June 2023 Notification of NRC Fire Protection Team Inspection Request for Information RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23159A1302023-06-0808 June 2023 Day Inservice Inspection Report for Interval 4, Period 3, (B1R25) ML23159A1542023-06-0808 June 2023 2022 Regulatory Commitment Change Summary Report RS-23-075, Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process2023-06-0707 June 2023 Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process ML23157A2832023-06-0606 June 2023 Notification of NRC Baseline Inspection and Request for Information BYRON 2023-0029, Response to Request for Additional Information Regarding Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements2023-06-0101 June 2023 Response to Request for Additional Information Regarding Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements ML23138A1342023-05-18018 May 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Braidwood Station and Byron Station ML23003A7882023-05-11011 May 2023 Report for December 12-16, 2022, Regulatory Audit Regarding Reinsertion of a High Burnup Accident Tolerant Fuel Lead Test Assembly 2024-02-02
[Table view] |
Text
SAFEGUARDS INFORMATION February 25, 2002 Oliver D. Kingsley, Jr.
President and Chief Nuclear Officer Byron Station, Units 1 & 2 Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
ISSUANCE OF ORDER FOR INTERIM SAFEGUARDS AND SECURITY COMPENSATORY MEASURES FOR - BYRON STATION, UNITS 1 & 2
Dear Mr. Kingsley:
The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Order that modifies the current operating license for your facility to require compliance with the specified interim safeguards and security compensatory measures. The Order applies to all Addressees listed in to the enclosed Order. These interim compensatory measures are listed in (contains Safeguards Information) to the enclosed Order. The Commission recognizes that you have voluntarily and responsibly implemented additional security measures following the events of September 11, 2001, but, in light of the continuing generalized high-level threat environment, the Commission concludes that the security measures should be embodied in an Order, consistent with the established regulatory framework. The Commission has determined that the generalized high-level threat environment requires that the enclosed Order be effective immediately.
These actions are interim and the basis for the Order is the need to take prudent actions to address security requirements in the present generalized high-level threat environment. This Order does not obviate the need for licensees to continue to meet the objectives of Security Level III described in NRC Information Notice 98-35, and maintain the effectiveness of existing security measures taken in response to the events of September 11, 2001. The requirements will remain in effect pending notification from the Commission that a significant change in the threat environment has occurred, or until the Commission determines that other changes are needed following a more comprehensive re-evaluation of current safeguards and security programs.
The enclosed Order calls for responses and actions within specified time frames. Please contact your Licensing Project Manager to facilitate resolution of any issues related to compliance with the requirements in the enclosed Order, or if you have any other questions.
NOTICE: Attachment 2 to the Order (Interim Compensatory Measures) contains "Safeguards Information." Upon separation of Attachment 2 to the Order, this letter, the enclosed Order, and Attachment 1 to the Order (Address List) are "DECONTROLLED."
SAFEGUARDS INFORMATION
O. Kingsley The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket Nos. 50-454 and 50-455
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page
Byron Stations cc:
Ms. C. Sue Hauser, Project Manager Attorney General Westinghouse Electric Corporation 500 S. Second Street Energy Systems Business Unit Springfield, Illinois 62701 Post Office Box 355 Pittsburgh, Pennsylvania 15230 Illinois Department of Nuclear Safety Office of Nuclear Facility Safety Joseph Gallo 1035 Outer Park Drive Gallo & Ross Springfield, Illinois 62704 1025 Connecticut Ave., NW, Suite 1014 Washington, DC 20036 Exelon Generation Company, LLC Byron Station Manager Howard A. Learner 4450 N. German Church Road Environmental Law and Policy Byron, Illinois 61010-9794 Center of the Midwest 35 East Wacker Dr., Suite 1300 Exelon Generation Company, LLC Chicago, Illinois 60601-2110 Site Vice President - Byron 4450 N. German Church Road U.S. Nuclear Regulatory Commission Byron, Illinois 61010-9794 Byron Resident Inspectors Office 4448 N. German Church Road U.S. Nuclear Regulatory Commission Byron, Illinois 61010-9750 Braidwood Resident Inspectors Office 35100 S. Rt. 53, Suite 79 Regional Administrator, Region III Braceville, Illinois 60407 U.S. Nuclear Regulatory Commission 801 Warrenville Road Illinois Emergency Management Lisle, Illinois 60532-4351 Agency Division of Disaster Assistance &
Ms. Lorraine Creek Preparedness RR 1, Box 182 110 East Adams Street Manteno, Illinois 60950 Springfield, Illinois 62701-1109 Chairman, Ogle County Board Chairman Post Office Box 357 Will County Board of Supervisors Oregon, Illinois 61061 Will County Board Courthouse Joliet, Illinois 60434 Mrs. Phillip B. Johnson 1907 Stratford Lane Exelon Generation Company, LLC Rockford, Illinois 61107 Braidwood Station Manager 35100 S. Rt. 53, Suite 84 George L. Edgar Braceville, Illinois 60407-9619 Morgan, Lewis and Bockius 1800 M Street, NW Washington, DC 20036-5869
Byron Stations Ms. Bridget Little Rorem Exelon Generation Company, LLC Appleseed Coordinator Regulatory Assurance Supervisor - Braidwood 117 N. Linden Street 35100 S. Rt. 53, Suite 84 Essex, Illinois 60935 Braceville, Illinois 60407-9619 Document Control Desk-Licensing Exelon Generation Company, LLC Exelon Generation Company, LLC Regulatory Assurance Supervisor - Byron 4300 Winfield Road 4450 N. German Church Road Warrenville, Illinois 60555 Byron, Illinois 61010-9794 Exelon Generation Company, LLC Mr. Robert Helfrich Site Vice President - Braidwood Senior Counsel, Nuclear 35100 S. Rt. 53, Suite 84 Mid-West Regional Operating Group Braceville, Illinois 60407-9619 Exelon Generation Company, LLC 4300 Winfield Road Mr. William Bohlke Warrenville, Illinois 60555 Senior Vice President, Nuclear Services Exelon Generation Company, LLC Mr. Jeffrey Benjamin 4300 Winfield Road Vice President - Licensing and Warrenville, Illinois 60555 Regulatory Affairs Exelon Generation Company, LLC Mr. Robert J. Hovey 4300 Winfield Road Operations Vice President Warrenville, Illinois 60555 Mid-West Regional Operating Group Exelon Generation Company, LLC Mr. John Skolds 4300 Winfield Road Chief Operating Officer Warrenville, Illinois 60555 Exelon Generation Company, LLC 4300 Winfield Road Mr. Christopher Crane Warrenville, Illinois 60555 Senior Vice President Mid-West Regional Operating Group Mr. John Cotton Exelon Generation Company, LLC Senior Vice President - Operations Support 4300 Winfield Road Exelon Generation Company, LLC Warrenville, Illinois 60555 4300 Winfield Road Warrenville, Illinois 60555 Mr. K. A. Ainger Director - Licensing Mid-West Regional Operating Group Exelon Generation Company, LLC 4300 Winfield Road Warrenville, Illinois 60555
O. Kingsley The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No(s).
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD3-2 R/F SBajwa AMendiola GDick CRosenberg RidsRgn3MailCenter Accession No. ML020490053 (Package)
Accession No. ML02 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY
CNO Heading The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No(s).
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD Reading Project Director Section Chief Project Manager Licensing Assistant Region Contact Accession No. ML020520754 (Package)
Accession No. ML020510637 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY