Update of Evacuation Time Estimates
ML012070310
Person / Time
Issue date: 08/01/2001
From: Matthews D
Division of Regulatory Improvement Programs
To:
References
TAC MB2092 RIS-01-016
Download: ML012070310 (4)


UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

WASHINGTON, D.C. 20555-0001 August 1, 2001 NRC REGULATORY ISSUE SUMMARY 2001-16 UPDATE OF EVACUATION TIME ESTIMATES

ADDRESSEES

All holders of operating licenses for nuclear power plants.

INTENT

The U.S. Nuclear Regulatory Commission (NRC) is issuing this Regulatory Issue Summary (RIS) to alert addressees to the possible need to update emergency planning evacuation time estimates as the results of the year 2000 census are published. This RIS does not transmit any new requirements or staff positions. No specific action or written response is required.

BACKGROUND INFORMATION

Addressees

are required to follow and maintain in effect emergency plans which meet the standards in Section 10 CFR 50.47(b) and the requirements of 10 CFR Part 50 Appendix E.

The requirements concerning emergency plan changes are found in Section 10 CFR 50.54(q).

This regulation allows a licensee to change its emergency plan without Commission approval provided that the change does not decrease the effectiveness of the plan and the plan, as changed, continues to meet the planning standards of Section 10 CFR 50.47(b) and the requirements of 10 CFR Part 50 Appendix E. Updating evacuation time estimates would not be considered a decrease in the effectiveness of the emergency plan under Section 10 CFR 50.54(q) and licensees may update the estimates without prior Commission approval.

Additionally,Section IV.G of Appendix E requires licensees to have provisions in these emergency plans to ensure that the emergency plan and its implementing procedures are kept up to date and that emergency equipment and supplies are properly maintained. Since the emergency plan is contained in the Final Safety Analysis Report in accordance with 10 CFR 50

Appendix E Section III, the updating requirements of 10 CFR 50.71(e) apply.

Guidance on evacuation time estimates is in Section J.8, 10l, 10m, and Appendix 4 of NUREG-0654, Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants. This guidance was endorsed by NRC Regulatory Guide 1.101, Rev 2. Additional information can be found in NUREG/CR-

4831, The State of the Art in Evacuation Time Estimate Studies for Nuclear Power Plants, March 1992.

SUMMARY OF ISSUE

S

Recently published results of the year 2000 census show increases or decreases in population within the plume exposure pathway emergency planning zone around certain nuclear power facilities. Consequently, the estimated times for evacuation of the public could increase or decrease. Longer or shorter evacuation times in turn affect decisions about evacuating the public in the event of a radiological emergency. Therefore, decision makers may need updated estimates of how long it would take to evacuate the public.

BACKFIT DISCUSSION

This RIS does not require any action or written response nor does it require any modification to plant structures, systems, components or design of facilities; therefore, the staff did not perform a backfit analysis.

Federal Register Notification

A notice of opportunity for public comment was not published in the Federal Register because this RIS is informational and pertains to a staff position that does not represent a departure from current regulatory requirements and practice.

PAPERWORK REDUCTION ACT STATEMENT

This RIS does not request any information collection.

If you have any question about this matter, please contact the person listed below or the appropriate Office of Nuclear Reactor Regulation (NRR) project manager.

/RA Frank P. Gillespie Acting for/

David B. Matthews, Director Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Technical contact: Edwin F. Fox, Jr., NRR

301-415-2908 E-mail: eff@nrc.gov Attachment: List of Recently Issued NRC Regulatory Issue Summaries NRC Regulatory Guide 1.101, Rev 2. Additional information can be found in NUREG/CR-

4831, The State of the Art in Evacuation Time Estimate Studies for Nuclear Power Plants, March 1992.

SUMMARY OF ISSUE

S

Recently published results of the year 2000 census show increases or decreases in population within the plume exposure pathway emergency planning zone around certain nuclear power facilities. Consequently, the estimated times for evacuation of the public could increase or decrease. Longer or shorter evacuation times in turn affect decisions about evacuating the public in the event of a radiological emergency. Therefore, decision makers may need updated estimates of how long it would take to evacuate the public.

BACKFIT DISCUSSION

This RIS does not require any action or written response nor does it require any modification to plant structures, systems, components or design of facilities; therefore, the staff did not perform a backfit analysis.

Federal Register Notification

A notice of opportunity for public comment was not published in the Federal Register because this RIS is informational and pertains to a staff position that does not represent a departure from current regulatory requirements and practice.

PAPERWORK REDUCTION ACT STATEMENT

This RIS does not request any information collection.

If you have any question about this matter, please contact the person listed below or the appropriate Office of Nuclear Reactor Regulation (NRR) project manager.

/RA Frank P. Gillespie Acting for/

David B. Matthews, Director Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Technical contact: Edwin F. Fox, Jr., NRR

301-415-2908 E-mail: eff@nrc.gov Attachment: List of Recently Issued NRC Regulatory Issue Summaries Distribution: RIS Reading File PUBLIC FEMA

ADAMS DOCUMENT TITLE:C:\Program Files\Adobe\Acrobat 4.0\PDF

Output\RISupdatingETE-Fox.wpd ADAMS ACCESSION NUMBER: ML012070310 TEMPLATE#: NRR-052 OFFICE IOLB TECH EDITOR SC:IOLB FEMA C:IOLB REXB

NAME EFox* PKleene* KGibson* Telecom* GTracy*kag EFields*

DATE 07/03/2001 06/12/2001 07/03/2001 07/19/2001 07/03/2001 07/26/2001 OFFICE SC:REXB C:REXB DRIP

NAME JTappert* LMarsh/jrt* DMatthews DATE 07/31/2001 07/31/2001 / /2001

OFFICIAL RECORD COPY

Attachment LIST OF RECENTLY ISSUED

NRC REGULATORY ISSUE SUMMARIES

_____________________________________________________________________________________

Regulatory Issue Date of Summary No. Subject Issuance Issued to

_____ _______________________________________________________________________________

2001-15 Performance of DC-Powered 08/01/2001 All holders of operating licenses Motor-Operated Valve Actuators for nuclear power reactors, except those who have permanently ceased operations and have certified that fuel has been permanently removed from the reactor vessel

2001-14 Position on Reportability 07/19/2001 All holders of boiling-water (BWR)

Requirements for Reactor Core operating licenses Isolation Cooling System Failure

2001-13 10 CFR Part Exemptions for 07/20/2001 All holders of licenses authorized Uranium Contained in Aircraft to manufacture aircraft Counterweights counterweights containing uranium, and organizations and end users who may possess such counterweights

2001-12 Nonconservatism in Pressurized 05/11/2001 All holders of operating licenses Water Reactor Spent Fuel Storage for pressurized water reactors Pool Reactivity Equivalencing Calculations

2001-11 Voluntary Submission of 05/18/2001 All holders of operating licenses Performance Indicator Data for nuclear power reactors, except those who have permanently ceased operations and have certified that fuel has been permanently removed from the reactor vessel

2001-10 Revisions to Staff Guidance on 04/02/2001 All holders of operating licenses Notices of Enforcement Discretion for nuclear power reactors, except those who have permanently ceased operations and have certified that fuel has been permanently removed from the reactor vessel

______________________________________________________________________________________

OL = Operating License CP = Construction Permit