|
---|
Category:Inspection Report
MONTHYEARIR 05000254/20230042024-02-0505 February 2024 Integrated Inspection Report 05000254/2023004 and 05000265/2023004 IR 05000254/20234032023-12-22022 December 2023 Public- Quad Cities Nuclear Power Station Security Baseline Inspection Report 05000254/2023403 and 05000265/2023403 IR 05000254/20230102023-12-20020 December 2023 Comprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20230032023-11-0909 November 2023 Integrated Inspection Report 05000254/2023003 and 05000265/2023003 IR 05000254/20230112023-09-20020 September 2023 Safety-Conscious Work Environment Issue of Concern Team Inspection Report 05000254/2023011 and 05000265/2023011 IR 05000254/20230022023-08-0808 August 2023 Integrated Inspection Report 05000254/2023002 and 05000265/2023002 IR 05000254/20234012023-06-26026 June 2023 Cyber Security Inspection Report 05000254/2023401 and 05000265/2023401 IR 05000265/20230402023-06-22022 June 2023 Reissue Quad Cities Nuclear Power Station 95001 Supplemental Inspection Supplemental Report 05000265/2023040 and Follow Up Assessment Letter ML23167B1722023-06-16016 June 2023 95001 Supplemental Inspection Report 05000265/2023040 and Follow-Up Assessment Letter IR 05000254/20234022023-05-15015 May 2023 Security Baseline and ISFSI Inspection Reports 05000254/2023402, 05000265/2023402, 07200053/2023401 IR 05000254/20230012023-05-0808 May 2023 Integrated Report 05000254/2023001 and 05000265/2023001 ML23065A2832023-03-0707 March 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20233012023-03-0707 March 2023 NRC Initial License Examination Report 05000254/2023301; 05000265/2023301 IR 05000254/20220062023-03-0101 March 2023 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2022006 and 05000265/2022006) IR 05000254/20220042023-02-10010 February 2023 Integrated Inspection Report 05000254/2022004 and 05000265/2022004 IR 05000254/20220112023-01-0606 January 2023 Triennial Fire Protection Inspection Report 05000254/2022011 and 05000265/2022011 IR 05000254/20220102022-12-13013 December 2022 Phase 4 Post-Approval License Renewal Inspection Report 05000254/2022010 and 05000265/2022010 ML22313A1502022-11-29029 November 2022 EA-22-062 QC ERV Final Action IR 05000254/20224012022-11-22022 November 2022 Security Baseline Inspection Report 05000254/2022401 and 05000265/2022401 IR 05000254/20220132022-11-17017 November 2022 Biennial Problem Identification and Resolution Inspection Report 05000254/2022013 and 05000265/2022013 IR 05000254/20220032022-11-0303 November 2022 Integrated Inspection Report 05000254/2022003 and 05000265/2022003 IR 05000254/20220052022-08-22022 August 2022 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2022005; 05000265/2022005) IR 05000254/20225012022-08-15015 August 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2022501 and 05000265/2022501 IR 05000254/20220022022-08-0909 August 2022 Integrated Inspection Report 05000254/2022002 and 05000265/2022002 IR 05000254/20220902022-08-0808 August 2022 NRC Inspection Report 05000254/2022090 and 05000265/2022090; Preliminary White Finding IR 05000254/20220122022-07-11011 July 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000254/2022012 and 05000265/2022012 IR 05000254/20220012022-05-11011 May 2022 Integrated Inspection Report 05000254/2022001 and 05000265/2022001 IR 05000254/20210062022-03-0202 March 2022 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2021006 and 05000265/2021006) ML22033A1672022-02-0202 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000265/2022001 IR 05000254/20210042022-02-0202 February 2022 Integrated Inspection Report 05000254/2021004 and 05000265/2021004 IR 05000254/20214022021-12-0101 December 2021 Security Baseline Inspection Report 05000254/2021402 and 05000265/2021402 IR 05000254/20210102021-11-24024 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000254/2021010 and 05000265/2021010 IR 05000254/20210032021-10-28028 October 2021 Integrated Inspection Report 05000254/2021003 and 05000265/2021003 IR 05000254/20214012021-09-0909 September 2021 Security Baseline Inspection Report 05000254/2021401 and 05000265/2021401 IR 05000254/20210052021-09-0101 September 2021 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2021005 and 05000265/2021005) ML21238A3142021-08-26026 August 2021 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000254/2021004; 05000265/2021004 IR 05000254/20213012021-08-23023 August 2021 NRC Initial License Examination Report 05000254/2021301; 05000265/2021301 IR 05000254/20210022021-08-0909 August 2021 Integrated Inspection Report 05000254/2021002 and 05000265/2021002 IR 05000254/20214032021-06-28028 June 2021 Quad Nuclear Power Station - Material Control and Accounting