MONTHYEARL-2024-184, Radiological Emergency Plan Revision 772024-11-0505 November 2024 Radiological Emergency Plan Revision 77 L-2024-173, Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-31031 October 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums L-2024-175, Cycle 34 Core Operating Report2024-10-24024 October 2024 Cycle 34 Core Operating Report L-2024-177, Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis2024-10-22022 October 2024 Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-157, Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-0303 October 2024 Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles L-2024-147, Submission of Periodic Reports2024-10-0101 October 2024 Submission of Periodic Reports L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-106, Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-022024-08-12012 August 2024 Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-02 L-2024-122, Core Operating Limits Report2024-08-12012 August 2024 Core Operating Limits Report L-2024-089, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-07-25025 July 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-100, Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project2024-06-19019 June 2024 Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update L-2024-076, Reply to Notice of Violation; NOV 05000250, 05000251/2024010-052024-05-29029 May 2024 Reply to Notice of Violation; NOV 05000250, 05000251/2024010-05 L-2024-082, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report L-2024-060, 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report2024-05-0909 May 2024 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report L-2024-073, Cycle 34 Core Operating Limits Report2024-05-0101 May 2024 Cycle 34 Core Operating Limits Report L-2024-072, Cycle 33 Core Operating Limits Report2024-05-0101 May 2024 Cycle 33 Core Operating Limits Report L-2024-048, Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision2024-04-30030 April 2024 Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision L-2024-069, Radiological Emergency Plan Revision 762024-04-22022 April 2024 Radiological Emergency Plan Revision 76 L-2024-066, Sixth 10-Year Inservice Testing Interval Relief Request No. PR-022024-04-17017 April 2024 Sixth 10-Year Inservice Testing Interval Relief Request No. PR-02 L-2024-047, Proposed Use of a Subsequent ASME Code Edition and Addenda2024-03-28028 March 2024 Proposed Use of a Subsequent ASME Code Edition and Addenda L-2024-040, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-03-28028 March 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-013, Submittal of Periodic Reports2024-03-28028 March 2024 Submittal of Periodic Reports L-2024-044, Revised Steam Generator Tube Inspection Reports2024-03-19019 March 2024 Revised Steam Generator Tube Inspection Reports L-2024-011, And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications L-2024-014, 2023 Annual Radioactive Effluent Release Report2024-02-29029 February 2024 2023 Annual Radioactive Effluent Release Report L-2024-025, Notification of Improved Standard Technical Specifications (ITS) Implementation2024-02-22022 February 2024 Notification of Improved Standard Technical Specifications (ITS) Implementation L-2024-008, Supplement to License Amendment Request 278. Incorporate Advanced Fuel Products. Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles2024-02-0909 February 2024 Supplement to License Amendment Request 278. Incorporate Advanced Fuel Products. Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2024-007, Inservice Inspection Program Owners Activity Report (OAR-1)2024-01-18018 January 2024 Inservice Inspection Program Owners Activity Report (OAR-1) L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-172, Supplement to Exemption Request Regarding Enhanced Weapons. Firearms Background Checks. and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Exemption Request Regarding Enhanced Weapons. Firearms Background Checks. and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-146, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-078, License Amendment Request 278, Incorporate Advanced Fuel Products, Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles2023-11-15015 November 2023 License Amendment Request 278, Incorporate Advanced Fuel Products, Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles L-2023-077, License Amendment Request 277 Updated Spent Fuel Pool Criticality Analysis2023-10-11011 October 2023 License Amendment Request 277 Updated Spent Fuel Pool Criticality Analysis L-2023-110, Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project2023-08-25025 August 2023 Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2023-115, Inservice Inspection Program Owners Activity Report (OAR-1)2023-08-21021 August 2023 Inservice Inspection Program Owners Activity Report (OAR-1) L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update L-2023-098, And Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 And Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 L-2023-094, Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project2023-07-27027 July 2023 Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) L-2023-086, Request Temporary Suspension of Turkey Point License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation.2023-06-28028 June 2023 Request Temporary Suspension of Turkey Point License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation. L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update 2024-09-25
[Table view] |
Text
April 1, 2019 L-2019-072 10 CFR 54 .21 (b)
U.S. Nuclear Regulatory Commission Attn : Document Control Desk Washington , D.C. 20555-0001 Re : Florida Power & Light Company Turkey Point Units 3 and 4 Docket Nos . 50-250 and 50-251 Turkey Point Units 3 and 4 Subsequent License Renewal Application First Annual Update References :
- 1. FPL Letter L-2018-004 to NRC dated January 30 , 2018 , Turkey Point Units 3 and 4 Subsequent License Renewal Application (ADAMS Accession No .
ML18037A812)
- 2. FPL Letter L-2018-082 to NRC dated April 10, 2018, Turkey Point Units 3 and 4 Subsequent License Renewal Application - Revision 1 (ADAMS Accession No.
