|
---|
Category:Inspection Plan
MONTHYEARIR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 IR 05000259/20220062023-03-0101 March 2023 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Report 05000259/2022006, 05000260/2022006 and 05000296/2022006 ML23020A0602023-01-20020 January 2023 Long Term Steam Dryer Inspection Plan IR 05000259/20220052022-08-30030 August 2022 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Report 05000259/2022005, 05000260/2022005 and 05000296/2022005 ML22210A1342022-07-20020 July 2022 Requalification Inspection Notification Letter ML22174A2722022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20224012022-03-0808 March 2022 Information Request for the Cyber-Security Baseline Inspection Notification to Perform Inspection 05000259/2022401; 05000260/2022401; 05000296/2022401 ML22091A1942022-03-0808 March 2022 2022 BFN POV Inspection Information Request IR 05000259/20210062022-03-0202 March 2022 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 (Report No. 05000259/2021006, 05000260/2021006 and 05000296/2021006 ML22025A4132022-01-25025 January 2022 RP Inspection Doc Request ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21343A4232021-12-0909 December 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000259/2022010, 05000260/2022010, and 05000296/2022010) and Request for Information (RFI) IR 05000259/20210052021-08-23023 August 2021 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2, and 3- Report Nos. 05000259/2021005, 05000260/2021005 and 5000296/2021005 IR 05000259/20200062021-03-0303 March 2021 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2020006, 05000260/2020006 and 05000296/2020006 ML21047A4732021-02-16016 February 2021 Notification of Browns Ferry Nuclear Power Plant Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000259/2021010, 05000260/2021010, and 05000296/2021010 ML20338A3682020-12-0303 December 2020 Notification of Inspection and Request for Information ML20266G4472020-09-22022 September 2020 Notification of Inspection and Request for Information IR 05000259/20200052020-08-18018 August 2020 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2020005, 05000260/2020005, and 05000296/2020005 ML20191A2232020-07-0909 July 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20190062020-03-0303 March 2020 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1,2,and 3 - NRC Report 05000259/2019006, 05000260/2019006, and 05000296/2019006 ML19108A1682019-04-18018 April 2019 EP Exercise Inspection RFI IR 05000259/20180062019-03-0404 March 2019 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2018006, 05000260/2018006 and 05000328/2018006 ML19030A6712019-01-25025 January 2019 U2 ISI RFI ML19024A4112019-01-24024 January 2019 Transmittal of RP Baseline Inspection Document Request 2019 ML18264A2052018-09-21021 September 2018 U1 ISI Emailed RFI Notification ML18059A1052018-02-28028 February 2018 EOC Assessment Letter ML18029A4672018-01-29029 January 2018 Notification of Browns Ferry Nuclear Plant Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000259/2018010, 05000260/2018010, and 05000296/2018010 ML18029A2552018-01-29029 January 2018 U3 RFI Email Request ML17236A1972017-08-24024 August 2017 Updated Inspection Plan ML17156A1612017-06-0202 June 2017 Notification of Inspection and Request for Information IR 05000259/20160062017-03-0101 March 2017 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2, and 3 (Report 05000259/2016006, 05000260/2016006 and 05000296/2016006) IR 05000259/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Reports 05000259/2016005, 05000260/2016005 and 05000296/2016005 ML16243A2242016-08-30030 August 2016 Notification of Inspection and Request for Information ML16120A1182016-04-27027 April 2016 Notification of Conduct of a Triennial Fire Protection Baseline Inspection - U.S. Nuclear Regulatory Commission Inspection Report Nos. 05000259/2016011, 05000260/2016011 and 05000296/2016011 IR 05000259/20150062016-03-0202 March 2016 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 NRC Inspection