IR 05000461/2001015

From kanterella
Jump to navigation Jump to search
IR 05000461/2001-015 DRP, Clinton Power Station, Inspection on 11/19-12/31/2001 Re Licensed Operator Requalification & Occupational Radiation Safety. Two Noncited Violations Noted
ML020170288
Person / Time
Site: Clinton Constellation icon.png
Issue date: 01/17/2002
From: Christine Lipa
Division Reactor Projects III
To: Kingsley O
Exelon Generation Co, Exelon Nuclear
References
IR-01-015
Download: ML020170288 (29)


Text

January 17, 2002

SUBJECT:

CLINTON POWER STATION NRC INSPECTION REPORT 50-461/01-15

Dear Mr. Kingsley:

On December 31, 2001, the NRC completed a safety inspection at your Clinton Power Station. The enclosed report documents the inspection findings which were discussed on January 7, 2002, with Mr. Pacilio and other members of your staff.

This inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

There was one finding of very low safety significance (Green) identified in the report which was determined to involve a violation of NRC requirements. An additional violation of NRC requirements which was outside the scope of the significance determination process was also identified. However, because of their very low safety significance and because they have been entered into your corrective action program, the NRC is treating these issues as Non-Cited Violations, in accordance with Section VI.A.1 of the NRCs Enforcement Policy. If you deny any or all of these Non-Cited Violations, you should provide a response with the basis for your denial, within 30 days of the date of this inspection report, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspectors at the Clinton Power Station. In accordance with 10 CFR 2.790 of the NRC's Rules of Practice, a copy of this letter, and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/NRC/ADAMS/index.html (the Public Electronic Reading Room).

Sincerely, Original signed by Christine A. Lipa Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-461 License No. NPF-62

Enclosure:

Inspection Report No. 50-461/01-15

REGION III==

Docket No:

50-461 License No:

NPF-62 Report No:

50-461/01-15(DRP)

Licensee:

AmerGen Energy Company, LLC Facility:

Clinton Power Station Location:

Route 54 West Clinton, IL 61727 Dates:

November 19 through December 31, 2001 Inspectors:

P. Louden, Senior Resident Inspector C. Brown, Resident Inspector S. Orth, Senior Radiation Specialist H. Peterson, Senior License Examiner D. Zemel, Illinois Department of Nuclear Safety Approved by:

Christine A. Lipa, Chief Branch 4 Division of Reactor Projects SUMMARY OF FINDINGS

IR 05000461-01-15, on 11/19-12/31/2001, AmerGen Energy Company LLC, Clinton Power Station; Licensed Operator Requalification, Occupational Radiation Safety.

This report covers a 6-week routine inspection, conducted by resident and regional specialist inspectors. One finding of very low safety significance was identified during this inspection.

The significance of most findings is indicated by their color (Green, White, Yellow, Red)

using IMC 0609, Significance Determination Process (SDP). An additional violation of NRC requirements which was outside the scope of the significance determination process was also identified. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described at its Reactor Oversight Process website at:

http://www.nrc.gov/NRR/OVERSIGHT/index.html.

A.

Inspector Identified Findings 1.

Cornerstone: Mitigating Systems Non-Cited Violation. The inspectors identified a finding wherein the licensee had failed to follow the Code of Federal Regulations (CFR) Title 10, Part 55.59(c)(5), Records, requirements by failing to systematically retain all of the original or authenticated copies of the original evaluation documents during the year 2000 annual NRC examination (10 CFR 55.59).

Although the records were not the original or authenticated copies of the original, the finding was of very low safety significance because records did exist in computerized clerically transcribed documents. However, the computer records had not been signed and there was no indication that they had been verified correct by the original authors.

The unauthenticated documents did provide information that, for the most part, licensed operators had participated and were evaluated during the year 2000 NRC annual requalification examination. However, the inspectors determined that the finding was more than minor. Specifically, the inspectors identified at least one instance in which the transcribed information appeared to be incorrect or missing. The records failure had a credible impact on safety, in that, it negatively impacted on the intent of the licensed operator requalification examination process which is, in part, to maintain a high level of confidence that licensed operators continue to possess the requisite knowledge and abilities needed to safely perform licensed duties. In addition, inadequate record keeping adversely affects the NRCs ability to perform its regulatory function (Section 1R11.6).

2.

Cornerstone: Occupational Radiation Safety Green. The inspectors identified a finding and associated Non-Cited Violation concerning the failure to perform an adequate radiological survey, as required by 10 CFR Part 20.1501. The licensee had identified this issue; however, the licensee did not thoroughly evaluate the cause(s) of the unanticipated radiological conditions and associated problems in the monitoring of radioactive waste activities, which has

resulted in previous, similar incidents.

The finding was of very low safety significance because the area radiation levels and the licensees additional administrative barriers would have limited the potential for an individual inadvertently entering the area and receiving a radiation exposure in excess of regulatory limits (Section 2OS1.3).

B.

Licensee Identified Violations No findings of significance were identified.

Report Details Summary of Plant Status The plant was operated at essentially 100 percent power for most of the inspection period.

The licensee manually shut down the reactor on December 15 to effect repairs on the reactor recirculation system A flow control valve. The plant was restarted on December 16 and remained online for the remainder of the inspection period.