ML18113A134)
Florida Power & Light Company (FPL) submitted a subsequent license renewal application (SLRA) for Turkey Point Units 3 and 4 (PTN 3 and 4) to the NRC on January 30 , 2018 (Reference 1) and SLRA Revision 1 on April 10, 2018 (Reference 2) .
The License Renewal Rule , 10 CFR 54.21 (b), requires that each year following submittal of an LRA, and at least 3 months before scheduled completion of the NRC review , an update to the LRA must be submitted that identifies any change to the current licensing basis (CLB) of the facility that materially affects the content of the LRA including the Updated Final Safety Analysis Report Supplement.
In accordance with the License Renewa l Rule , FPL has performed the annual review of PTN 3 and 4 CLB changes since submittal of SLRA Revision 1 to determine whether any sections of the SLRA were materially affected by these changes . As a result of th is annual review , FPL identified four changes to the PTN 3 and 4 CLB materially affecting SLRA content. A description of these changes and the corresponding affected SLRA content revisions are provided in Attachments 1 and 2.
If you have any questions , or need additional information , please contact me at 561 -
691 -2294 .
Florida Powe r & Li ght Com pany 700 Universe Boulevard , Juno Beach, FL 33408
Turkey Point Units 3 and 4 Docket Nos . 50-250 and 50-251 L-2019-072 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct.
Executed on April 1, 2019 .
William Maher Senior Licensing Director Florida Power & Light Company WDM/RFO Attachments : - Current Licensing Basis (CLB) Changes Affecting the SLRA - Affected SLRA Content Revisions cc:
Senior Resident Inspector, USNRC, Turkey Point Nuclear Regional Administrator, USNRC , Region II Project Manager, USNRC , Turkey Point Nuclear Plant Project Manager, USNRC , SLRA Plant Project Manager, USNRC , SLRA Environmental Ms . Cindy Becker, Florida Department of Health
Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 CLB Changes Affecting the SLRA L-2019-072 Attachment 1 Page 1 of 2 CURRENT LICENSING BASIS (CLB) CHANGES AFFECTING THE SLRA Screening Document and SLRA PTN 3 and 4 CLB Aging Management Content Change ltem 1 Review (AMR) Document Affected Affected Change 1 EC 288059 relocated a code boundary Screening Document: Section break from valve 3-502 in Unit 3 and 4-502 in Unit FPLCORP020-REPT-002 2.3.1.1.1 4 to the reactor vessel (RV) flange downstream of the inner 0-! irJg and the internal restricting orifice . AMR Document:
FPLCORP020-REPT-032 The SLRA is updated to discuss this boundary relocation .
Change 2 Additional SR/NNS boundaries were Screening Document: Section 2.3.3 .1 added at valves 3-50-868 , 3-50-869 , 4-50-868, FPLCORP020-REPT-008 and 4-50-869 for tie in of the ICW Supplemental Cooling System . AMR Document:
FPLCORP020-REPT-039 The SLRA is updated because the SLRA currently does not include discussion of this boundary in the Intake Cooling Water system.
The SLRA is updated to add this new SR/NNS boundary and a new boundary drawing is listed.
Change 3 EC 283021 re-routed the Units 3 and Screening Document: Section 4 condenser SJAE exhausts to the plant vent None 2.3.3 .11.1 stack where the exhaust will be monitored by the plant vent stack SPING (RAD-6304) . SJAE AMR Document:
exhaust piping was not previously part of LR ; None however, the combined U3 and U4 SJAE headers tie into ductwork that is in the scope of SLR (561 O-M-3060 SH1 ).
The SLRA is updated to discuss this new LR boundary.
1 Excl udes change determinations where the SLRA was unaffected althoug h a Screening Doc ument or AMR Document was affected .
Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 CLB Changes Affecting the SLRA L-2019-072 Attachment 1 Page 2 of 2 CURRENT LICENSING BASIS (CLB) CHANGES AFFECTING THE SLRA Screening Document and SLRA PTN 3 and 4 CLB Aging Management Content Change Item 1 Review (AMR) Document Affected Affected Change 4 EC 271017 replaced a portion of the Screening Document: Table 3.4 .2-2 14-inch feedwater piping downstream of FCV FPLCORP020-REPT-013 498 with chrome-moly piping. Section AMR Document: 3.4 .2.1.2 The SLRA is updated because the SLRA FPLCORP020-REPT-031 currently does not include low-alloy steel in the Feedwater and Blowdown Summary of Aging Management Evaluation Table , or the list of materials of construction for the Feedwater and Blowdown components . The SLRA is updated to add chrome moly (low-alloy steel) to Table 3.4 .2-2 and Section 3.4.2.1.2
Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Affected SLRA Content Revisions L-2019-072 Attachment 2 Page 1 of 3 As a result of four PTN current licensing basis (CLB) changes affecting the SLRA during the SLRA first annual update period , SLRA Sections 2.3 .1.1.1, 2.3.3.1,
. 2.3.3.11 .1, 3.4.2 .1.2 and Table 3.4 .2-2 are amended as indicated by the following text deletion (strikethrough) and text addition (red underlined font) revisions :
[Change 1]
2.3.1.1 Reactor Coolant and Connected Piping 2.3.1 .1.1 Reactor Coolant Piping Boundary Reactor coolant piping boundaries for SLR are included in the RCS SLR boundary drawings listed in Section 2.3.1, Reactor Coolant System . Note that one Class 1 code boundary has been relocated from valve *-502 in Unit 3 and 4 to the reactor vessel (RV) flange downstream of the inner 0-ring and the internal restricting orifice. This change also relocates the SLR boundary to the RV flange for each unit.