Reports 05000259/2015006, 05000260/2015006 and 05000296/2015006 ML16013A0812016-01-12012 January 2016 Browns Ferry Nuclear Plant, Unit 3 - Notification of Inspection and Request for Information ML15348A1802015-12-14014 December 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for the Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Report 005000259/2015005, 005000260/2015005, and 005000296/2015005 IR 05000259/20140012015-03-0404 March 2015 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 - NRC Inspection Reports 05000259/2014001, 05000260/2014001 and 05000296/2014001 IR 05000259/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 (NRC Inspection Reports 05000259/2014006, 05000260/2014006 and 05000296/2014006) ML14063A1092014-03-0404 March 2014 2013 Annual Assessment Letter for Browns Ferry ML14031A4122014-01-31031 January 2014 U3 2014002 ISI RFI Final - Copy ML13353A5852013-12-19019 December 2013 PIR Notification Letter 2014 ML13246A1842013-09-0303 September 2013 Mid Cycle Assessment Letter ML13084A0052013-03-25025 March 2013 Emergency Preparedness Inspection Notification and Request for Information IR 05000259/20120012013-03-0404 March 2013 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 & 3 (IR 05000259-12-001, 05000260-12-001, and 05000296-12-001) ML13037A1662013-02-0101 February 2013 Notification of Inspection and Request for Information IR 05000259/20120062012-09-0404 September 2012 Browns Ferry 2012 Mid Cycle ML12248A2962012-09-0404 September 2012 Mid Cycle ML12066A0602012-03-0505 March 2012 Inspection/Activity Plan, 30/01/2012 - 06/01/2013, RPT 22 2023-08-29
[Table view] Category:Letter
MONTHYEARML24032A4762024-02-0101 February 2024 Final Report of a Part 21 Evaluation Associated with Starter Contactors for the BFN Unit 1 High Pressure Coolant Injection Suppression Pool Inboard Suction Valve ML24023A2802024-01-23023 January 2024 Final Report of a Deviation or Failure to Comply Associated with a Relay in the Reactor Core Isolation Cooling Condensate Pump CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24016A3042024-01-16016 January 2024 Final Report of a Part 21 Evaluation Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump CNL-23-071, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-472024-01-11011 January 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-47 ML24022A1732024-01-0303 January 2024 Receipt and Availability of the Subsequent License Renewal Application ML23319A1992024-01-0303 January 2024 Issuance of Amendment Nos. 333, 356, and 316 Regarding the Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves ML23355A2062023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23348A3942023-12-14014 December 2023 Interim Part 21 Report of a Potential Deviation or Failure to Comply Associated with Starter Contactors for the High Pressure Coolant Injection Suppression Pool Inboard Suction Valve IR 05000259/20230102023-12-11011 December 2023 Commercial Grade Dedication Inspection Report 05000259/2023010 and 05000260/2023010 and 05000296/2023010 ML23335A0722023-12-0101 December 2023 Interim Report of a Deviation or Failure to Comply Associated with a Relay in the Unit 2 Reactor Core Isolation Cooling Condensate Pump ML23334A2492023-11-30030 November 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-070, Submittal of Fifth 10-Year Interval Inservice Testing Program Plan2023-11-29029 November 2023 Submittal of Fifth 10-Year Interval Inservice Testing Program Plan ML23331A2532023-11-27027 November 2023 Summary Report for 10 CFR 50.9 Evaluations, Technical Specifications Bases Changes, Technical Requirement Manual Changes, and NRC Commitment Revisions CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23325A1102023-11-21021 November 2023 Anchor Darling Double Disc Gate Valve Commitment Revision ML23320A2542023-11-16016 November 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump IR 05000259/20230032023-11-13013 November 2023 Integrated Inspection Report 05000259/2023003, 05000260/2023003 and 05000296/2023003 IR 05000259/20230402023-11-0202 November 