1. REACTOR SAFETY Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity 1R01 Adverse Weather (71111.01)

a.

Inspection Scope The inspectors reviewed design features, procedure implementation, and conducted independent walkdowns of equipment used to protect mitigating systems from adverse winter weather conditions.

b.

Findings No findings of significance were identified.

1R04 Equipment Alignments (71111.04S)

a.

Inspection Scope The inspectors reviewed piping and instrument diagrams, system procedures, training manuals, previously identified equipment deficiencies, condition reports, and vendor information as part of a full system walkdown of the feedwater system which is a high risk-importance system at the station.

b.

Findings No findings of significance were identified.

1R11 Licensed Operator Requalification (71111.11)

.1 Facility Operating History a.

Inspection Scope The inspectors reviewed the plants operating history from January 2000 through October 2001, to assess whether the Licensed Operator Requalification Training (LORT) program had addressed operator performance deficiencies noted at the plant.

b.

Findings No findings of significance were identified.

.2 Licensee Requalification Examinations a.

Inspection Scope The inspectors performed a biennial inspection of the licensees LORT program. The inspectors reviewed the annual requalification operating and written examination material to evaluate general quality, construction, and difficulty level. The operating portion of the examination was inspected during November 14 through 15, 2001. The operating examination material consisted of dynamic simulator scenarios and job performance measures (JPMs). The biennial written examination was administered on November 16, 2001. The biennial written examination material included a total of 35 open reference multiple choice questions. The inspectors reviewed the methodology for developing the examinations, including the LORT program 2-year sample plan, probabilistic risk assessment insights, previously identified operator performance deficiencies, and plant modifications. The inspectors assessed the level of examination material duplication during the current year annual examinations and with last years annual examinations. The inspectors also interviewed members of the licensees management and training staff and discussed various aspects of the examination development.

b.

Findings No findings of significance were identified.

.3 Licensee Administration of Requalification Examinations a.

Inspection Scope The inspectors observed the administration of the requalification operating test to assess the licensees effectiveness in conducting the test and to assess the facility evaluators ability to determine adequate performance using objective, measurable performance standards. The inspectors evaluated the performance of one operating shift crew during two dynamic simulator scenarios and five JPMs in parallel with the facility evaluators. The inspectors observed the training staff personnel administering the operating test, including pre-examination briefings, observations of operator performance, individual and crew evaluations after dynamic scenarios, techniques for JPM cuing, and the final evaluation briefing for licensed operators. The inspectors noted the performance of the simulator to support the examinations. The inspectors also reviewed the licensees overall examination security program.

b.

Findings No findings of significance were identified.

.4 Licensee Training Feedback System a.

Inspection Scope The inspectors assessed the methods and effectiveness of the licensees processes for revising and maintaining its LORT program up to date, including the use of feedback from plant events and industry experience information. The inspectors interviewed licensee personnel (operators, instructors, training management, and operations management) and reviewed the applicable licensee procedures. In addition, the inspectors reviewed the licensees quality assurance and quality control oversight activities, including the licensees training and operations department self-assessment reports, to evaluate the licensees ability to assess the effectiveness of its LORT program and to implement appropriate corrective actions.

b.

Findings No findings of significance were identified.

.5 Licensee Remedial Training Program a.

Inspection Scope The inspectors assessed the adequacy and effectiveness of the remedial training conducted since the previous annual requalification examinations and the training planned for the current examination cycle to ensure that they addressed weaknesses in licensed operator or crew performance identified during training and plant operations.

The inspectors reviewed remedial training procedures and individual remedial training plans, and interviewed licensee personnel (operators, instructors, and training management). In addition, the inspectors reviewed the licensees current examination cycle remediation packages for unsatisfactory operator performance on the written examination and operating test to ensure that remediation and subsequent re-evaluations were completed before returning individuals to licensed duties.

b.

Findings No findings of significance were identified.

.6 Conformance with Operator License Conditions a.

Inspection Scope The inspectors evaluated the facility and individual operator licensees' conformance with the requirements of 10 CFR Part 55. The inspectors reviewed the licensees program for maintaining active operator licenses and to assess compliance with 10 CFR 55.53(e) and (f). The inspectors reviewed the procedural guidance and the process for tracking on-shift hours for licensed operators and which control room positions were granted credit for maintaining active operator licenses. The inspectors also reviewed eight licensed-operator medical records maintained by the facility for

ensuring the medical fitness of its licensed operators and to assess compliance with medical standards delineated in ANSI/ANS-3.4 and with 10 CFR 55.21 and 10 CFR 55.25. In addition, the inspectors reviewed the licensees LORT program to assess compliance with the requalification program requirements as described by 10 CFR 55.59(c).

b.

Findings Non-Cited Violation. The inspectors determined that the licensee had failed to follow regulatory requirements for record keeping with respect to the year 2000 annual NRC licensed operator requalification examination evaluations. Specifically, these records were not the original or authenticated copies of the original documentation. The failure to follow NRC records keeping requirements was a violation; however, records keeping was outside the significance determination process (SDP), so it does not fit the color coding scheme.

Although the records were not the original or authenticated copies of the original, the finding was of very low safety significance because records did exist in the form of computerized, clerically transcribed documents. The computer records had not been signed and there was no indication that they had been verified correct by the original authors. However, the unauthenticated documents did provide information that licensed operators, for the most part, had participated and were evaluated during the year 2000 NRC annual requalification examination.

The inspectors determined that the fact that the licensee had systematically failed to retain the original or authenticated copies of the original evaluation documents during the year 2000 annual NRC examination was more than minor. Specifically, the inspectors identified at least one instance in which the transcribed information appeared to be incorrect or missing. Crew evaluation records indicated that a senior reactor operator (SRO) licensed individual had stood in an SRO position during the evaluation, but no corresponding individual evaluation was included in the transcribed information.

The records failure had a credible impact on safety, in that, it negatively impacted on the intent of the licensed operator requalification examination process which, in part, is to maintain a high level of confidence that licensed operators continue to possess the requisite knowledge and abilities needed to safely perform licensed duties. In addition, inadequate records keeping adversely affects the NRCs ability to perform its regulatory function. The inspectors determined that NRC Inspection Manual Chapter 0609, Appendix I, Operator Requalification Human Performance Significance Determination Process (SDP), could not be used to evaluate this issue. As a result, the failure of the licensee to follow NRC requirements for records maintenance was outside the SDP and was dispositioned in accordance with the NRC Enforcement Policy.

Code of Federal Regulations (CFR) Title 10, Part 55.59(c)(5), Records, requires, in part, that the licensee shall maintain records documenting the participation of each licensed operator and senior operator in the requalification program. The records must contain the results of evaluations and documentation of operating tests and of any

additional training administered in areas in which an operator or senior operator has exhibited deficiencies. The facility shall retain these records until the operators or senior operators license is renewed. The record may be the original or a reproduced copy or a microform provided that the copy or microform is authenticated by authorized personnel. Contrary to the above, on November 19, 2001, the inspectors identified that all of year 2000 annual NRC licensed operator requalification examination evaluations were not the original or authenticated copies of the original documentation.

Because this issue was of very low safety significance and because the licensee entered this issue into their corrective action program as CR 83262 and 83288, this Severity Level IV Violation is being treated as a Non-Cited Violation (NCV 50-461/01-15-01), consistent with Section VI.A.1 of the NRC Enforcement Policy.

.7 Written Examination and Operating Test Results a.

Inspection Scope The inspectors reviewed the pass/fail results of individual written tests, operating tests, and simulator operating tests (required to be given per 10 CFR 55.59(a)(2))

administered by the licensee during calender year 2001.

b.

Findings No findings of significance were identified.

1R12 Maintenance Rule (10 CFR Part 50.65) Implementation (71111.12)

a.

Inspection Scope The inspectors reviewed the effectiveness of the licensees maintenance efforts in implementing the maintenance rule (MR) requirements, including a review of scoping, goal-setting, performance monitoring, short-term and long-term corrective actions, and current equipment performance problems. These systems were selected based on their designation as risk significant under the MR, or their being in the increased monitoring (MR category (a)(1)) group. The systems were:

Battery chargers 1E & 1F

Flooding Mitigation

Reactor Recirculation (RR) System b.

Findings No findings of significance were identified.

1R13 Maintenance Risk Assessment and Emergent Work Evaluation (71111.13)

a.

Inspection Scope The inspectors observed the licensees risk assessment processes and considerations used to plan and schedule maintenance activities on safety-related structures, systems, and components particularly to ensure that maintenance risk and emergent work contingencies had been identified and resolved. The inspectors assessed the effectiveness of risk management activities for the following work activities or work weeks:



Division III emergency diesel generator (EDG) 24-hour run and high pressure core spray (HPCS) quarterly surveillance concurrent with 1E and 1F 125 Vdc battery charger problems during work week 01-49.



Division III EDG broken voltage regulator repairs and maintaining condensate polishing (CP) filter power supplies while swapping the 1E & 1F battery chargers with the swing battery charger during the week ending December 8, 2001.

  • Emergency reserve auxiliary transformer (ERAT) failure and associated repair activities during the week ending December 22, 2001.

b.

Findings No findings of significance were identified.

1R14 Personnel Performance During Non-routine Plant Evolutions (71111.14)

a.

Inspection Scope The inspectors reviewed personnel performance during planned and unplanned plant evolutions and selected licensee event reports focusing on those involving personnel response to non-routine conditions. The review was performed to ascertain that operators responses were in accordance with the required procedures. In particular, the inspectors reviewed personnel performance during the following plant events:

Operator performance during the execution of a temporary modification used to control the RR A flow control valve (FCV) and subsequent operator actions once it was determined that the temporary modification was not adequate and a decision was made to shut down the plant.

  • General licensee actions and response to an emergent ERAT inoperability and deluge on December 18, 2001.

b.

Findings No findings of significance were identified.

1R15 Operability Evaluations (71111.15)

a.

Inspection Scope The inspectors reviewed the following operability determinations (ODs) and evaluations affecting mitigating systems to determine whether operability was properly justified and the component or system remained available such that no unrecognized risk increase had occurred.

