Category:Inspection Report Correspondence
MONTHYEARIR 05000277/20244022024-03-12012 March 2024 Cybersecurity Inspection Report 05000277/2024402 and 05000278/2024402 (Cover Letter Only) IR 05000277/20164042016-08-25025 August 2016 Security Inspection Report 05000277/2016404 and 05000278/2016404 (Cover Letter Only) IR 05000277/20084032008-04-28028 April 2008 IR 05000277-08-403, & IR 05000278-08-403, on 03/24/2008 - 03/28/2008, Peach Bottom Atomic Power Station, Units 2 & 3, Physical Protection. (Letter Only W/O OUO-SRI) IR 05000277/20084042008-04-18018 April 2008 IR 05000277-08-404, IR 05000278-08-404, - Cover Letter for Peach Bottom Station - NRC Deviation Memorandum Inspection - Inattentive Security Officer Root Cause Corrective Action Evaluation - (Letter Only - Public) 04/18/2008 IR 05000277/20074062008-01-24024 January 2008 IR 05000277-07-406, and IR 05000278-07-406, on 12/05/2007 - 1/10/2008, for Peach Bottom, Units 2 and 3, Event Followup ML0522104192005-06-0101 June 2005 PI&R Inspection Requests for IR 05000277-05-006, 05000278-05-006, on 06/01 - 07/28/2005 IR 05000277/20020032002-06-13013 June 2002 IR 05000277-02-03, IR 05000278-02-03, on 03/31-05/18/2002; Exelon Generation Company, Peach Bottom Atomic Power Station; Units 2 and 3. Operability Evaluations. Non-cited Violation Identified IR 05000277/20020022002-04-29029 April 2002 IR 05000277/2002-002, IR 05000278/2002-002, on 02/17-03/30/2002; Exelon Generation Company, Peach Bottom Atomic Power Station; Units 2 and 3. Heat Sink Performance, Licensed Operator Requalification Program IR 05000277/20010152002-03-0101 March 2002 IR 05000277/2001-015, IR 05000278/2001-015, on 12/30-02/16/2002; Exelon Generation Company, Peach Bottom Atomic Power Station; Units 2 and 3. Integrated Report IR 05000277/20010102002-01-17017 January 2002 IR 05000277/2001-010, IR 05000278/2001-010, Peach Bottom Atomic Power Station Units 2 & 3, Inspection on 11/18/2001 - 12/29/2001related to Operability Evaluations. One Noncited Violation Noted 2024-03-12
[Table view] Category:Letter
MONTHYEARIR 05000277/20240032024-11-0404 November 2024 Integrated Inspection Report 05000277/2024003 and 05000278/2024003 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24281A1012024-10-0707 October 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24221A2582024-09-0606 September 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Peach Bottom Atomic Power Station, Units 2 and 3 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification 05000277/LER-2024-003, Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum2024-09-0505 September 2024 Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000277/20240102024-08-23023 August 2024 Fire Protection Team Inspection Report 05000277/2024010 and 05000278/2024010 ML24235A0342024-08-23023 August 2024 U.S. Nuclear Regulatory Commission’S Analysis of Constellation Energy Generation’S Decommissioning Funding Status Report IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) IR 05000277/20240022024-08-14014 August 2024 Integrated Inspection Report 05000277/2024002 and 05000278/2024002 ML24225A1692024-08-12012 August 2024 10 CFR 50.46 Annual Report ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24214A3232024-08-0101 August 2024 Response to Request for Additional Information - Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) ML24191A0612024-07-0606 July 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24177A1512024-06-24024 June 2024 Post Accident Monitoring Instrumentation Report ML24166A1172024-06-20020 June 2024 Regulatory Audit Summary Regarding Proposed Alternative Schedule to Complete Decommissioning Beyond 60 Years RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000277/20243012024-06-13013 June 2024 Initial Operator Licensing Examination Report 05000277/2024301 and 05000278/2024301 RS-24-058, Regarding Subsequent License Renewal Environmental Review2024-06-0505 June 2024 Regarding Subsequent License Renewal Environmental Review ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24150A2722024-05-29029 May 2024 Annual Radiological Environmental Operating Report 81, January 1, 2023 Through December 31, 2023 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000277/20240012024-05-13013 May 2024 Integrated Inspection Report 05000277/2024001 and 05000278/2024001 ML24134A1792024-05-13013 May 2024 Supplemental Information in Support of Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations IR 05000277/20245012024-05-0808 May 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2024501 and 05000278/2024501 