September 23, 2010
SUBJECT:
ARKANSAS NUCLEAR ONE - NRC INSPECTION PROCEDURE 95001 SUPPLEMENTAL INSPECTION REPORT 05000313/2010406 AND 05000368/2010406
Dear Mr. Berryman:
On September 10, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed a supplemental inspection pursuant to Inspection Procedure 95001 at your Arkansas Nuclear One, Units 1 and 2 to follow up on previous security inspection findings. The enclosed inspection report documents the inspection results, which were discussed at the exit meeting on September 10, 2010, with you, and other members of your staff. The NRC was informed of your readiness for the inspection on August 2, 2010.
The inspection consisted of examination of activities conducted under your license as they related to safety, compliance with the Commissions rules and regulations, and the conditions of your operating license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, ADAMS.
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the UNITED STATES NUCLEAR REGULATORY COMMISSION R E GI ON I V 612 EAST LAMAR BLVD, SUITE 400 ARLINGTON, TEXAS 76011-4125 Entergy Operations, Inc.
- 2 - Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Sincerely,
/RA/
Michael P. Shannon, Chief
Plant Support Branch-1
Division of Reactor Safety
Docket No.: 50-313; 50-368 License No.: NPF 6; DPR 51
Inspection Report 05000313/2010406; 05000368/2010406 w/Attachment: Supplemental Information
cc w/o enclosure:
Senior Vice President
& Chief Operating Officer Entergy Operations, Inc.
P.O. Box 31995 Jackson, MS 39286-1995
Thomas Palmisano Vice President, Oversight Entergy Operations, Inc.
P.O. Box 31995 Jackson, MS 39286-1995 Entergy Operations, Inc.
- 3 - Mark Giles Acting Manager, Licensing Arkansas Nuclear One 1448 SR 333 Russellville, AR 72802
Joseph A. Aluise Associate General Counsel - Nuclear Entergy Services, Inc 639 Loyola Avenue New Orleans, LA 70113
Senior Manager, Nuclear Safety & Licensing Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995 Entergy Operations, Inc.
- 4 - bcc w/enclosure:
Ronald Albert (Ronald.Albert@nrc.gov), Chief, Reactor Security Oversight Branch Shyrl Coker, (Shyrl.Coker@nrc.gov) NSIR/DSO/DDSO, TWFN Mail Stop: T-3A5M Clay Johnson, (Clay.Johnson@nrc.gov), NSIR/DSO/DDSO/SPEB, TWFN 3D43 Branch Chief, RI DRS (James.Trapp@nrc.gov)
Branch Chief, RII DRS/PSB2 (Michael.Ernstes@nrc.gov)
Branch Chief, RIII DRS/PSB (Eric.Duncan@nrc.gov)
Senior Resident Inspector (Alfred.Sanchez@nrc.gov)
Electronic distribution by RIV:
bcc w/o enclosure:
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Chuck.Casto@nrc.gov)
DRP Director (Kriss.Kennedy@nrc.gov)
DRP Deputy Director (Anton.Vegel@nrc.gov)
DRS Director (Roy.Caniano@nrc.gov)
DRS Deputy Director (Troy.Pruett@nrc.gov)
Branch Chief, DRP/E (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Alfred.Sanchez@nrc.gov)
Resident Inspector (Jeffrey.Josey@nrc.gov)
Resident Inspector (Jeff.Rotton@nrc.gov)
Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)
Project Engineer (William.Schaup@nrc.gov)
ANO Administrative Assistant (Vacant)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Kaly.Kalyanam@nrc.gov)
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource OEDO RIV Coordinator (Margie.Kotzalas@nrc.gov) Entergy Operations, Inc.
- 5 - Security Related Complete Report - OUO:
SUNSI Rev Compl.
x Yes No ADAMS x Yes No Reviewer Initials ETB Publicly Avail Yes x No Sensitive x Yes No Sens. Type Initials ETB
Letter Only:
SUNSI Rev Compl.
x Yes No ADAMS x Yes No Reviewer Initials ETB Publicly Avail x Yes No Sensitive Yes x No Sens. Type Initials ETB
SPSI/PSB-1 PSI/PSB-1 C:PSB-1 C:PBE C:PSB-1 ETByre MBrooks MPShannon JAClark MPShannon