  • Operability evaluation for ECR 353113, Fan differential pressure switch in main control room ventilation system.
  • CR 87635 - Functionality of VC [control room ventilation] dampers relies upon procedure steps and OD

CR 86833 - CPS [Clinton Power Station] 3001.01 section 15.2 requires OD for 1B21-F010A&B and OD

CR 87110 - CCP [continuous containment purge] Exhaust Fan Tripped While Lifting Leads per Clearance

CR 87718 - Testing of RCIC [reactor core isolation cooling] vacuum breakers not per ASME Code Requirements b.

Findings No findings of significance were identified.

1R22 Surveillance Testing (71111.22)

a.

Inspection Scope The inspectors observed portions of the following surveillance tests to determine whether risk significant systems and equipment were capable of performing their intended safety functions. The inspectors also assessed the operational readiness of the systems.



Division III EDG 24-hr run surveillance test b.

Findings No findings of significance were identified.

2.

RADIATION SAFETY Cornerstone: Occupational Radiation Safety 2OS1 Access Control to Radiologically Significant Areas (71121.01)

.1 Plant Walkdowns a.

Inspection Scope The inspectors reviewed the radiological conditions of work areas within radiation areas and high radiation areas (HRAs) in the auxiliary, containment, radwaste, and turbine buildings. The inspectors performed independent measurements of area radiation levels and reviewed associated licensee controls to determine if the controls (i.e., surveys, postings, and barricades) were adequate to meet the requirements of 10 CFR Part 20 and Technical Specifications.

b.

Findings No findings of significance were identified.

.2 High Dose Rate High Radiation Area and Very High Radiation Area Controls a.

Inspection Scope The inspectors reviewed the licensees controls for high dose rate HRAs and very high radiation areas. In particular, the inspectors reviewed the licensees revised procedure for posting and controlling HRAs to verify the licensees compliance with 10 CFR Part 20 and Technical Specifications. The inspectors also performed a walkdown to verify the adequacy of boundaries, controls, and postings. In addition, the inspectors reviewed the licensees controls for highly irradiated material stored in the spent fuel storage pool to verify that the licensee had implemented adequate measures to prevent inadvertent personnel exposures from these materials.

b.

Findings No findings of significance were identified.

.3 Problem Identification and Resolution a.

Inspection Scope The inspectors reviewed the licensees condition reports (CRs) (June 2000 through November 2001) concerning problems in access controls, HRAs, radiation worker performance, and radiation protection technician performance. The inspectors also reviewed the licensees common cause evaluations concerning radioactive source controls and radiation worker practices. The inspectors reviewed these documents to

assess the licensees ability to identify repetitive problems, contributing causes, the extent of conditions, and to initiate corrective actions which will achieve lasting results.

b.

Findings A Green finding and associated Non-Cited Violation were identified concerning the failure to perform an adequate radiological survey, as required by 10 CFR 20.1501.

On October 8, 2001, a radiation protection technician was performing a routine, quarterly survey of areas within the licensees radwaste building. Within the Unit 1 floor drain evaporator room (a posted radiation and contaminated area), the technician measured a general area dose rate of about 280 millirem per hour. The technician documented the measurement on a survey form but failed to upgrade the rooms posting to an HRA. Later in the shift, a radiation protection shift supervisor noticed the higher radiation levels documented on the form and had another technician perform a complete survey of the area. That technician identified area radiation levels up to 900 millirem per hour in the room and posted the room as an HRA. The radiation protection staff documented the incident in a CR (No. 78199).

The inspectors reviewed the CR and observed that the licensee took adequate actions to evaluate the technicians performance error in not identifying the change in room status (i.e., upgrade to an HRA). However, the inspectors identified that the licensee had not thoroughly evaluated what had lead to the change in radiological conditions in the room, how long the conditions had existed, and why the licensee had not anticipated the change from operating conditions. Instead, the licensee limited its review to the technician performance error (failing to identify an HRA) and did not evaluate the underlying issues concerning the control of radioactive waste transfers and changing radiological conditions. In reviewing this incident, the inspectors noted other surveys during the previous 6 months that identified unanticipated changes in radiological conditions in the radwaste building. For example, an unexpected HRA was identified on November 29, 2001, in the 702 foot elevation of the radwaste building (pump alley), as identified on a licensees survey record. In this case, the licensee was performing a survey to support the tagging of valves. The inspectors observed that these incidents were not entered into the licensees corrective action program, and, similar to the October 8, 2001 survey, the licensee did not fully resolve the underlying issues that lead to the changing conditions. Based on this review and other CRs related to the control of radioactive waste transfers, the inspectors concluded that the licensee had not taken thorough actions to identify and correct the issues.

This finding, if left uncorrected, would become a more significant concern and could involve unplanned, unintended dose should individual workers inadvertently enter an improperly surveyed and posted HRA. Consequently, the inspectors evaluated the significance of the issue using the Occupational Radiation Safety Significance Determination Process (SDP). Since the licensee had additional administrative barriers in place (i.e., the use of electronic dosimeters and the restrictions on entering areas affected by radioactive waste transfers), the inspectors determined that the finding did not constitute a significant potential for an overexposure and was of very low safety significance (Green).

