Ack Receipt of 850117 & s Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-267/85-31
ML20198C963
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 05/16/1986
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Walker R
PUBLIC SERVICE CO. OF COLORADO
References
NUDOCS 8605230100
Download: ML20198C963 (2)


Text

January 17, 1985

SUBJECT:

I&E Inspection Report 85-31 REFERENCE: NRC Letter, Gagliardo to Lee, dated 12/18/85 (G-85500)

Dear Mr. Hunter:

November 22, 1985

SUBJECT:

Emergency Diesel Generators REFERENCES:

1) NRC letter dated 2/24/86, Gagliardo to Lee (G-86099)

2) PSC letter dated 1/17/86, Gahm to Hunter (P-86046)

Dear Mr. Berkow:

This letter is in response to the NRC concerns discussed in Reference 1, regarding the startup check list for automatic operation of the Emergency Diesel Generatc.s, System Operating Procedure (SOP) 92-04, Section 2.2.

As previously noted in Reference 2, 50P 92-04 Section 2.2 has been revised to ensure that the valves associated with Emergency Diesel Generator service water, engine lube oil drains, and engine water jacket heaters are aligned correctly for automatic Emergency Diesel Generator operation.

In addition, PSC has initiated General Services Action Request (GSAR) - 1105, to assign valve numbers to all valves in the Emergency Diesel Generator Rooms.

This will include valves in the instrument air lines, which operate the service water temperature control val ves, engine lube oil drain valves and drain plugs, and engine water jacket heater valves.

PSC has implemented Procedure

,

l Deviation Report (PDR)86-290 which revises 50P 92-04 to require a I

i dccumented valve line-up check and independent verification, for the

- OJ.,O '.C ' ^^ *O - 860331 1 0 PDR ADOCK 05000267 l

(

P PDR

.

P-86228-2-March 31, 1986

.

f's.

.

.

Emergency Diesel Generator. auxiliary systems.

The valve line-up

,

,

check list refers to the. instrument air valves for the service water temperature control valves, engine lube oil drain valves and drain plugs, and engine water jacket heater valves by nomenclature.

When valve numbers have been assigned to these valves, the valve line-up check list will be revised to refer to the valve numbers.

These administrative changes will ensure that the valve line-ups for the Emergency Diesel Generator auxiliary systems are correct, to support automatic operation of the Energency Diesel Generators, and that the valve line-up check and independent verification are documented.

If ou have any further questions, please contact M. H. Holmes at (303 480-6960.

Very truly yours, W< h H. L. Brey, Manager Nuclear Licensing and Fuels HLB /BRD:bt