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24121A1832024-04-30030 April 2024 Pre-Submittal Meeting Presentation Material Peach Bottom ECCS Compensated Level System Replacement Project ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24120A2762024-04-23023 April 2024 Independent Spent Fuel Storage Installation (ISFSI) Facility - Annual Radioactive Effluent Release Report 66 January 1, 2023 Through December 31, 2023 CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24107A2462024-04-15015 April 2024 Submittal of Changes to Technical Specifications Bases ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24102A0472024-04-11011 April 2024 Operator Licensing Examination Approval 05000277/LER-2024-002, Uncoordinated DC Circuits Cause Unanalyzed Condition2024-04-0808 April 2024 Uncoordinated DC Circuits Cause Unanalyzed Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. IR 05000277/20244022024-03-12012 March 2024 Cybersecurity Inspection Report 05000277/2024402 and 05000278/2024402 (Cover Letter Only) ML24061A2642024-03-0101 March 2024 Revision of Two Procedures That Implement the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) Commissioners ML24060A1192024-02-29029 February 2024 Notification of Conduct of a Fire Protection Team Inspection 2024-09-06
[Table view] Category:Inspection Report
MONTHYEARIR 05000277/20240032024-11-0404 November 2024 Integrated Inspection Report 05000277/2024003 and 05000278/2024003 IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) IR 05000277/20240102024-08-23023 August 2024 Fire Protection Team Inspection Report 05000277/2024010 and 05000278/2024010 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) IR 05000277/20240022024-08-14014 August 2024 Integrated Inspection Report 05000277/2024002 and 05000278/2024002 IR 05000277/20243012024-06-13013 June 2024 Initial Operator Licensing Examination Report 05000277/2024301 and 05000278/2024301 IR 05000277/20240012024-05-13013 May 2024 Integrated Inspection Report 05000277/2024001 and 05000278/2024001 IR 05000277/20245012024-05-0808 May 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2024501 and 05000278/2024501 IR 05000277/20244022024-03-12012 March 2024 Cybersecurity Inspection Report 05000277/2024402 and 05000278/2024402 (Cover Letter Only) IR 05000277/20230062024-02-28028 February 2024 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2023006 and 05000278/2023006) IR 05000171/20230012024-02-20020 February 2024 Constellation Energy Generation, LLC - Peach Bottom Atomic Power Station, Unit 1 - NRC Inspection Report No. 05000171/2023001 IR 05000277/20230042024-02-12012 February 2024 Integrated Inspection Report 05000277/2023004 and 05000278/2023004 IR 05000277/20234022024-01-11011 January 2024 Security Baseline Inspection Report 05000277/2023402 and 05000278/2023402 and Independent Spent Fuel Storage Installation Security Inspection 07200029/2023401 IR 05000277/20230032023-10-30030 October 2023 Integrated Inspection Report 05000277/2023003 and 05000278/2023003 and Exercise of Enforcement Discretion IR 05000277/20244012023-10-0505 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000277/2024401 and 05000278/2024401 IR 05000277/20230102023-09-15015 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000277/2023010 and 05000278/2023010 and Notice of Violation ML23251A2022023-09-11011 September 2023 Cover Letter W/Report IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) IR 05000277/20230112023-08-15015 August 2023 Comprehensive Engineering Team Inspection Report 05000277/2023011 and 05000278/2023011 IR 05000277/20230022023-08-0808 August 2023 Integrated Inspection Report 05000277/2023002 and 05000278/2023002 IR 05000277/20230402023-07-17017 July 2023 95001 Inspection Supplemental Report 05000277/2023040 and Follow-Up Assessment Letter IR 05000277/20230012023-05-0808 May 2023 Integrated Inspection Report 05000277/2023001 and 05000278/2023001 IR 05000277/20220042023-04-0505 April 2023 Acknowledgement of Dispute of Green Finding - NRC Inspection Report 05000277/2022004 and 05000278/2022004 IR 05000277/20234012023-03-27027 March 2023 Security Baseline Inspection Report 05000277/2023401 and 05000278/2023401 IR 05000277/20230122023-03-10010 March 2023 Title 10 of the Code of Federal Regulations 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components Inspection Report 05000277/2023012 and 05000278/2023012 IR 05000277/20220062023-03-0101 March 2023 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2022006 and 05000278/2022006) ML23033A3332023-02-0202 February 2023 Integrated Inspection Report 05000277/2022004 and 05000278/2022004 IR 05000171/20220012023-01-0404 January 2023 Constellation Energy Generation, LLC, Peach Bottom Atomic Power Station, Unit 1 - NRC Inspection Report 05000171/2022001 IR 05000277/20220902022-11-28028 November 2022 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation, Inspection Report 05000277/2022090 IR 05000277/20220032022-10-27027 October 2022 Integrated Inspection Report 05000277/2022003 and 05000278/2022003 and Preliminary White Finding and Apparent Violation IR 05000277/20224012022-09-27027 September 2022 Material Control and Accounting Program Inspection Report 05000277/2022401 and 05000278/2022401 (Cover Letter Only) IR 05000277/20220052022-08-31031 August 2022 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2022005 and 05000278/2022005) IR 05000277/19570012022-08-19019 August 2022 631999-Termination License 50-27757-01 for G. Scott Crowther Dba Crowther Associates IR 07200079/20224042022-08-0404 August 2022 NRC Security Inspection Report 07200079/2022404 (Cover Letter) IR 05000277/20223012022-07-28028 July 2022 Initial Operator Licensing Examination Report 05000277/2022301 and 05000278/2022301 IR 05000277/20220022022-07-28028 July 2022 Integrated Inspection Report 05000277/2022002 and 05000278/2022002 IR 05000277/20224032022-07-13013 July 2022 Cyber Security Inspection Report 05000277/2022403 and 05000278/2022403 (Cover Letter Only) IR 05000277/20224022022-06-15015 June 2022 Security Baseline Inspection Report 05000277/2022402 and 05000278/2022402 and Independent Spent Fuel Storage Installation Security Inspection Report 07200029/2022401 (Cover Letter Only) IR 05000277/20225012022-06-0808 June 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2022501 and 05000278/2022501 IR 05000277/20220112022-05-18018 May 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000277/2022011 and 05000278/2022011 ML22117A0362022-04-27027 April 2022 Integrated Inspection Report 05000277/2022001 and 05000278/2022001 IR 05000482/20220012022-04-25025 April 2022 Integrated Inspection Report 05000482/2022001 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2022001 IR 05000277/20210062022-03-0202 March 2022 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2021006 and 05000278/2021006) IR 05000277/20210042022-02-0909 February 2022 Integrated Inspection Report 05000277/2021004 and 05000278/2021004 IR 05000482/20210042022-01-19019 January 2022 Integrated Inspection Report 05000482/2021004 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2021002 IR 05000171/20210012022-01-12012 January 2022 Safstor Inspection Report 05000171/2021001 IR 05000277/20223022022-01-10010 January 2022 Operator Licensing Retake Examination Report 05000277/2022302 and 05000278/2022302 IR 05000277/20210032021-11-0909 November 2021 Integrated Inspection Report 05000277/2021003 and 05000278/2021003 IR 05000482/20210032021-11-0505 November 2021 Integrated Inspection Report 05000482/2021003 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2021001, WC2021003 IR Ch IR 07200079/20214012021-10-21021 October 2021 ISFSI Security Inspection Report 07200079/2021401 2024-08-29
[Table view] |
Text
ril 18, 2008
SUBJECT:
PEACH BOTTOM ATOMIC POWER STATION - NRC DEVIATION MEMORANDUM INSPECTION - INATTENTIVE SECURITY OFFICER ROOT CAUSE CORRECTIVE ACTION EVALUATION - INSPECTION REPORT NOS.
05000277/2008404 AND 05000278/2008404
Dear Mr. Pardee:
On March 7, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a Deviation Memorandum inspection at your Peach Bottom Atomic Power Station (PBAPS). The enclosed inspection report documents the inspection results, which were discussed on March 6, 2008, with Mr. Michael Massaro, Plant Manager, and on March 7, 2008, with other members of your staff.
On November 23, 2007, the NRC Executive Director for Operations approved a Deviation Memorandum (ML073320344) which provides for enhanced oversight of PBAPS. This enhanced oversight includes additional inspections in the areas of security force performance monitoring, corrective action effectiveness, safety conscious work environment, and verification of Confirmatory Action Letter (ML072920283) commitments.
The purpose of this inspection was to evaluate the effectiveness of the corrective actions taken in response to the inattentive security officer events discovered in September 2007. The NRC inspection approach included procedure and corrective action reviews, individual and management interviews, record reviews, walkdowns, security turnover observations, and discussions to gather input and comments directly from site workers. The inspectors also observed work activities and meetings.
