Category:Inspection Report
MONTHYEARIR 05000277/20234022024-01-11011 January 2024 Security Baseline Inspection Report 05000277/2023402 and 05000278/2023402 and Independent Spent Fuel Storage Installation Security Inspection 07200029/2023401 IR 05000277/20230032023-10-30030 October 2023 Integrated Inspection Report 05000277/2023003 and 05000278/2023003 and Exercise of Enforcement Discretion IR 05000277/20244012023-10-0505 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000277/2024401 and 05000278/2024401 IR 05000277/20230102023-09-15015 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000277/2023010 and 05000278/2023010 and Notice of Violation ML23251A2022023-09-11011 September 2023 Cover Letter W/Report IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) IR 05000277/20230112023-08-15015 August 2023 Comprehensive Engineering Team Inspection Report 05000277/2023011 and 05000278/2023011 IR 05000277/20230022023-08-0808 August 2023 Integrated Inspection Report 05000277/2023002 and 05000278/2023002 IR 05000277/20230402023-07-17017 July 2023 95001 Inspection Supplemental Report 05000277/2023040 and Follow-Up Assessment Letter IR 05000277/20230012023-05-0808 May 2023 Integrated Inspection Report 05000277/2023001 and 05000278/2023001 IR 05000277/20220042023-04-0505 April 2023 Acknowledgement of Dispute of Green Finding - NRC Inspection Report 05000277/2022004 and 05000278/2022004 IR 05000277/20234012023-03-27027 March 2023 Security Baseline Inspection Report 05000277/2023401 and 05000278/2023401 IR 05000277/20230122023-03-10010 March 2023 Title 10 of the Code of Federal Regulations 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components Inspection Report 05000277/2023012 and 05000278/2023012 IR 05000277/20220062023-03-0101 March 2023 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2022006 and 05000278/2022006) ML23033A3332023-02-0202 February 2023 Integrated Inspection Report 05000277/2022004 and 05000278/2022004 IR 05000171/20220012023-01-0404 January 2023 Constellation Energy Generation, LLC, Peach Bottom Atomic Power Station, Unit 1 - NRC Inspection Report 05000171/2022001 IR 05000277/20220902022-11-28028 November 2022 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation, Inspection Report 05000277/2022090 IR 05000277/20220032022-10-27027 October 2022 Integrated Inspection Report 05000277/2022003 and 05000278/2022003 and Preliminary White Finding and Apparent Violation IR 05000277/20224012022-09-27027 September 2022 Material Control and Accounting Program Inspection Report 05000277/2022401 and 05000278/2022401 (Cover Letter Only) IR 05000277/20220052022-08-31031 August 2022 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2022005 and 05000278/2022005) IR 05000277/19570012022-08-19019 August 2022 631999-Termination License 50-27757-01 for G. Scott Crowther Dba Crowther Associates IR 07200079/20224042022-08-0404 August 2022 NRC Security Inspection Report 07200079/2022404 (Cover Letter) IR 05000277/20220022022-07-28028 July 2022 Integrated Inspection Report 05000277/2022002 and 05000278/2022002 IR 05000277/20223012022-07-28028 July 2022 Initial Operator Licensing Examination Report 05000277/2022301 and 05000278/2022301 IR 05000277/20224032022-07-13013 July 2022 Cyber Security Inspection Report 05000277/2022403 and 05000278/2022403 (Cover Letter Only) IR 05000277/20224022022-06-15015 June 2022 Security Baseline Inspection Report 05000277/2022402 and 05000278/2022402 and Independent Spent Fuel Storage Installation Security Inspection Report 07200029/2022401 (Cover Letter Only) IR 05000277/20225012022-06-0808 June 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2022501 and 05000278/2022501 IR 05000277/20220112022-05-18018 May 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000277/2022011 and 05000278/2022011 ML22117A0362022-04-27027 April 2022 Integrated Inspection Report 05000277/2022001 and 05000278/2022001 IR 05000482/20220012022-04-25025 April 2022 Integrated Inspection Report 05000482/2022001 