IR 05000269/2016009

From kanterella
Jump to navigation Jump to search
Confirmatory Action Letter Followup Inspection Report 05000269/2016009, 05000270/2016009 and 05000287/2016009
ML16168A176
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 06/16/2016
From: Catherine Haney
Region 2 Administrator
To: Batson S
Duke Energy Carolinas
References
CAL 2-10-003 IR 2016009
Download: ML16168A176 (12)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION une 16, 2016

SUBJECT:

OCONEE NUCLEAR STATION- CONFIRMATORY ACTION LETTER FOLLOWUP INSPECTION REPORT 05000269/2016009, 05000270/2016009, AND 05000287/2016009

Dear Mr. Batson:

In a letter to the U.S. Nuclear Regulatory Commission (NRC) dated April 29, 2016, (ML16131A671), Oconee Nuclear Station (ONS) indicated that it had met the commitments of the June 22, 2010, Confirmatory Action Letter (CAL) (ML101730329) through completion of external flood modifications to mitigate a postulated Jocassee Dam failure.

On May 19, 2016, the NRC completed its review of your actions taken to satisfy the external flooding modification commitments documented in the CAL for ONS Units 1, 2, and 3 and discussed the results of this inspection with you and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection report. No NRC-identified or self-revealing findings were identified during this inspection.

The NRC has determined that the results of this inspection, in conjunction with previously completed inspection activities related to interim compensatory measures, and the April 14, 2016, NRC staff assessment letter approving the revised Flood Hazard Revaluation Report (FHRR) (ML15352A207), provide adequate assurance that the required terms as directed by the June 22, 2010 CAL have been satisfied by ONS. The June 22, 2010, Confirmatory Action Letter is now closed. As stated in the April 14, 2016, letter the NRC staff will address ongoing external flooding issues for ONS within the framework of the Fukushima Near-Term Task Force Recommendation 2.1 process, to ensure consistency in the staffs approach to addressing these issues for all plants. These issues will be addressed in separate correspondence and inspection activities. As stated in the April 14, 2016, letter, the NRC views continued implementation of certain compensatory actions in response to the CAL as an important element in Dukes overall strategy to mitigate the risks associated with a potential failure of the Jocassee Dam. In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this letter, please contact Frank Ehrhardt of my staff at 404-997-4611.

Sincerely,

/RA/

Catherine Haney Regional Administrator Docket Nos.: 50-269, 50-270, 50-287 License Nos.: DPR-38, DPR-47, DPR-55

Enclosure:

NRC IR 05000269/2016009, 05000270/2016009, AND 05000287/2016009 w/Attachment: Supplemental Information

REGION II==

Docket Nos: 50-269, 50-270, 50-287 License Nos: DPR-38, DPR-47, DPR-55 Report Nos: 05000269/2016009, 05000270/2016009, 05000287/2016009 Licensee: Duke Energy Carolinas, LLC Facility: Oconee Nuclear Station, Units 1, 2 and 3 Location: Seneca, SC 29672 Dates: May 16-19, 2016 Inspectors: M. Toth, Project Engineer C. Oelstrom, Construction Inspector Approved by: Frank Ehrhardt, Chief Reactor Projects Branch 1 Division of Reactor Projects Enclosure

SUMMARY

IR 05000269/2016009, 05000270/2016009, and 05000287/2016009; May 16, 2016, through

May 19, 2016; Oconee Nuclear Station (ONS) Units 1, 2 and 3; Confirmatory Action Letter Followup Inspection Report.

The report covered a one-week period of followup inspection by two region-based inspectors associated with the June 22, 2010, Confirmatory Action Letter (CAL) 2-10-003. This inspection included evaluation of five external flood modifications implemented by Oconee Nuclear Station as directed by the CAL. No findings were identified during this inspection. The NRCs program for overseeing the safe operations of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 5.

REPORT DETAILS

1. BACKGROUND

On August 15, 2008, the U.S. Nuclear Regulatory Commission (NRC) issued a letter (Accession No. ML081640244) to Duke Energy Carolinas, LLC (Duke) for Oconee Nuclear Station Units 1, 2, and 3 (ONS) requesting information related to site external flooding, which included a potential failure of the Jocassee Dam. The information requested included a bounding external flood hazard analysis of the ONS site due to a postulated Jocassee Dam failure, which was provided in a letter to the NRC on August 2, 2010, (ML102170006). The NRC evaluated and accepted this analysis in a January 28, 2011, letter to Duke (ML110280153). In concert with this analysis, Duke committed to implement certain interim compensatory measures (ICMs) to mitigate the effects of external flooding at ONS due to a postulated Jocassee Dam failure. A June 3, 2010, letter to the NRC (ML101610083) documented the ICMs, which were subsequently inspected by the NRC. The NRC concluded the inspection with no findings or violations on June 10, 2010, (inspection report dated July 7, 2010, ML12363A083). On June 22, 2010, the NRC issued a Confirmatory Action Letter (CAL 2-10-003) to Duke documenting the licensees commitments regarding external flooding concerns (ML101730329). The CAL acknowledged Dukes commitments to: maintain the ICMs until final resolution of external flooding at ONS due to a postulated Jocassee Dam failure was reached (by submitting an acceptable, updated flood hazard analysis for that event); and to construct and complete permanent flooding modifications to mitigate the inundation associated with that event. The licensees updated flood hazard analysis led to the staff assessment letter, which was issued on January 28, 2011.