[Change 2]
2.3.3.1 Intake Cooling Water Boundary The SLR boundaries are reflected on the SLRBDs listed below. The bounda ries have been extended beyond the boundaries identified in the original Turkey Point license renewal effort to support changes associated with NFPA 805.
Turkey Point Common 5610-M-3019, Sheet 1 Turkey Point Unit 3 5613-M-3019 , Sheet1 5613-M-3019 , Sheet2 Turkey Point Unit 4 5614-M-3019 , Sheet1 5614-M-3019 , Sheet2 The subsequent license renewal boundaries of the ICW system begin with the ICW pumps at the intake structure . For the ICW piping and components that are associated with heat removal from the CCW heat exchangers , the subsequent license renewa l boundary ends at the discharge structure . For the ICW piping and components associated with heat removal from the TPCW heat exchangers, the safety-related pressure boundary ends at the downstream side of POV-*-4882 , POV-*-4883 , *-50-315,
Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Affected SLRA Content Revisions L-2019-072 Attachment 2 Page 2 of 3 and *-50-335 . For the ICW piping and components associated with the addition of the ICW Supplemental Cooling system, the safety-related boundary ends at the upstream side of new valves *-50-868 and *-50-869. The nonsafety-related piping and the TPCW heat exchangers provide seismic support/anchorage for the upstream safety-related portion of the system. For NFPA 805 , this piping must maintain a pressure boundary downstream to valve *-50-401 to provide isolation of ICW in the event of spurious operation of POV-*-4882 or POV-*-4883 , and thus these piping and components are included in the scope of subsequent license renewal.
[Change 3]
2.3.3.11 .1 Auxiliary Building and Electrical Equipment Room Ventilation Boundary SLR boundaries are reflected on the SLRBDs listed below. There are no significant differences between the current boundaries and those identified as part of the original Turkey Point license renewal effort.
Turkey Point Common 5610-M -3060 , Sheet1 5610-M-3060, Sheet3 The subsequent license renewal boundary for auxiliary build ing ventilation begins at the inlet to the auxiliary building supply fans V10 and V11 , and includes system ductwork in the auxiliary building that provides supply air to safety-related rooms . The license renewal boundary continues through ductwork to the auxiliary building exhaust fans V8A and V8B ,
and ends at the fan exhaust ductwork located outside the auxiliary building . Note that a SLR boundary has been added on the common ductwork header upstream of the auxiliary building exhaust fans V8A and V8B to accommodate the addition of exhaust piping from the discharge of the Unit 3 and Unit 4 steam jet air ejectors (SJAEs). Note that the plant vent stack is only considered within the scope of subsequent license renewa l as a nonsafety-related structure that could affect safety-related functions and is included with non-containment structures in Section 2.4.2.12.
Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Affected SLRA Content Revisions L-2019-072 Attachment 2 Page 3 of 3
[Change 4)
Table 3.4.2-2: Feedwater and Slowdown - Summary of Aging Management Evaluation Component Intended Material Environment Aging Effect Aging Management Program NUREG-2191 Table 1 Notes Type Function Requiring Item Item Management Piping Pressure Low-allo~ Treated Loss of Water Chemistrv One-Time VIII.D1 .SP-74 3.4-1, 014 A boundarv steel water {int) material lnsoection Piping Pressure Low-allo~ Treated Wall thinning - Flow-Accelerated Corrosion VIII.D1 .S-408 3.4-1, 060 A boundarv steel water lint\ erosion Piping Pressure Low-allo~ Treated Wall thinning - Flow-Accelerated Corrosion VIII.D1 .S-16 3.4-1, 005 A boundarv steel water lint) FAC f.iQing Pressure Low-allo~ Air - outdoor Loss of External Surfaces Monitoring VIII.H.S-402a 3.4-1, 063 A (insulated) boundarv steel {ext) material of Mechanical Comoonents Piping and Pressure Low-allo~ Treated Cumulative TLAA - Section 4.3.2, Metal VIII.D1 .S-11 3.4-1, 001 A ID.P.i.llil boundart steel water (int} fatigue Fatigue of Piping Components comoonents damaae 3.4.2.1.2 Feedwater and Blowdown Materials The materials of construction for the Feedwater and Blowdown components are: