IR 05000327/2008007

From kanterella
Jump to navigation Jump to search
IR 05000327-08-007 & 05000328-08-007 on 10/09/2008 for Sequoyah -TI 2515/171 Verification of Site Specific Implementation of B.5.b Phase 2 and 3 Mitigating Strategies Inspection
ML083150207
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 11/07/2008
From: Eugene Guthrie
Reactor Projects Region 2 Branch 6
To: Campbell W
Tennessee Valley Authority
References
IR-08-007
Download: ML083150207 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

ber 7, 2008

SUBJECT:

SEQUOYAH NUCLEAR PLANT - TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NOS. 05000327/2008007 AND 05000328/2008007

Dear Mr. Campbell:

On October 9, 2008, the United States Nuclear Regulatory Commission (NRC) completed a team inspection at your Sequoyah Nuclear Plant. The enclosed report documents the inspection results, which were discussed with members of your staff on October 9, 2008.

The inspection examined activities conducted under your license as they relate to the implementation of B.5.b Phase 2 and 3 mitigating strategies, your compliance with the Commissions rules and regulations, and with the conditions of your operating license. Within these areas, the inspection involved examination of selected procedures and representative records, observations of activities, and interviews with personnel.

This report documents no findings of significance.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). 2 However, because of the sensitive information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

Sincerely,

/RA/

Eugene Guthrie, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-327, 50-328 License Nos.: DPR-77, DPR-79 Nonpublic Enclosure: NRC Inspection Report 05000327/2008007 and 05000328/2008007 w/Attachment: Supplemental Information cc w/encl: (See Page 3) _________________________ X SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP HQ:NRR RII:DRP RII:DRP HQ:NRR SIGNATURE /RA by email/ /RA by email/ /RA by email/ /RA by email/

NAME M. Speck R. Moore J. Greene J. Baptist E. Guthrie D. Nelson DATE 11/ /2008 11/ /2008 11/ /2008 11/ /2008 11/ /2008 11/ /2008 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO 3 cc w/Encl:

Ashok S. Bhatnagar General Counsel Senior Vice President Tennessee Valley Authority Nuclear Generation Development and 6A West Tower Construction 400 West Summit Hill Drive Tennessee Valley Authority Knoxville, TN 37902 6A Lookout Place 1101 Market Street John C. Fornicola Chattanooga, TN 37402-2801 General Manager Nuclear Assurance Timothy P. Cleary Tennessee Valley Authority Site Vice President 3R Lookout Place Sequoyah Nuclear Plant 1101 Market Street Tennessee Valley Authority Chattanooga, TN 37402-2801 P.O. Box 2000 Soddy-Daisy, TN 37384-2000 Beth A. Wetzel Manager Tom Coutu Corporate Licensing Vice President Tennessee Valley Authority Nuclear Support 4K Lookout Place Tennessee Valley Authority 1101 Market Street 3R Lookout Place Chattanooga, TN 37402-2801 1101 Market Street Chattanooga, TN 37402-2801 Robert H. Bryan, Jr.

General Manager Walter M. Justice, II Licensing and Industry Affairs Interim Vice President Tennessee Valley Authority Nuclear Engineering & Technical Services 4X Blue Ridge Tennessee Valley Authority 1101 Market Street 6A Lookout Place Chattanooga, TN 37402-2801 1101 Market Street Chattanooga, TN 37402-2801 Christopher R. Church Plant Manager Sequoyah Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Soddy-Daisy, TN 37384-2000 4 Letter to William R. Campbell, Jr. from Eugene Guthrie dated November 7, 2008 SUBJECT: SEQUOYAH NUCLEAR PLANT - TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NOS. 05000327/2008007 AND 05000328/2008007 Distribution w/encl:

L. Reyes, RA V. McCree, DRA L. Wert, DRP J. Moorman, DRP (Acting)

K. Kennedy, DRS R. Croteau, DRS H. Christensen, DRS E. Guthrie, DRP E. Bowman, NRR B. Moroney, NRR (PM: SEQ)

OE Mail (email address if applicable)

RIDSNRRDIRS Region II Docket Room (with concurrences)

Distribution w/o encl:

PUBLIC