Code of Federal Regulations Title 10, Part 20.1501 requires, in part, that each licensee make or cause to be made surveys that may be necessary for the licensee to comply with the regulations in this part and are reasonable under the circumstances to evaluate the magnitude and extent of radiation levels. As defined in 10 CFR 20.1003, survey means an evaluation of the radiological conditions and potential hazards incident to the production, use, transfer, release, disposal, or presence of radioactive material or other sources. As described above, the licensees failure to perform an adequate survey to evaluate the radiological conditions necessary to post an HRA (as required by 10 CFR 20.1902) was a violation of 10 CFR 20.1501. However because of the very low safety significance of the item and because the licensee has included the incomplete corrective actions for CR No. 78199 in its corrective action program as CR No. 89324, this 10 CFR Part 20 violation is being treated as a Non-Cited Violation (NCV 50-461/01-15-02).

Cornerstone: Public Radiation Safety 2PS3 Radiological Environmental Monitoring Program (71122.03)

.1 Review Of Environmental Monitoring Reports and Data a.

Inspection Scope The inspectors reviewed the most current (1999 and 2000) Annual Radiological Environmental Operating Reports submitted by the licensee, along with environmental monitoring results for the first, second, and third quarters of calendar year 2001. The inspectors also reviewed Revision 19 to the Offsite Dose Calculation Manual (ODCM),

sampling location commitments, monitoring and measurement frequencies, land use census results, inter-laboratory comparison program results, and data analysis. These reviews were conducted to verify that the radiological environmental monitoring program (REMP) was implemented as required by Technical Specifications and the ODCM and that any changes did not affect the licensees ability to monitor the impacts of radioactive effluent releases on the environment.

b.

Findings No findings of significance were identified.

.2 Walkdowns Of Radiological Environmental Monitoring Stations and Meteorological Tower a.

Inspection Scope The inspectors conducted a walkdown of 3-of-the-10 environmental air sampling stations (i.e., locations CL-1, CL-2, and CL-94) and 6-of-the-54 thermoluminescence dosimeter (TLD) monitoring stations (i.e., CL-1, CL-2, CL-48, CL-76, CL-77, and CL-94) to determine whether they were located as described in the ODCM and to assess the equipment material condition and operability. The inspectors also reviewed records and observed instrument readouts to verify that the meteorological instruments

were operable, calibrated, and maintained in accordance with the licensees procedures and consistent with regulatory guidance. Meteorological data readouts and recording instruments in the control room and at the towers (primary and backup) were verified operable and compared to determine if there were any line loss problems.

b.

Findings No findings of significance were identified.

.3 Review of Radiological Environmental Monitoring Program Sample Collection and Analysis a.

Inspection Scope The inspectors accompanied a technician to observe the collection and preparation of air filters (particulate) and cartridges (iodine) to verify that the sampling was representative and that the techniques were sound and in accordance with station procedure. The inspectors observed the technician complete air sampler field tests and confirmed that the tests were conducted in accordance with procedure. Selected air sampler and water compositor calibration and maintenance records for calendar years 2000 and 2001 were reviewed to verify that the equipment was being properly maintained. Additionally, the inspectors reviewed the most recent results of the vendor laboratorys inter-laboratory comparison program and quality assurance program to verify that the vendor was capable of making accurate radio-chemical measurements.

b.

Findings No findings of significance were identified.

.4 Unrestricted Release of Material From the Radiologically Controlled Area a.

Inspection Scope The inspectors evaluated the licensees controls, procedures, and practices for the unrestricted release of material from radiologically controlled areas. Specifically, the focus of the inspectors review was to verify that: (1) radiation monitoring instrumentation used to perform surveys for unrestricted release of materials was appropriate; (2) instrument sensitivities were consistent with NRC guidance contained in Inspection and Enforcement Circular 81-07 and Health Physics Positions in NUREG/CR-5569 for both surface contaminated and volumetrically contaminated materials; (3) criteria for survey and release conformed to NRC requirements; (4) licensee procedures were technically sound and provided clear guidance for survey methods; and (5) radiation protection and chemistry staffs adequately implemented station procedures. In addition, the inspectors reviewed data to verify that the licensee identified its plant radionuclide mix and adequately assessed the impact of difficult to detect contaminants (such as those that decay by electron capture) relative to its unrestricted release program.

b.

Findings No findings of significance were identified.

.5 Identification and Resolution of Problems a.

Inspection Scope The inspectors reviewed the results of the licensees most recent REMP self-assessment performed during calendar year 2001 and its CR database to determine whether identified problems were entered into the corrective action program and were adequately resolved. The inspectors also reviewed the licensees most recent assessment of its vendors laboratory to ensure that the vendors analytical capabilities and practices were adequate to produce accurate radiological measurements.

b.

Findings No findings of significance were identified.

4. OTHER ACTIVITIES 4OA1 Performance Indicator Verification (71151)

a.

Inspection Scope

The inspectors reviewed the licensees determination of its performance indicator (PI)

for the public radiation safety cornerstone (RETS/ODCM [Radiological Effluent Technical Specifications/ Offsite Dose Calculation Manual] Radiological Effluent Occurrences) to verify that the licensee accurately determined the performance indicator and had identified all occurrences required by the indicator. Specifically, the inspectors reviewed condition reports (February 2001 through December 2001) and quarterly offsite dose calculations for radiological effluents (February 2001 through December 2001).

b.

Findings No findings of significance were identified.