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2022001 IR 05000277/20210062022-03-0202 March 2022 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2021006 and 05000278/2021006) IR 05000277/20210042022-02-0909 February 2022 Integrated Inspection Report 05000277/2021004 and 05000278/2021004 IR 05000482/20210042022-01-19019 January 2022 Integrated Inspection Report 05000482/2021004 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2021002 IR 05000171/20210012022-01-12012 January 2022 Safstor Inspection Report 05000171/2021001 IR 05000277/20223022022-01-10010 January 2022 Operator Licensing Retake Examination Report 05000277/2022302 and 05000278/2022302 IR 05000277/20210032021-11-0909 November 2021 Integrated Inspection Report 05000277/2021003 and 05000278/2021003 IR 05000482/20210032021-11-0505 November 2021 Integrated Inspection Report 05000482/2021003 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2021001, WC2021003 IR Ch IR 07200079/20214012021-10-21021 October 2021 ISFSI Security Inspection Report 07200079/2021401 IR 05000277/20210122021-09-22022 September 2021 Biennial Problem Identification and Resolution Inspection Report 05000277/2021012 and 05000278/2021012 IR 05000277/20213012021-09-0101 September 2021 Initial Operator Licensing Examination Report 05000277/2021301 and 05000278/2021301 IR 05000277/20210052021-09-0101 September 2021 Updated Inspection Plan for the Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2021005 and 05000278/2021005) IR 05000277/20210022021-08-0404 August 2021 Integrated Inspection Report 05000277/2021002 and 05000278/2021002 IR 05000277/20210102021-07-20020 July 2021 Triennial Fire Protection Inspection Report 05000277/2021010 and 05000278/2021010 IR 05000277/20210012021-04-28028 April 2021 Integrated Inspection Report 05000277/2021001 and 05000278/2021001 IR 05000277/20214012021-04-27027 April 2021 Security Baseline Inspection Report 05000277/2021401 and 05000278/2021401 IR 05000277/20210112021-04-0101 April 2021 Temporary Instruction 2515/194 Inspection Report 05000277/2021011 and 05000278/2021011 IR 05000277/20200062021-03-0303 March 2021 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2020006 and 05000278/2020006) IR 05000277/20200042021-02-0505 February 2021 Integrated Inspection Report 05000277/2020004 and 05000278/2020004 and Independent Spent Fuel Storage Installation Inspection Report 07200029/2020401 IR 07200029/20200012021-01-0505 January 2021 Peach Atomic Power Station, Independent Spent Fuel Storage Installation (ISFSI) NRC Inspection Report No. 07200029/2020001 IR 05000277/20205012020-12-17017 December 2020 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2020501 and 05000278/2020501 2024-01-11
[Table view] Category:Letter
MONTHYEARML24022A2262024-01-22022 January 2024 (PBAPS) Unit 3 - Submittal of the Inservice Inspection (ISI) Owner'S Activity Report (OAR) for the 24th Refueling Outage for Unit 3 ML23346A2412024-01-17017 January 2024 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information (EPID L-2019-PMP-0061) - Letter IR 05000277/20234022024-01-11011 January 2024 Security Baseline Inspection Report 05000277/2023402 and 05000278/2023402 and Independent Spent Fuel Storage Installation Security Inspection 07200029/2023401 ML23354A1922024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML23355A0622023-12-18018 December 2023 Independent Spent Fuel Storage Installation (Isfsi), Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23334A2502023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23305A3472023-11-0101 November 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) IR 05000277/20230032023-10-30030 October 2023 Integrated Inspection Report 05000277/2023003 and 05000278/2023003 and Exercise of Enforcement Discretion ML23286A0012023-10-13013 October 2023 Reply to a Notice of Violation (NOV) - NOV 05000277, 05000278/2023010-01 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23271A1342023-10-11011 October 2023 Dtf Analysis Letter IR 