IR 05000269/1973001
| ML19322A910 | |
| Person / Time | |
|---|---|
| Site: | Oconee |
| Issue date: | 02/02/1973 |
| From: | Murphy C NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | James Keppler US ATOMIC ENERGY COMMISSION (AEC) |
| Shared Package | |
| ML19322A898 | List: |
| References | |
| NUDOCS 7911270669 | |
| Download: ML19322A910 (3) | |
Text
O
-
~ ~ -
- - - - ~ ~
~
.
.
!
.,,
-
~ UNITED STATES
"
,
s
", \\?A ATOMIC ENERGY COMMISSION
,
,
'
i
[A fI DIRECCC?.",CE OF EII."*",!!KY CIIT3.T Z 3 necie,. ii - su -c eu g -
g 2m peaca-acs statt, s:=r-assi ym,,
m, n,.
g m,,.3 y.
m.~r.. a c :. m
.
February 2, 1973
.
.
.
J. G. Keppler, Chief, Reactor Test and Operations Branch, Directorate of Regulatory Operations, Headquarters ADVANCE INSPECTION INFORMATION MEMORANDUM - DUKE POWER COMPANY (OCONEE 1)
LICENSE NO. CPPR-33, DOCKET No. 50-269 - REPORT NO. 50-269/73-1
,
\\
This memorandum summarizes information to be contained in R0 Report No.
50-269/73-1. A prelicensing inspection was conducted during the period of January 27 - February 1, 1973. Upon completion or resolution of the following items, Region II will find Oconee 1 ready for issuance of an operating license:
,.
A.
Items to be Completed Prior to Fuel Loading Note: DPC nas coccitted themselve's verbally to complete all the (
following items prior to fuel loading.
1.
Tests DPC has not completed the testing, reviews, evaluations, resolution of deficiencies and approvals pertaining to twenty-nine preoperational tests.
2.
Core Flood Restrictors DPC has not completed the installation of the core flood restrictors.
3.
Reactor Vessel and Internals
_.
,
The cleaning of the reactor vessel and internals has not been completed.
4.
Security Plan DPC does not have an acceptable security plan nor approved implementing procedures.
/
TRANSMITTED VIA MAG CARD
,,
.
2/1/73 - 4:19 p.m. (c5)
7911270 6 6 7
-
--
.. _. - -. -.
-~
- _ _ = -
--
- -
.
l
';
.
,
I
.
..
'
(')
',
'
'
.
-
J. G. Keppler-2-February 2, 1973
.
.
5.
Administrative Pror n as Administrative instructions have not been completed for use of emergency, alarm, maintenance or operating procedures, i
B.
Items to be Completed Prior to Criticality
Note: DPC has committed themselves verbally to complete all of the following items prior to criticality.
1.
Preoperational Tests DPC has not completed twenty-two tests, test reviews, evaluations,
'
approvals and correction of deficiencice, that are necessary prior to criticality.
!
-
\\
2.
Power Ascension Tests
'
DPC does not have approved procedures for all power ascension tests.
3.
Welding Deficiencies DPC has not received and approved ths consultant's final report pertaining to welding deficiencies.
'
'
.
,
4.
Emergency Procedures
{
DPC does not have approved procedures for six categories of emergencies.
5.
Alarm Procedures j
DPC has not approved certain alarm procedures.
'
,
6.
Baseline Inspection ~
Not all the documentation pertaining to the baseline inspection was available for review.
Information to be available on February 5, 1973.
,
e
,
.. _, -
e
.
-.
- - _
.-..
_ _ _ _ - -.
- -
o
- ,'
.
,
%
.
[
,
,,
.
!
'.7. G. Keppler-3-February 2, 1973 7.
Reactor Coolant Pump Oil Fire
,
Letter report received from DP * on January 30, 1973. Evaluation to be complete February 5, 1973. We do not anticipate any problems with the report.
.DPC has advised the Regulatory Operations inspector that they will be ready to load fuel on February 6, 1973.
Installation of the core flood restrictors is currently the critical path item.
/
W
- "
C. E. Murphy, Acting Chief Facilities Test and Startup.