On March 12, 2012, the NRC issued a subsequent letter to Duke (ML12053A340)requesting additional information in response to the 2011 Fukushima Dai-ichi accident.

This information was requested in support of the Near Term Task Force (NTTF)evaluation regarding flooding concerns.

On March 12, 2013, Duke submitted its flood hazard reevaluation report (FHRR) for ONS (ML13079A227), which was superseded with a revised FHRR on March 6, 2015, (ML15072A106). The NRC accepted the 2015 FHRR in a staff assessment letter issued on April 14, 2016 (ML15352A207). In this letter, the staff concluded the revised FHRR provided an acceptable alternative flood hazard analysis for a postulated Jocassee Dam failure event for the ONS site, for the purpose of meeting the terms of the June 22, 2010, CAL.

The NRC completed subsequent inspections in April 2013 (ML13115A063) and October 2013, (ML13318A936) at ONS regarding the implementation of the external flooding ICMs to validate whether these CAL commitments were being met. These inspections were in addition to annual baseline inspection activities conducted by the resident inspectors. No findings or violations were issued based on these inspections.

On April 29, 2016, Duke issued a letter to the NRC (ML16131A671) stating that the external flooding modifications were complete. Based on this information, the NRC conducted an on-site inspection of the modifications and concluded these efforts on May 19, 2016. Completion of the external flood modifications was the last remaining commitment of the June 22, 2010, Confirmatory Action Letter requiring inspection. The NRC has determined that Duke has satisfied all of the commitments of the CAL.

OTHER ACTIVITIES

4OA5 Other Activities

.1 Followup on Confirmatory Action Letter (IP 92702)

a. Inspection Scope

The inspectors reviewed the following modifications made by the licensee to comply with the June 22, 2010, Confirmatory Action Letter:

  • 100kV FANT back-up power line tower relocation
  • East slope scour protection
  • Intake dike scour protection
  • Discharge diversion wall

The inspectors verified that the design bases, licensing bases, and performance capability of structures, systems, and components (SSCs) had not been degraded through implementation of the five modifications listed above. As part of this review, inspectors verified that evaluations conducted by the licensee were in accordance with 10 CFR 50.59 and applicable internal procedures. Additionally, the inspectors evaluated whether system functionality and availability, configuration control, post-installation test activities, and changes to documents, such as drawings, procedures, and operator training materials, complied with licensee standards and NRC requirements. The inspectors reviewed documentation and performed field walkdowns of the modifications to determine whether they were installed in accordance with applicable regulatory requirements, standards, and codes. Additionally, the inspectors conducted field walkdowns to verify the as-built condition matched applicable design drawings. As part of the records review and field walkdown of the as-built condition, the inspectors verified:

  • concrete had no material faults, such as cold joints, cracking, voids, exposed rebar, or open joints
  • the transition zone of the concrete sections to ground was without defect or degradation, including no visual signs of settlement, subsidence, and/or rotation
  • the diversion wall foundation was properly backfilled and compacted
  • the scour protection was of the form specified in the design
  • no vegetation was present in between scour protection
  • scour protection was of the type and size specified, and was stable and secure without any visible signs of erosion or washout
  • slopes adhered to design specifications
  • proper backfill was used and compacted to meet intended design requirements
  • backflow preventer gate was installed per design, and the equipment to operate the gate was securely stored in the vicinity of the flood gate
  • procedures for operating the gate clearly indicated where the required operating equipment was located
  • backflow preventer gate framing was solidly affixed to the wall per the design, and guide tracks were free of obstructions or defects
  • FANT line transmission line towers were relocated to updated flood heights based on location along the transmission path (as applicable)

The inspectors reviewed a sample of related corrective action documents to verify the licensee was identifying and correcting any deficiencies associated with modifications.

Documents reviewed are listed in the attachment.

b. Findings

No findings were identified.

4OA6 Meetings, Including Exit

On May 19, 2016, the inspectors presented the inspection results to Mr. Scott Batson and other members of the licensees staff. The inspectors verified that no proprietary information was retained by the inspectors or documented in this report.

ATTACHMENT:

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

C. Arnold, Senior Project Manager, External Flood Protection Project
S. Batson, Site Vice President
D. Baxter, Regulatory Project Manager
E. Burchfield, General Manager Engineering
D. Haile, Regulatory Affairs
D. Hubbard, Director, Organizational Effectiveness
A. Johnson, Fukushima Response Organization
D. Jones, Fukushima Response Manager
R. Ransom, External Flood Protection Project, Lead Civil Engineer
T. Ray, Plant Manager
C. Wasik, Regulatory Affairs Manager

LIST OF ITEMS OPENED, CLOSED, DISCUSSED AND UPDATED

Closed

CAL 2-10-003 CAL OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 COMMITMENTS TO ADDRESS EXTERNAL FLOODING CONCERNS (4OA5)

LIST OF DOCUMENTS REVIEWED