05000277/20244012023-10-0505 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000277/2024401 and 05000278/2024401 ML23265A1502023-09-22022 September 2023 License Amendment Request Revise a License Condition and Certain Technical Specifications to Remove Restrictions in Support of Decommissioning Activities ML23264A8682023-09-21021 September 2023 Independent Spent Fuel Storage Installation Registration of Dry Storage Canister WC-EOS-37PTH-008-B4L, WC-EOS-37PTH-007-B4L, and WC-EOS-37PTH-002-B4L IR 05000277/20230102023-09-15015 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000277/2023010 and 05000278/2023010 and Notice of Violation ML23251A2022023-09-11011 September 2023 Cover Letter W/Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23232A0012023-08-19019 August 2023 Revision of One Procedure That Implements the Radiological Emergency Response Plan (Rerp). Includes EPP 06-009, Rev. 13 IR 05000277/20230112023-08-15015 August 2023 Comprehensive Engineering Team Inspection Report 05000277/2023011 and 05000278/2023011 ML23226A1112023-08-14014 August 2023 10 CFR 50.46 Annual Report IR 05000277/20230022023-08-0808 August 2023 Integrated Inspection Report 05000277/2023002 and 05000278/2023002 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor IR 05000277/20230402023-07-17017 July 2023 95001 Inspection Supplemental Report 05000277/2023040 and Follow-Up Assessment Letter ML23188A0532023-07-0707 July 2023 Registration of Use of Independent Spent Fuel Storage Installation (ISFSI) Casks ML23186A1272023-07-0606 July 2023 Response to Disputed Non-Cited Violation Documented in Peach Bottom Atomic Power Station, Units 2 and 3, Inspection Report 05000277/2022004 and 05000278/2022004 ML23178A0352023-06-27027 June 2023 Senior Reactor and Reactor Operator Initial License Examinations RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23151A4162023-05-31031 May 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) ML23150A2052023-05-30030 May 2023 Independent Spent Fuel Storage Installation (Isfsi), Annual Radiological Environmental Operating Report 80 January 1, 2022 Through December 31, 2022 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23142A1602023-05-23023 May 2023 Summary of April 11, 2023, Public Observation Meeting with Constellation Energy Generation, LLC Re Proposed Exemption Request from Work Hour Requirements ML23132A1582023-05-18018 May 2023 Correction to Technical Specification 3.4.7 (Page 3.4-16) Issued in Amendment No. 337 ML23132A1532023-05-12012 May 2023 Transmittal of 2022 Annual Financial Reports WM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) IR 05000277/20230012023-05-0808 May 2023 Integrated Inspection Report 05000277/2023001 and 05000278/2023001 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI 2024-01-05
[Table view] |
Text
ber 24, 2002
SUBJECT:
PEACH BOTTOM ATOMIC POWER STATION UNITS 2 & 3 NRC-EVALUATED EMERGENCY PREPAREDNESS EXERCISE INSPECTION REPORT 50-277/02-008, 50-278/02-008
Dear Mr. Skolds:
The enclosed report documents an inspection at the Peach Bottom Atomic Power Station, Units 2 & 3, which evaluated the performance of your emergency response organization during the November 19, 2002, full-participation exercise and the post-exercise critique as specified in the reactor oversight program. The inspectors discussed the findings of this inspection with Mr. R.
G. West and other members of your staff on November 21, 2002.
This inspection was an examination of activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license. Within these areas, the inspection consisted of a selected examination of procedures and representative records, observations of activities, and interviews with personnel.
Based on the results of this inspection, no findings of significance were identified.
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/ADAMS.html (the Public Electronic Reading Room).
Should you have any questions regarding this report, please contact Mr. Richard J. Conte at (610) 337-5183.
Sincerely,
/RA/
Richard J. Conte, Chief Operational Safety Branch Division of Reactor Safety Docket Nos. 50-277; 50-278 License Nos.: DPR-44, DPR-56
Enclosures:
Inspection Report No. 50-287/02-011, 50-288/02-011 Attachment 1: Supplemental Information
REGION I==
Docket Nos: 50-277, 50-278 License Nos: DPR-44, DPR-56 Report Nos: 50-277/02-008, 50-278/02-008 Licensee: Exelon Generation Company, LLC Correspondence Control Desk 200 Exelon Way, KSA 1-N-1 Kennett Square, PA 19348 Facilities: Peach Bottom Atomic Power Station Units 2 & 3 Location: 1848 Lay Road Delta, Pennsylvania Dates: November 19-21, 2002 Inspectors: N. McNamara, Sr. Emergency Preparedness Inspector T. Fish, Sr. Operations Engineer M. Buckley, Resident Inspector, Susquehanna J. Noggle, Sr. Health Physicist Approved by: Richard J. Conte, Chief Operational Safety Branch Division of Reactor Safety
SUMMARY OF FINDINGS IR 05000277/02-008, IR 05000278/02-008; on 11/19-21/2002; Peach Bottom Atomic Power Station; Units 2&3; Emergency Preparedness Exercise Report.
This team inspection was conducted by regional based inspectors and a resident inspector. No findings of significance were identified. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversite Process, Revision 3, dated July 2000.
A. Inspector Identified Findings Cornerstone: Emergency Preparedness No findings of significance were identified B. Licensee Identified Findings None ii
Report Details 1. REACTOR SAFETY Cornerstone: Emergency Preparedness (EP)
1EP1 Exercise Evaluation A. Inspection Scope An in-office review was conducted of Exelons exercise objectives submitted to the NRC on August 20, 2002 and the exercise scenario submitted on September 29, 2002 to determine if the Peach Bottom exercise would test major elements of Exelons Emergency Plan as required by 10 CFR 50.47(b)(14).
The onsite inspection consisted of the following review and assessment:
- The adequacy of Exelons performance on the biennial full-participation exercise performance by primarily focusing on the implementation of the risk-significant planning standards (RSPS) in 10 CFR 50.47 (b) (4), (5), (9) & (10) which are emergency classification, offsite notification, radiological assessment, and protective action recommendations, respectively.
- The overall adequacy of Exelons emergency response facilities and its implementation of NUREG-0696, Functional Criteria for Emergency Response Facilities and Emergency Plan commitments. The facilities assessed were the simulator, technical support center (TSC), the operations support center (OSC)
and the emergency operations facility (EOF).
- Other performance areas besides the RSPS, such as, the emergency response organizations (ERO) recognition of abnormal plant conditions, command and control, intra- and inter-facility communications, prioritization of mitigation activities, utilization of repair and field monitoring teams, interface with offsite agencies, and the overall implementation of the Emergency Plan and its implementing procedures.
- Past performance issues from NRC inspection reports and Exelon drill reports to determine effectiveness of corrective actions as demonstrated during this exercise to ensure compliance with 10CFR50.47(b)(14).
- The post-exercise critique to evaluate the Exelons self-assessment of its ERO performance during the exercise and to ensure compliance with 10CFR50 Appendix E.IV.F.2.g.
The inspectors reviewed various documentation which are listed in Attachment 1 to this report.
b. Findings No findings of significance were identified in this area.
1EP4 Emergency Action Level and Emergency Plan Changes a. Inspection Scope The inspectors conducted an in-office review of Exelon submitted changes for the Emergency Plan-related documents received from March 2002 to September 2002 to determine if the changes decreased the effectiveness of the Plan. A thorough review was conducted of documents related to the RSPS whereas a cursory review was conducted for non-RSPS documents. In October, 2002 Exelon submitted to the NRC a Standardized Emergency Plan and an annex to the Plan specific to Peach Bottom. A review of these documents are ongoing and the NRCs assessment of the changes will be documented in a subsequent inspection report.
b. Findings No findings of significance were identified in this area.