2023 Supplemental Inspection Supplemental Report 05000259 2023040 and Follow-Up Assessment Letter ML23292A2532023-10-18018 October 2023 BFN 2024-301, Corporate Notification Letter (210-day Ltr) ML23282A0022023-10-0606 October 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump ML23278A0122023-10-0505 October 2023 Updated Final Safety Analysis Report, Amendment 30 ML23271A1702023-09-28028 September 2023 Site Emergency Plan Implementing Procedure Revision ML23270A0702023-09-26026 September 2023 SLRA Pre-Application Meeting Summary 09-13-2023 ML23257A1232023-09-22022 September 2023 Administrative Changes to Technical Specification Pages Issued for License Amendment Nos. 332, 355, and 315 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23263B1042023-09-20020 September 2023 Special Report 260/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation ML23205A2132023-09-0808 September 2023 Issuance of Amendment Nos. 332, 355, and 315 Regarding the Revision of Technical Specifications to Adopt TSTF-566-A and TSTF-580-A, Rev. 1 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 ML23233A0432023-08-18018 August 2023 Enforcement Action EA-22-122 Inspection Readiness Notification ML23219A1542023-08-17017 August 2023 Request to Use Later Edition of ASME Code for Operation and Maintenance and Alternative Requests BFN-IST-01 Through 05 for the Fifth 10-Year Interval Inservice Testing Program ML23228A1642023-08-16016 August 2023 Site Emergency Plan Implementing Procedure Revision ML23228A0202023-08-15015 August 2023 (BFN) Unit 1 - Special Report 259/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation IR 05000259/20230022023-08-10010 August 2023 Integrated Inspection Report 05000259/2023002, 05000260/2023002, 05000296/2023002 and 07200052/2023001 ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills ML23171A8862023-07-24024 July 2023 Issuance of Amend. Nos. 331, 354, and 314; 365 and 359 Regarding Adoption of TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML23201A2182023-07-20020 July 2023 Registration of Use of Cask to Store Spent Fuel (MPC-298 and -299) ML23159A2552023-07-20020 July 2023 Proposed Alternative to the Requirements of the ASME Code Regarding Volumetric Inspection of Standby Liquid Control Nozzles ML23199A3072023-07-18018 July 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions IR 05000259/20233012023-07-18018 July 2023 NRC Operator License Examination Report Nos. 05000259/2023301, 05000260/2023301, and 05000296/2023301 2024-02-01
[Table view] |
Text
March 3, 2020
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2 AND 3 - REPORT 05000259/2019006, 05000260/2019006 AND 05000296/2019006
Dear Mr. Barstow:
The NRC has completed its end-of-cycle performance assessment of Browns Ferry Nuclear Plant, Units 1, 2 and 3, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2019, through December 31, 2019. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.
The NRC determined the performance at Browns Ferry Nuclear Plant, Units 1, 2 and 3 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs ROP Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
Although plant performance was within the Licensee Response Column, the NRC has not yet finalized the significance of Apparent Violation (AV) 05000259, 260, 296/2019490-01, Security Finding. The final safety significance determination may affect the NRCs assessment of plant performance and the enclosed inspection plan.
In addition to the ROP baseline inspections, we also plan on conducting infrequently performed inspections which include Initial License Examination, Temporary Instruction 2515/193, and the inspection of the implementation of EA13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions.
The enclosed inspection plan lists the inspections scheduled through December 31, 2020.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections).
Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, and Requests for Withholding.
Please contact me at (404) 997-4703 with any questions you may have regarding this letter.