40A2 Identification and Resolution of Problems (71152)

The inspectors identified a weakness in the licensees resolution of a failure to identify and post an HRA, as required by 10 CFR Part 20. The issue is documented in Section 2OS1.3.

4OA3 Event Follow-up (71153)

a.

Inspection Scope The inspectors evaluated licensee events regarding plant status and mitigating actions in order to provide input to determine the need for an incident investigation team (IIT),

augmented inspection team (AIT), or special inspection (SI). Specifically:

The licensees responses to the December 15 shut down and repair work on the RR A FCV.

  • The operators immediate actions and the overall licensee assessment of and response to the unplanned trip and deluge of the ERAT on December 22.

b.

Findings No findings of significance were identified.

4OA6 Meeting(s)

Exit Meetings The inspectors presented the inspection results to Mr. M. J. Pacilio and other members of licensee management at the conclusion of the inspection on January 7, 2002. The licensee acknowledged the findings presented. No proprietary information was identified.

Senior Official at Exit:

J. M. Heffley, Site Vice President Date:

November 19, 2001 Proprietary No Subject:

Results of an Inspection of the Licensees Licensed Operator Requalification Program Change to Inspection Findings:

No Senior Official at Telephone Exit:

Kurtis Hansen, Licensed Operator Requalification Group Lead Date:

December 19, 2001 Proprietary No Subject:

Results of Licensed Operator Requalification Testing for Calendar Year 2001 and Applicability of NRC Inspection Manual Chapter 0609, Appendix I, Operator Requalification Human Performance Significance Determination process (SDP)

Change to Inspection Findings:

Yes, reduced the number of NCV findings from two to one.

Senior Official at Exit:

J. Sears, Radiation Protection Manager Date:

12/26/01 Proprietary:

None Subject:

Occupational and Public Radiation Safety Change to Inspection Findings:

None

KEY POINTS OF CONTACT Licensee K. Baker, Design Engineering Manager R. Campbell, Radiation Protection A. Daniels, Chemistry Manager R. Davis, Radiological Engineering Manager C. Dieckmann, Shift Operations Superintendent R. Frantz, Regulatory Assurance Representative J. Heffley, Site Vice President W. Iliff, Director - Regulatory Assurance Director J. Madden, Nuclear Oversight Manager T. Miracle, Radiation Protection M. Pacilio, Plant Manager J. Randich, Work Management Director J. Sears, Radiation Protection Director T. Shortell, Operations Training Manager R. Svaleson, Operations Director F. Tsakeres, Training Manager J. Williams, Site Engineering Director LIST OF ITEMS OPENED and CLOSED Opened and Closed 50-461/01-15-01 NCV Failure to Follow 10 CFR 55.59(c)(5), Licensed Operator Requalification Program Requirements, Records.

(Section R11.6)

50-461/01-15-02 NCV Failure to perform an adequate survey to identify and post an HRA (Section 2OS1.3)

LIST OF ACRONYMS USED AIT Augmented Inspection Team ANS American National Standard ASME American Society of Mechanical Engineers CFR Code of Federal Regulations CPS Clinton Power Station CR Condition Report DRP Division of Reactor Projects EDG Emergency Diesel Generator ERAT Emergency Reserve Auxiliary Transformer FCV Flow Control Valve HPCS High Pressure Core Spray HRA High Radiation Area IIT Incident Investigation Team IR

Inspection Report

JPM

Job Performance Measure

LORT

Licensed Operator Requalification Training

MR

Maintenance Rule

NCV

Non-Cited Violation

NOMS

Nuclear Operations Management System

NRC

Nuclear Regulatory Commission

OD

Operability Determination

ODCM

Offsite Dose Calculation Manual

PI

Performance Indicator

REMP

Radiological Environmental Monitoring Program

RETS

Radiological Effluent Technical Specifications

RCIC

Reactor Core Isolation Cooling

RR

Reactor Recirculation

SDP

Significance Determination Process

SI

Special Inspection

SRO

Senior Reactor Operator

TLD

Thermoluminescence Dosimeter

UFSAR

Updated Final Safety Analysis Report

LIST OF DOCUMENTS REVIEWED

1R01

Adverse Weather Protection

CPS 1860.01

Cold Weather Operation

Revision 3

UFSAR, Volumes 1,2,and 3

Site and System Descriptions

1R04

Equipment Alignment

Piping and Instrumentation

Drawing

MO5-1004 Reactor Feedwater

CPS 3103.01E001

Feedwater Electrical Lineup

Revision 11

CPS 3103.01V001

Feedwater Valve Lineup

Revision 9

CPS 3103.01V002

Feedwater Instrumentation Valve

Lineup

Revision 9

CPS 3103.01

Feedwater (Operating Procedure)

Revision 20a

1R11

Licensed Operator Requalification

Training Plan

LORT Two Year Cycle Plan for

2001/2002

Year 2001/2002

Training Documentation

LORT Cycle 01.01, 01.03, 01.04,

01.05, and 01.07 Training

Documentation

Year 2001

Training Scores

2001 LORT Scores - Cycle 01.01 thru

01.07

Various

Attendance Documentation

Requal Cycle 01.01 thru 01.07 Training

Attendance Documentation

Various

Evaluation Records

Year 2000 LORT Annual NRC

Examination Evaluation Documentation

Various

Evaluation Records

Year 2001 Cycle 8 - Crew E, Simulator,

JPM, and Written Evaluations

November 14-16,

2001

Remediation Packages

Year 2001 Cycle 8 Crew A - Crew

Failure and Two Individual Failure

Evaluations and Remediation

Packages

November 7-9,

2001

Documents

PRA Task to Training Matrix

none

Documents

Quality Assurance Field Observation

Reports

Various, 1999-2000

Documents

LORT Lesson Plan and Attendance

Books

Cycle 01.01 thru 01.07

Various, 2001

CR 00083261

Training Incomplete

November 16, 2001

CR 00083262

LORT Training Records Retrieval

November 16, 2001

CR 00083288

Common Cause Analysis on NTD

Records

November 17, 2001

CR 00082877

Instructor Override Needed for NRC

Exam Not Loaded

November 14, 2001

CR 00083264

JPM Validation Inadequate

November 16, 2001

Self-Assessment Report

ACAD 91-015 Focused Area

Self-Assessment on Objective 4

Analysis, Design, and Development -

Conduct of Licensed Operator

Continuing Training

March 20, 2001

Self-Assessment Report

Clinton Focused Area Assessment

Objective 8 for Operations Training

September 24-26, 2001

October 2, 2001

Self-Assessment Report

Clinton Power Station Licensed

Operator Requalification Training

Program Focus Area Self-Assessment

Report September 25-26, 2001

November 8, 2001

Self-Assessment Report

Clinton Station Operations Training

Comprehensive Self-Assessment

August 13-17, 2001

September 20,

2001

USAR

Clinton Updated Safety Analysis

Report Chapter 15

Revision 7

OP-AA-1

Nuclear Policy: Conduct of Operations

Revision 0

OP-AA-20

Conduct of Operations Process

Description

Revision 0

OP-AA-101-111

Roles and Responsibilities of On-Shift

Personnel

Revision 0

OP-AA-105-101

Administrative Process for NRC

License and Medical Requirements

Revision 0

OP-CL-402-1001

Operations Policy, CPS Narrative Log

(NOMS)/Records

Revision 7b

TQ-AA-105-102

NRC Active License Maintenance

Revision 0

TQ-AA-106

License Operator Requal Training

Program

Revision 0

TQ-AA-201

Examination Security and

Administration

Revision 0

TQ-AA-210-4101

Remedial Training Notification and

Action on Failure

Revision 0

TQ-AA-210-4102

Performance Review Committee Data

Sheet

Revision 0

TQ-AA-210-4111

Missed Scheduled Training

Notifications

Revision 0

TQ-AA-210-5108

Post Examination Test Item Analysis

Revision 0

NTAFT LOR 02

Classroom Attendance Sheet

Various

NTAFT LOR 03

Simulator Attendance Sheet

Various

NTAFT LOR 13

Simulator Demonstration Examination

Individual Competency Evaluation

Form

Revision 1

NTAFT LOR 14

Simulator Demonstration Examination

Crew Competency Evaluation Form

Revision 1

NTAFT LOR 15

Simulator Demonstration Examination

Shift Manager Competency Evaluation

Form

Revision 1

NTAFT EVA 02

Nuclear Generating Group Trainee

Reaction - Single Topic (Various

Feedback Forms -September 2001)

Revision 3

CPS 1401.05

CPS Narrative Log - Nuclear

Operations Management

System/Records

Various

Training Procedure

Illinois Power Nuclear Program,

Training Program Description -

Operations Continuing

Revision 7

EC-02

EPIP: Emergency Classification

Attachment 2, Emergency

Classification Guide

Revision 6

Examination Material

Year 2000 Examination Material -

Various Scenarios and JPMs

Various, 2000

Examination Material

Year 2001 Cycle 8 - Examination

Material

Week 2 Written Examinations - SRO &

RO

Approved

November 6, 2001

JPM 011264J014

Alternate Start of Division 3 Diesel

Generator - Manual Override of Air

Start Solenoids

Revision 1

JPM 015200J035

Perform a Start of the 1A Turbine

Driven Reactor Feedwater Pump

Revision 2

JPM 011264J011

Manually Start Emergency Diesel

Generator 1A

Revision 0

JPM 041301J002

Service Air Compressor Startup With

Air System Completely Depressurized

per CPS 3214.01

Revision 3

JPM 015200J070

Defeating Alternate Rod Insertion (ARI)

Logic Trips

Revision 1

JPM 011259J004

Startup Motor Driven Reactor

Feedwater Pump

Revision 1

JPM 011264J009

Parallel DG 1C With Off Site Power

Revision 1

ESG-08

Simulator Scenario - ATWS

Revision 16

ESG-12

Simulator Scenario - Small Break

LOCA

Revision 14

1R12

Maintenance Rule Implementation

Plant Health Report

Third Quarter 2001

1R13

Maintenance Risk Assessment and Emergent Work Evaluation

CPS WC-101

Online Work Control Process

Revision 6

1R14

Personnel Performance During Non-routine Plant Evolutions

CPS 3005.02

Unit Power Changes - Compensatory

Operation of RR A FCV

Revision 0

ECN-28505

Modification to the RR A FCV

Feedback Circuitry

Contingency Plan

OPS-01-031 Lockout of RR A FCV

1R15

Operability Evaluations

ECR 353113

Fan differential pressure switch in main

control room ventilation system.