4. OTHER ACTIVITIES 4OA1 Performance Indicator (PI) Verification a. Inspection Scope The inspectors reviewed Exelons procedure for developing the data for the EP PIs which are: (1) Drill and Exercise Performance (DEP), (2) ERO Drill Participation and (3) ANS Reliability. The inspectors also reviewed the Exelons drill/exercise reports, training records and ANS testing data for 2002 to verify the accuracy of the reported data. The review was conducted in accordance with NRC Inspection Procedure 71151.
The acceptance criteria are 10 CFR 50.9 and NEI 99-02, Revision 2, Regulation Assessment Performance Indicator Guideline.
b. Findings No findings of significance were identified in this area.
4OA2 Identification and Resolution of Problems a. Inspection Scope The inspectors reviewed Exelons critique findings documented in 2001 and 2002 drill and exercise reports to determine if significant performance trends exist and to determine the effectiveness of licensee corrective actions based upon ERO performance during the exercise. The inspectors verified that issues identified during this exercise were entered into Exelons corrective action program and reviewed
condition reports related to significant findings from past drill/exercise reports to assess the adequacy of the corrective actions.
b. Findings No findings of significance were identified.
40A6 Meetings, including Exit The inspectors presented the inspection results to Mr. R. G. West and other members of the Exelons staff at the conclusion of the inspection on November 21, 2002.
ATTACHMENT 1 SUPPLEMENTAL INFORMATION KEY POINTS OF CONTACT Peach Bottom Atomic Power Station, Units 2 & 3 G. Johnston, Plant Manager D. Tailleart, MAROG Emergency Preparedness Manager A. Coppa, PB EP Manager S. Mannix, MAROG Emergency Preparedness NRC M. Shanbaky, Branch Chief, Region I S. Iyer, Reactor Engineer, Region I LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED Opened None Discussed None LIST OF ACRONYMS ANS Alert and Notification System DEP Drill and Exercise Performance EOF Emergency Operations Facility EP Emergency Preparedness ERO Emergency Response Organization OSC Operations Support Center PI Performance Indicator RSPS Risk Significant Planning Standard SDP Significant Determination Process TSC Technical Support Center
LIST OF DOCUMENTS REVIEWED Exelon Nuclear Standardized Radiological Emergency Plan Exelon Radiological Emergency Plan Annex for Peach Bottom Atomic Power Station Emergency Procedure No. EP-AA-111, Emergency Classification and PARs Emergency Procedure No. EP-AA-112, ERO/ERF Activation and Operation Emergency Procedure No. EP-AA-114, Notifications Emergency Procedure No. EP-AA-113, Personnel Protective Actions Emergency Procedure No. EP-AA-112-200, TSC Activation and Operation Emergency Procedure No. EP-AA-112-100, Control Room Operations Emergency Procedure No. EP-AA-112, ERO/Emergency Response Facility Activation Emergency Procedure No. EP-MA-110-200, Dose Assessment Emergency Procedure No. EP-AA-112-402, EOF Command and Control Training Drill Findings and Observation Report, Dated January 2, 20002 PB October 18, 2002 Pre-Exercise Preliminary Evaluation Report, dated October 23, 2002 PB August 22, 2002 Standard Plan Drill Report, September 20, 202 PB August 29, 2002 DEP Drill Evaluation Report PB August 16, 2002 DEP Drill Evaluation Report Training Drill Findings and Observation Report, dated March 18, 2002 PB Emergency Preparedness Training Drill, dated July 26, 2001 PB Emergency Preparedness Training Drill, dated June 25, 2001 PB Emergency Preparedness Training Drill, dated April 26, 2001 PB Emergency Preparedness Training Drill, dated January 24, 2001