Sincerely,
/RA/
Thomas Stephen, Acting Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos.: 50-259, 50-260, 50-296 License Nos.: DPR-33, DPR-52, DPR-68 Enclosure:
Browns Ferry Inspection/Activity Plan (03/01/2020- 12/31/2021)
cc: Distribution via ListServ
ML20063N074 OFFICE RII:DRP RII:DRP RII:DRP NAME J Seat S Ninh T Stephen DATE 2/18/2020 2/18/2020 2/26/2020
IP 22 Inspection Activity Plan Report Browns Ferry 03/01/2020 - 12/31/2021 Unit Start End Activity CAC Title Staff Count UNIT 3 IN-SERVICE INSPECTION 1 3 03/02/2020 03/06/2020 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS 3 1, 2, 3 05/04/2020 05/08/2020 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments EMERGENCY PREPAREDNESS PROGRAM INSPECTION 2 1, 2, 3 05/04/2020 05/08/2020 IP 71114.02 000717 Alert and Notification System Testing 1, 2, 3 05/04/2020 05/08/2020 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2, 3 05/04/2020 05/08/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2, 3 05/04/2020 05/08/2020 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2, 3 05/04/2020 05/08/2020 IP 71151 001397 Performance Indicator Verification RELIABLE HARDENED CONTAINMENT VENT TI-193 2 1, 2, 3 05/11/2020 05/14/2020 TI 2515/193 000511 Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions SECURITY BASELINE INSPECTION 2 1, 2, 3 06/01/2020 06/05/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2, 3 06/01/2020 06/05/2020 IP 71130.07 000739 Security Training RP PUBLIC RAD SAFETY BASELINE INSPECTION 2 1, 2, 3 07/06/2020 07/10/2020 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2, 3 07/06/2020 07/10/2020 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2, 3 07/06/2020 07/10/2020 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1, 2, 3 07/06/2020 07/10/2020 IP 71151 000746 Performance Indicator Verification TRIENNIAL HEAT SINK PERFORMANCE 1 1, 2, 3 07/20/2020 07/24/2020 IP 71111.07T 000700 Heat Sink Performance PROBLEM IDENTIFICATION AND RESOLUTION 4 1, 2, 3 08/24/2020 08/28/2020 IP 71152B 000747 Problem Identification and Resolution 1, 2, 3 09/07/2020 09/11/2020 IP 71152B 000747 Problem Identification and Resolution This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report Browns Ferry 03/01/2020 - 12/31/2021 Unit Start End Activity CAC Title Staff Count BROWNS FERRY REQUAL INSPECTION 2 1, 2, 3 09/14/2020 09/18/2020 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance MATERIAL CONTROL & ACCOUNTING 3 1, 2, 3 10/01/2020 12/31/2020 IP 71130.11 000742 Material Control and Accounting (MC&A)
UNIT 1 IN-SERVICE INSPECTION 1 1 10/05/2020 10/09/2020 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
SECURITY BASELINE INSPECTION 1 1, 2, 3 02/08/2021 02/12/2021 IP 71130.02 000734 Access Control 1, 2, 3 02/08/2021 02/12/2021 IP 71130.09 001656 Security Plan Changes 1, 2, 3 02/08/2021 02/12/2021 IP 71151 001338 Performance Indicator Verification UNIT 2 IN-SERVICE INSPECTION 1 2 03/08/2021 03/12/2021 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
RP OCCUPATIONAL RAD SAFETY BASELINE INSPECTION 3 1, 2, 3 03/08/2021 03/12/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 03/08/2021 03/12/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2, 3 03/08/2021 03/12/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 03/08/2021 03/12/2021 IP 71124.04 000728 Occupational Dose Assessment 1, 2, 3 03/08/2021 03/12/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2, 3 03/08/2021 03/12/2021 IP 71151 000746 Performance Indicator Verification 1, 2, 3 04/12/2021 04/16/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 04/12/2021 04/16/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2, 3 04/12/2021 04/16/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 04/12/2021 04/16/2021 IP 71124.04 000728 Occupational Dose Assessment 1, 2, 3 04/12/2021 04/16/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2, 3 04/12/2021 04/16/2021 IP 71151 000746 Performance Indicator Verification BROWNS FERRY INITIAL LICENSE EXAM 6 1, 2, 3 04/12/2021 04/16/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1, 2, 3 05/17/2021 05/28/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report Browns Ferry 03/01/2020 - 12/31/2021 Unit Start End Activity CAC Title Staff Count DESIGN BASES ASSURANCE INSPECTION (TEAMS) 4 1, 2, 3 05/17/2021 05/21/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
1, 2, 3 06/07/2021 06/11/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
EMERGENCY PREPAREDNESS EXERCISE 5 1, 2, 3 06/20/2021 06/26/2021 IP 71114.01 000716 Exercise Evaluation 1, 2, 3 06/20/2021 06/26/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2, 3 06/20/2021 06/26/2021 IP 71151 001397 Performance Indicator Verification TARGET SET INSPECTION 2 1, 2, 3 12/06/2021 12/10/2021 IP 71130.14 000743 Review of Power Reactor Target Sets This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.