CR 87635

Functionality of VC dampers relies

upon procedure steps + OD

CR 86833

CPS 3001.01 section 15.2 requires OD

for 1B21-F010A&B + OD

CR 87110

CCP Exhaust Fan Tripped While Lifting

Leads per Clearance

CR 87718

Testing of RCIC vacuum breakers not

per Code Requirements

1R22

Surveillance Testing

CPS 9080.14

Diesel Generator 1C 24-Hour Run and

Hot Restart - Operability

Revision 34

2OS1 Access Control to Radiological Significant Areas

CPS Radiological Survey

Sheet

Nos. 01-10-08-003, 01-10-08-13,

01-10-19-16, 01-11-15-03,

01-11-29-06, 01-11-30-03,

01-11-30-12, and 01-12-6-3

CR 64550

2-01-07-121 Common Cause Analysis

(CCA) on Radioactive Source

CR 81484

Radiation Area Sign Obscured by

Workers Propping Open Door

CR 83692

Radworker Insufficient Knowledge of

Radiological Conditions

CR 84645

Work Practices Lead to Personnel

Contamination Event

CR 89324

Incomplete Corrective Actions in RP

CR

CR 2-00-12-142

Radworker Performance Weakness

CR 2-01-01-021

Source Plaques Improperly Signed

Out

CR 2-01-02-022

CPS Radioactive Source Database

Not Updated in Accordance with CPS

9974.01

CR 2-01-02-178

Failure to Perform Face to Face

Turnovers with Oncoming Relief Lead

Technician

CR 2-01-03-012

Inadequate RP Turnover Resulted in

Improper Survey of Radwaste

Shipment W01-004

CR 2-01-04-189

Key Control Documentation

Deficiencies Found During Self-

assessment

CR 2-01-05-336

Failure to Control SF System Drain

Resulted in Unplanned Spread of

Contamination

CR 2-01-06-043

CPS 3870.01 Performed Without RP

Being Present

CR 2-01-06-166

Cubicle Deposted form Radwaste

Transfer While Transfer Appendix/s

Open for that Cubicle

CR 2-01-06-210

Radioactive Material Found Outside

the RCA (Radiological Controlled

Area)

CR 2-01-06-243

Radworker Required Prompting to

Remove Tool from Pocket Prior to

Exiting the RCA

CR 2-01-06-244

Radworker Required Prompting to

Remove Tool from Pocket Prior to

Exiting the RCA

RP-AA-460

Controls for High and Very High

Radiation Areas

Revision 2

2PS3

Radiological Environmental Monitoring Program

Clinton Power Station 1999 Annual

Radiological Environmental Operating

Report

April 24, 2000

Clinton Power Station 2000 Annual

Radiological Environmental Operating

Report

April 25, 2001

Monthly Progress Report to AmerGen

Co., Clinton, Illinois

November 5, 2001

Self Assessment Report: Radiological

Environmental Monitoring, and Dose

Calculation Program and Radioactive

Effluents (ODCM/REMP)

October 2001

48095

Field Observation Report

May 22, 2001;

June 5, 2001; June

18, 2001

CPS 7911.33

Operation and Sample Volume

Programming of Water Compositor

Samplers performed in November

2001

Revision 7

CPS 8699.19

Calibration of Gas Rotameters

performed on October 16, 2001,

October 9, 2001, and October 15,

1999 for environmental air samplers

Revision 6

CPS 9437.14

Meteorology System Loop Calibration

performed on April 26, 2001; August

29, 2001; October 26, 2001; and

October 29, 2001

Revision 36a

CPS 9911.70

Radiological Environmental

Surveillance Airborne Radioiodine and

Particulate Monitoring

Revision 34b

CR 00064337

2-01-04-118 Failure to Comply with

Regulatory Guide 1.23

April 18, 2001

CR 00078955

Reporting Errors Found in Monthly

Report

October 19, 2001

CR 00079291

Failure to Meet Requirements for Free

Release

October 18, 2001

CR 00082197

Documentation Errors Found in

ODCM/REMP Monthly Reports

October 24, 2001

CR 00082418

Material Processed out of the RCA

Without Passing a SAM

October 4, 2001

CR 00083143

ODCM Composite Water Sampler

Found Not Sampling

November 16, 2001

CR 00084170

Water Compositors not Programmed

IAW Station Procedure

November 28, 2001

CR 00084348

Blown Fuse Anapaest CL-15

Environmental Air Sampling Station

November 29, 2001

CR 00085038

Inconsistent Documentation in 1999

and 2000 REMP Reports

December 4, 20011

CR 2-01-04-046

Surface Water Sample Damaged

During Shipment to Vendor Results in

Non-Analysis Requirement

April 6, 2001

P1l-01-02

Quality Assurance Assessment:

Radiation Protection, Chemistry and

Radwaste

June 12, 2001

RP-CL-304

Unconditional Release Surveys

Revision 0

SR-2001-341

Supplier Evaluation Service

Department, Audit Report No.

SR-2001-341

July 22, 2001