Overall, the results for the material reviewed during this inspection indicate that the corrective actions taken as a result of the inattentive security officer events have been generally effective, and that you have made progress integrating use of the corrective action program within the security organization. No findings of significance were identified during this inspection.
When separated from its Enclosure, this Document is DECONTROLLED. Mr. As part of our normal assessment process, this inspection will be one of the inputs for our PBAPS mid-cycle review which will be conducted during the summer of 2008. The mid-cycle review will collectively assess Deviation Memorandum and Confirmatory Action Letter inspection results in conjunction with a review of the last 12 months of Reactor Oversight Process baseline inspection activity and performance indicators.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response Security-Related Information - Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Sincerely,
/RA/
Paul G. Krohn, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos.: 50-277, 50-278 License Nos.: DPR-44, DPR-56 Enclosures: Inspection Report 05000277/2008404 and 05000278/2008404 w/Attachment: Supplemental Information Mr. cc w/encl; w/OUO-SRI J. Kovalchick, Manager - Nuclear Security J. Powers, Director, Office of Homeland Security, PA D. Allard, Director, Department of Environmental Protection, Bureau of Radiation Protection, PA G. Aburn, Maryland Department of Environment A. Lauland, Homeland Security Advisor, MD cc w/o encl w/o OUO-SRI:
C. Crane, Executive Vice President, Exelon, Chief Operating Officer, Exelon Generation J. Grimes, Site Vice President, Peach Bottom M. Pacilio, Chief Operating Officer, Exelon M. Massaro, Plant Manager, Peach Bottom J. Armstrong, Regulatory Assurance Manager, Peach Bottom J. Bardurski, Manager, Financial Control & Co-Owner Affairs R. DeGregorio, Senior Vice President, Mid-Atlantic P. Cowan, Director, Licensing K. Jury, Vice President, Licensing and Regulatory Affairs J. Bradley Fewell, Associate General Counsel, Exelon Director, Training Correspondence Control Desk R. McLean, Power Plant and Environmental Review Division (MD)
S. Pattison, Asst Secretary, MD Department of Environment T. Snyder, MD Department of Environment Public Service Commission of Maryland, Engineering Division Board of Supervisors, Peach Bottom Township B. OConnor, Council Administrator of Harford County Council R. Ayers, Deputy Manager, Harford County Div of Emergency Operations E. Crist, Harford County Emergency Management R. Brooks, Cecil County Dept. of Emergency Services Mr. & Mrs. Dennis Hiebert, Peach Bottom Alliance E. Epstein, TMI - Alert J. Johnsrud, National Energy Committee, Sierra Club Mr. & Mrs. Kip Adams R. Fletcher, Department of Environment, Radiological Health Program R. French, Dir, PA Emergency Management Agency D. Lockbaum, Union of Concerned Scientists 2 As part of our normal assessment process, this inspection will be one of the inputs for our PBAPS mid-cycle review which will be conducted during the summer of 2008. The mid-cycle review will collectively assess Deviation Memorandum and Confirmatory Action Letter inspection results in conjunction with a review of the last 12 months of Reactor Oversight Process baseline inspection activity and performance indicators.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response Security-Related Information - Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Sincerely,
/RA/
Paul G. Krohn, Chief Reactor Projects Branch 4 Division of Reactor Projects Enclosures: Inspection Report 05000277/2008404 and 05000278/2008404 w/Attachment:
Supplemental Information Distribution:
S. Collins, ORA M. Gamberoni, DRS N. McNamara, SLO M. Dapas, ORA D. Roberts, DRS K. Farrar, ORA D. Lew, DRP D. Caron, DRS D. Holody, ORA J. Clifford, DRP F. Brown, NRR S. Williams, RI, OEDO P. Krohn, DRP J. Anderson, NRR J. Trapp, DRS E. Dacus, OCA T. Setzer, DRP R. Correia, NSIR R. Fuhrmeister, DRP D. Screnci, PLO F. Bower, DRP N. Sheehan, PLO M. Brown, DRP M. McLaughlin, SLO SUNSI Review Complete: ____pgk__ (Reviewer=s Initials)
DOCUMENT NAME: G:\DRP\BRANCH4\PEACH BOTTOM\Inspection Reports\2008\DevmemoRCErev2.doc After declaring this document AAn Official Agency Record@ letter will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS RI/DRP RI/DRS RI/DRP NAME PFrechette/ PF TSetzer/TS JTrapp/JMT PKrohn/PGK DATE 04/10 /08 04/ 08 /08 04/11 /08 04/ 08 /08 OFFICIAL RECORD COPY