MONTHYEARL-MT-24-038, Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI2024-10-15015 October 2024 Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI L-MT-24-025, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2024-09-26026 September 2024 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements L-MT-24-029, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI2024-09-13013 September 2024 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI L-MT-24-028, Response to RCI for RR-017 ISI Impracticality2024-08-28028 August 2024 Response to RCI for RR-017 ISI Impracticality L-MT-24-022, – Preparation and Scheduling of Operator Licensing Examinations2024-07-0909 July 2024 – Preparation and Scheduling of Operator Licensing Examinations L-MT-24-019, Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii)2024-06-10010 June 2024 Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii) L-MT-24-017, Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-01602024-06-0404 June 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-0160 L-MT-24-015, Response to Request for Additional Information - Alternative Request VR-09 for OMN-172024-05-16016 May 2024 Response to Request for Additional Information - Alternative Request VR-09 for OMN-17 L-MT-24-013, 2023 Annual Radiological Environmental Operating Report2024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report L-MT-24-016, 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2024-05-0808 May 2024 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) L-MT-24-002, Submittal of Revision 41 to the Updated Safety Analysis Report2024-04-17017 April 2024 Submittal of Revision 41 to the Updated Safety Analysis Report L-MT-24-004, Submittal of 10 CFR 72.48 Report for Monticello Nuclear Generating Plant (MNGP)2024-04-17017 April 2024 Submittal of 10 CFR 72.48 Report for Monticello Nuclear Generating Plant (MNGP) L-MT-24-006, Subsequent License Renewal Application Annual Update 1 and Supplement 92024-02-29029 February 2024 Subsequent License Renewal Application Annual Update 1 and Supplement 9 L-MT-24-007, Response to NRC Request for Additional Information on Proposed Inservice Inspection Alternative RR-002 for the Sixth Ten-Year ISI Interval2024-02-15015 February 2024 Response to NRC Request for Additional Information on Proposed Inservice Inspection Alternative RR-002 for the Sixth Ten-Year ISI Interval L-MT-24-001, 10 CFR 50.55a Request RR-017 - Inservice Inspection (ISI) Impracticality in Accordance with 10 CFR 50.55a(g)(5)(iii) During the Fifth Ten-Year Interval2024-01-30030 January 2024 10 CFR 50.55a Request RR-017 - Inservice Inspection (ISI) Impracticality in Accordance with 10 CFR 50.55a(g)(5)(iii) During the Fifth Ten-Year Interval L-MT-23-054, Subsequent License Renewal Application Supplement 82024-01-11011 January 2024 Subsequent License Renewal Application Supplement 8 L-MT-23-047, License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data2023-12-29029 December 2023 License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data L-MT-23-056, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 22023-12-18018 December 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 2 L-MT-23-042, 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462023-12-11011 December 2023 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 L-MT-23-053, Condition Prohibited by Technical Specifications Due to Inoperable Main Steam Line Low Pressure Isolation Switch2023-12-0404 December 2023 Condition Prohibited by Technical Specifications Due to Inoperable Main Steam Line Low Pressure Isolation Switch L-MT-23-052, Subsequent License Renewal Application Supplement 72023-11-30030 November 2023 Subsequent License Renewal Application Supplement 7 L-MT-23-051, Update to the Technical Specification Bases2023-11-28028 November 2023 Update to the Technical Specification Bases L-MT-23-049, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 12023-11-21021 November 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 L-MT-23-043, 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-092023-11-13013 November 2023 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-09 L-MT-23-038, License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.62023-11-10010 November 2023 License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 L-MT-23-046, Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 12023-11-0909 November 2023 Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 1 L-MT-23-041, Subsequent License Renewal Application Response to Request for Confirmation of Information Set 22023-10-0303 October 2023 Subsequent License Renewal Application Response to Request for Confirmation of Information Set 2 L-MT-23-037, Subsequent License Renewal Application Response to Request for Additional Information Set 32023-09-22022 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 3 L-MT-23-036, Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 62023-09-0505 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 6 L-MT-23-035, Subsequent License Renewal Application Supplement 52023-08-28028 August 2023 Subsequent License Renewal Application Supplement 5 L-MT-23-034, Subsequent License Renewal Application Response to Request for Additional Information Set 12023-08-15015 August 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 1 L-MT-23-032, 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-112023-07-31031 July 2023 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-11 L-MT-23-028, 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report2023-07-31031 July 2023 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report L-MT-23-031, Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 12023-07-18018 July 2023 Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 1 L-MT-23-030, Subsequent License Renewal Application Supplement 32023-07-0404 July 2023 Subsequent License Renewal Application Supplement 3 L-MT-23-025, Subsequent License Renewal Application Supplement 22023-06-26026 June 2023 Subsequent License Renewal Application Supplement 2 L-MT-23-019, Submittal of 2022 Annual Radiological Environmental Operating Report2023-05-10010 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report L-MT-23-020, Submittal of 2022 Annual Radioactive Effluent Release Report2023-05-10010 May 2023 Submittal of 2022 Annual Radioactive Effluent Release Report L-MT-23-021, Core Operating Limits Report (COLR) for the Monticello Nuclear Generating Plant for Cycle 322023-05-0202 May 2023 Core Operating Limits Report (COLR) for the Monticello Nuclear Generating Plant for Cycle 32 L-MT-23-017, 2022 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2023-04-18018 April 2023 2022 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) L-MT-23-010, Subsequent License Renewal Application Supplement 12023-04-0303 April 2023 Subsequent License Renewal Application Supplement 1 L-MT-23-013, Core Operating Limits Report (COLR) for Cycle 31, Revision 32023-03-28028 March 2023 Core Operating Limits Report (COLR) for Cycle 31, Revision 3 L-MT-23-012, Core Operating Limits Report (COLR) for Monticello Nuclear Generating Plant Cycle 31, Revision 22023-03-17017 March 2023 Core Operating Limits Report (COLR) for Monticello Nuclear Generating Plant Cycle 31, Revision 2 L-MT-23-008, 10CFR50.55a Request to Use Later Edition of ASME Section XI for ISI Code of Record (RR-003)2023-02-0707 February 2023 10CFR50.55a Request to Use Later Edition of ASME Section XI for ISI Code of Record (RR-003) L-MT-23-004, CFR 50.55a Request RR-001, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI for the Monticello Third Interval Containment Inservice Inspection Program2023-01-23023 January 2023 CFR 50.55a Request RR-001, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI for the Monticello Third Interval Containment Inservice Inspection Program L-MT-23-005, Response to the NRC Request for Additional Information Regarding the 50.55a Request Pr 08, HPCI Pump Quarterly Testing (EPID Number L-2022-LLR-0088)2023-01-0606 January 2023 Response to the NRC Request for Additional Information Regarding the 50.55a Request Pr 08, HPCI Pump Quarterly Testing (EPID Number L-2022-LLR-0088) L-MT-22-049, Industry Groundwater Protection Initiative Special Report2022-12-15015 December 2022 Industry Groundwater Protection Initiative Special Report L-MT-22-052, L-MT-22-052 Monticello Nuclear Generating Plant 10 CFR 50.55a Request No. Pr 08, Request for HPCI Pump Quarterly Alternative2022-12-15015 December 2022 L-MT-22-052 Monticello Nuclear Generating Plant 10 CFR 50.55a Request No. Pr 08, Request for HPCI Pump Quarterly Alternative L-MT-22-046, 2022 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462022-12-13013 December 2022 2022 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 L-MT-22-048, Update to the Monticello Technical Specification Bases2022-11-28028 November 2022 Update to the Monticello Technical Specification Bases 2024-09-26
[Table view] |
Text
2807 West County Road 75 Monticello, MN 55362 (l Xcel Energy*
RESPONSIBLE BY NATURE ~
800.895.4999 xcelenergy.com June 1, 2018 L-MT-18-031 EA-14-193 ATTN: Director - Division of Nuclear Materials Safety U.S. Nuclear Regulatory Commission 2443 Warrenville Road Suite 210 Lisle, IL 60532-4352 Monticello Nuclear Generating Plant Docket No. 50-263 Renewed Facility Operating License No. DPR-22 Independent Spent Fuel Storage Installation Docket No. 72-58 Project Plan Progress Update toward Restoring 10 CFR 72 Compliance to Dry Shielded Canisters Designated 11 through 16
References:
- 1) NRC letter to NSPM, Confirmatory Order Related to NRC Reports No.
05000263/2015008; 07200058/2014001 and OI Report 3-2014-004; Monticello Nuclear Generating Plant, dated December 21, 2015 (ADAMS Accession No. ML15355A459)
- 2) NSPM letter to NRC, Project Plan for Restoring 10 CFR 72 Compliance to Dry Shielded Canisters Designated 11 through 16, dated December 12, 2016 (ADAMS Accession No. ML16347A295)
- 3) NSPM letter to NRC, Project Plan Progress Toward Restoring 10 CFR 72 Compliance to Dry Shielded Canisters Designated 11 through 16, dated June 6, 2017 (ADAMS Accession No. ML17157B356)
- 4) NSPM letter to NRC, Exemption Request for Nonconforming Dye Penetrant Examinations of Dry Shielded Canisters (DSCs) 11 through 15, dated October 18, 2017 (ADAMS Accession No. ML17296A205)
- 5) NRC letter to NSPM, First Request for Additional Information for Review of Exemption Request for Five Nonconforming Dry Shielded Canisters 11 through 15 (CAC No. 001028, Docket No. 72-58, EPID L-2017-LLE-0029),
dated March 6, 2018 (ADAMS Accession No. ML18065A545)
- 6) NSPM letter to NRC, Response to Request for Additional Information Regarding Exemption Request for Nonconforming Dye Penetrant Examinations of Dry Shielded Canisters (DSCs) 11 through 15 (CAC No.
001028, EPID L-2017-LLE-0029), dated April 5, 2018 (ADAMS Accession No. ML18100A183)
Director - Division of Nuclear Materials Safety Page 2
- 7) NRC email to NSPM, Monticello Exemption: NRC Clarification Questions on RAI #1 Responses, dated May 1, 2018 (ADAMS Accession No. ML18121A250)
- 8) NRC Conversation Record, Clarification Call with Xcel Energy (XE) on RAI #1 Response in Regard to Monticello Exemption Request for DSCs 11-15, dated May 14, 2018 (ADAMS Accession No. ML18134A323)
- 9) NSPM letter to NRC, Supplement to Exemption Request for Nonconforming Dye Penetrant Examinations of Dry Shielded Canisters (DSCs) 11 through 15 (CAC No. 001028, EPID L-2017-LLE-0029), dated May 31, 2018 (ADAMS Accession No. ML18151A870)
Pursuant to Confirmatory Order EA-14-193 (Reference 1), Northern States Power Company, a Minnesota corporation (NSPM), doing business as Xcel Energy, provided in Reference 2 a project plan for restoring 10 CFR 72 compliance to dry shielded canisters (DSCs) designated 11 through 16 at the Monticello Nuclear Generating Plant.
Action 3 of the Confirmatory Order requires the following:
Within 180 days after submittal of the DSCs 11 through 16 project plan, Xcel Energy shall submit a letter to the Director, DNMS, Region III, regarding progress under the plan and any non-editorial changes to the plan. A letter providing a progress update and any non-editorial changes shall be provided every 360 calendar days thereafter to the Director, DNMS, Region III, until the plan is completed.
Reference 3 provided the initial 180 day progress letter on the project plan. At the time the progress letter was submitted, NSPM anticipated submitting an exemption request for DSCs 11-15 as early as September 2017. Following input from multiple experts regarding structural, risk, and dose considerations for development of the exemption request, NSPM submitted the request on October 18, 2017 (Reference 4).
The exemption request is currently under review by NRC staff. NSPM received a Request for Additional Information (RAI) on March 6, 2018 (Reference 5), and provided a response to the RAI on April 5, 2018 (Reference 6). Subsequently, the NRC provided clarifying questions in regard to NSPMs RAI response on May 1, 2018 (Reference 7). Those questions were discussed during a teleconference between NSPM and members of the NRC staff on May 10, 2018 (Reference 8). During the teleconference, NSPM agreed to supplement its RAI response in Reference 6. That supplement was provided on May 31, 2018 (Reference 9).
The project plan detailed in Reference 2 and updated by Reference 3 continues on track for restoring 10 CFR 72 compliance for DSCs 11-15 by March 2020, as identified in the project plan.
If additional information is required, please contact Mr. Shane Jurek at (612) 330-5788.
Director - Division of Nuclear Materials Safety Page 3 Summary of Commitments new commitments and no revisions to existing commitments .
. O'Connor Senio ice President and Chief Nuclear Officer North rn States Power Company - Minnesota cc: Document Control Desk, USNRC Administrator, Region Ill, USNRC Deputy Regional Administrator, Region Ill, USNRC NRR Project Manager, Monticello Nuclear Generating Plant, USNRC NMSS Project Manager, Spent Fuel Management, USNRC Resident Inspector, Monticello, USNRC Director, Office of Nuclear Material Safety and Safeguards, USNRC Director, Office of Nuclear Reactor Regulation, USNRC Director, Division of Spent Fuel Management, USNRC Enforcement/Investigations Officer, Region Ill, USNRC Regional Counsel, Region Ill, USNRC Peter Glass, Xcel Energy Jay Silberg, Pillsbury Law