Program Inspection Report 05000254/2021403 and 05000265/2021403 IR 05000254/20210012021-04-26026 April 2021 Integrated Inspection Report 05000254/2021001 and 05000265/2021001 IR 05000254/20200062021-03-0404 March 2021 Annual Assessment Letter for Quad Cities Nuclear Power Station Units 1 and 2 (Report 05000254/2020006 and 05000265/2020006) IR 05000254/20200042021-02-0404 February 2021 Integrated Inspection Report 05000254/2020004 and 05000265/2020004 IR 05000254/20204022021-01-11011 January 2021 Security Baseline Inspection Report 05000254/2020402 and 05000265/2020402 IR 05000254/20200102020-11-24024 November 2020 Biennial Problem Identification and Resolution Inspection Reportt 05000254/2020010 and 05000265/2020010 IR 05000254/20200112020-11-0909 November 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000254/2020011 and 05000265/2020011 IR 05000254/20200032020-11-0909 November 2020 Integrated Inspection Report 05000254/2020003; 05000265/2020003 and 07200053/2020001 IR 05000254/20205012020-09-0808 September 2020 Emergency Preparedness Inspection Report 05000254/2020501 and 05000265/2020501 IR 05000254/20200052020-09-0101 September 2020 Updated Inspection Plan for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2020005 and 05000265/2020005) IR 05000254/20200022020-08-11011 August 2020 Integrated Inspection Report 05000254/2020002 and 05000265/2020002 IR 05000254/20200012020-05-11011 May 2020 Integrated Inspection Report 05000254/2020001 and 05000265/2020001 2024-02-05
[Table view] Category:Letter
MONTHYEARIR 05000254/20230042024-02-0505 February 2024 Integrated Inspection Report 05000254/2023004 and 05000265/2023004 ML24004A0052024-01-17017 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0042 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2024-01-0303 January 2024 Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval IR 05000254/20234032023-12-22022 December 2023 Public- Quad Cities Nuclear Power Station Security Baseline Inspection Report 05000254/2023403 and 05000265/2023403 IR 05000254/20230102023-12-20020 December 2023 Comprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010 ML23349A1622023-12-17017 December 2023 Issuance of Amendment Nos. 298 and 294 Increase Completion Time in Technical Specification 3.8.1.B.4 (Emergency Circumstances) RS-23-128, Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-15015 December 2023 Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 RS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days ML23339A1762023-12-0505 December 2023 Notification of NRC Baseline Inspection and Request for Information (05000265/2024001) ML23319A3342023-11-20020 November 2023 Regulatory Audit in Support of License Amendment Requests to Adopt TSTF 505, Revision 2 and 10 CFR 50.69 RS-23-104, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000254/20230032023-11-0909 November 2023 Integrated Inspection Report 05000254/2023003 and 05000265/2023003 RS-23-113, Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 262023-10-20020 October 2023 Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 26 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23206A0382023-09-21021 September 2023 Proposed Alternative to the Requirements of the ASME Code IR 05000254/20230112023-09-20020 September 2023 Safety-Conscious Work Environment Issue of Concern Team Inspection Report 05000254/2023011 and 05000265/2023011 RS-23-089, Sixth Ten-Year Interval Inservice Testing Program2023-09-0505 September 2023 Sixth Ten-Year Interval Inservice Testing Program RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-086, Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-08-28028 August 2023 Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval SVP-23-038, Owner'S Activity Report Submittal Fifth 10-Year Interval 2023 Refueling Outage Activities2023-08-14014 August 2023 Owner'S Activity Report Submittal Fifth 10-Year Interval 2023 Refueling Outage Activities IR 05000254/20230022023-08-0808 August 2023 Integrated Inspection Report 05000254/2023002 and 05000265/2023002 ML23178A0742023-08-0707 August 2023 Issuance of Amendment Nos. 296 and 292 Adoption of TSTF-416 Low Pressure Coolant Injection (LPCI) Valve Alignment Verification Note Location ML23216A0362023-08-0707 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI ML23216A0562023-08-0404 August 2023 Information Meeting (Open House) with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2 SVP-23-031, Regulatory Commitment Change Summary Report2023-07-14014 July 2023 Regulatory Commitment Change Summary Report ML23181A1062023-06-30030 June 2023 Postponement- Information Meeting (Open House) with a Question-And-Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23179A1932023-06-28028 June 2023 07122023 Letter-Significant Public Meeting to Discuss NRC End-of-Cycle Performance Assessment of Quad Cities Nuclear Plant for Performance for 2022 Calendar Year IR 05000254/20234012023-06-26026 June 2023 Cyber Security Inspection Report 05000254/2023401 and 05000265/2023401 IR 05000265/20230402023-06-22022 June 2023 Reissue Quad Cities Nuclear Power Station 95001 Supplemental Inspection Supplemental Report 05000265/2023040 and Follow Up Assessment Letter RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23167B1722023-06-16016 June 2023 95001 Supplemental Inspection Report 05000265/2023040 and Follow-Up Assessment Letter RS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2023-06-0808 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors RS-23-059, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0808 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23144A3632023-05-26026 May 2023 Information Meeting (Open House) with a Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23033A4042023-05-15015 May 2023 Exemption from the Requirements of 10 CFR Part 2, Section 2.109(B) Related to Submission of Subsequent License Renewal Application Letter IR 05000254/20234022023-05-15015 May 2023 Security Baseline and ISFSI Inspection Reports 05000254/2023402, 05000265/2023402, 07200053/2023401 ML23132A2022023-05-12012 May 2023 Annual Radiological Environmental Operating Report ML23125A0612023-05-0808 May 2023 Proposed Alternative to the Requirements of the ASME Code IR 05000254/20230012023-05-0808 May 2023 Integrated Report 05000254/2023001 and 05000265/2023001 RS-22-067, 10 CFR 50.46 Annual Report2023-05-0404 May 2023 10 CFR 50.46 Annual Report ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 RS-23-068, Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell2023-04-28028 April 2023 Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell SVP-23-018, Radioactive Effluent Release Report for 20222023-04-28028 April 2023 Radioactive Effluent Release Report for 2022 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23110A0622023-04-25025 April 2023 Transmittal of Final Quad Cities Nuclear Power Plant, Unit 1 Accident Sequence Precursor Report (Licensee Event Report 254-2022-001) ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration 2024-02-05
[Table view] |
Text
ber 12, 2008
SUBJECT:
QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION 05000254/2008-008; 05000265/2008-008
Dear Mr. Pardee:
On August 8, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed a routine biennial PI&R inspection at your Quad Cities Nuclear Power Station, Units 1 and 2. The enclosed report documents the inspection findings, which were discussed on August 8 with Mr. Tulon and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings of significance were identified. The team concluded that problems were properly identified, evaluated, and resolved within the corrective action program (CAP). Assessments, the use of operating experience, and monitoring of the safety conscious work environment were also adequate. There were some minor issues identified with CAP implementation such that continued attention to the program is appropriate.
Corrective actions for certain adverse trends were not initially effective. Therefore, your staff should be attentive to the significance and difficulty certain issues represent so that the corrective actions are more appropriately aggressive.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Mark A. Ring, Chief Branch 1 Division of Reactor Projects Docket Nos. 50-254; 50-265 License Nos. DPR-29; DPR-30 Enclosure: Inspection Report 05000254/2008-008; 05000265/2008-008 w/Attachment: Supplemental Information cc w/encl: Site Vice President - Quad Cities Nuclear Power Station Plant Manager - Quad Cities Nuclear Power Station Regulatory Assurance Manager -
Quad Cities Nuclear Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Vice President - Law and Regulatory Affairs D. Tubbs, Manager of Nuclear Associate General Counsel Document Control Desk - Licensing Assistant Attorney General J. Klinger, State Liaison Officer, Illinois Emergency Management Agency M. Rasmusson, State Liaison Officer, State of Iowa Chairman, Illinois Commerce Commission Chief Radiological Emergency Preparedness Section, Dept. Of Homeland Security
SUMMARY OF FINDINGS
IR 05000254/2008-008; 05000265/2008-008; 07/21/2008 - 08/08/2008; Quad Cities Nuclear
Power Station, Units 1 & 2; routine biennial problem identification and resolution inspection (PI&R).
This inspection was performed by three regional inspectors and the Quad Cities Senior Resident Inspector. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.
Problem Identification and Resolution On the basis of the sample selected for review, the team concluded that implementation of the CAP was generally good. The licensee had a low threshold for identifying problems and entering them in the CAP. Items entered into the CAP were screened and prioritized in a timely manner using established criteria; were properly evaluated commensurate with their safety significance; and corrective actions were generally implemented in a timely manner, commensurate with the safety significance. The team noted that the licensee reviewed operating experience for applicability to station activities. Audits and self-assessments were determined to be performed at an appropriate level to identify deficiencies. On the basis of licensee self-assessments and interviews conducted during the inspection, workers at the site expressed freedom to raise safety concerns. The team observed that some significant adverse trends in human performance and equipment clearances and tagging were not initially identified and aggressively addressed for effective results. Subsequent efforts were more effective.
NRC-Identified
and Self-Revealed Findings No violations of significance were identified.
Licensee-Identified Violations
None.
REPORT DETAILS
OTHER ACTIVITIES
4OA2 Problem Identification and Resolution
Completion of sections
.1 through .4 constitutes one biennial sample of problem
identification and resolution as defined in Inspection Procedure 71152.
.1 Assessment of the CAP Effectiveness
a. Inspection Scope
The inspectors reviewed the licensees Corrective Action (CA) program implementing procedures and attended CA program meetings to assess the implementation of the CA program by site personnel.
The inspectors reviewed risk and safety significant issues in the licensees CA program since the last NRC Problem Identification and Resolution (PI&R) inspection in December 2006. The selection of issues ensured an adequate review of issues across NRC cornerstones. The inspectors used issues identified through NRC generic communications, department self-assessment, licensee audits, operating experience reports, and NRC documented findings as sources to select issues. Additionally, the inspectors reviewed issue reports generated as a result of facility personnels performance in daily plant activities. In addition, the inspectors reviewed Issue Reports (IRs) and a selection of completed investigations from the licensees various investigation methods, which included root cause, apparent cause, equipment apparent cause, and common cause investigations.
A five year review of the residual heat removal service water system was undertaken to assess the licensee staffs efforts in monitoring for system degradation due to aging aspects. The inspectors also performed partial system walkdowns of emergency AC and DC electrical systems.
During the reviews, the inspectors determined whether the licensee staffs actions were in compliance with the facilitys corrective action program and 10 CFR Part 50, Appendix B requirements. Specifically, the inspectors determined if licensee personnel were identifying plant issues at the proper threshold, entering the plant issues into the stations CA program in a timely manner, and assigning the appropriate prioritization for resolution of the issues. The inspectors also determined whether the licensee staff assigned the appropriate investigation method to ensure the proper determination of root, apparent, and contributing causes. The inspectors also evaluated the timeliness and effectiveness of corrective actions for selected issue reports, completed investigations, and NRC findings, including non-cited violations.
b. Assessment
- (1) Effectiveness of Problem Identification Overall, based on the number of IRs generated by all the plant departments, plant procedures that established a low threshold for reporting, and the types of issues in the program, the team concluded that the licensee was adequately identifying issues in the CAP. However, there were some minor issues not documented and several significant trends that were not identified in the program. Degradation of a safe shutdown makeup pump, a diesel fire pump oil leak leading to smoking insulation, and the adverse trend leading to a substantive cross-cutting issue by the NRC were issues not identified appropriately. In addition, during the inspection, the team identified that the failure of an emergency preparedness (EP) siren was not documented in the site CAP. This occurred because corporate EP staff handles siren repairs, but it prevented site staff, particularly operations staff, from being aware of a site equipment deficiency. The issue was minor in this case and an IR was initiated identifying the problem of coordination between organizations.
Findings No findings of significance were identified.
- (2) Effectiveness of Prioritization and Evaluation of Issues The team concluded that issue resolutions, established and monitored through the ownership review committee and the management review committee, were correctly assigned significance and priority in accordance with station procedures. While evaluations were generally adequate, there were three non-cited violations identified over the two year inspection period where evaluations were lacking in knowledge or thoroughness. A leak in the standby liquid control tank was not correctly evaluated for design code requirements, a risk evaluation improperly took credit for manual operation of the reactor core isolation cooling system, and pump breaker failures were inadequately evaluated. These issues were addressed through the CAP when they were identified.
Findings No findings of significance were identified.
- (3) Effectiveness of Corrective Actions Although corrective actions reviewed by the team were effective in most cases, several examples where results were less than desirable were also observed. For example, the quality of containment closeout inspections was a repeat issue identified by the resident inspectors. A packing leak from an RHRSW valve onto an RHR pump motor was inadequately addressed, and resulted in wetting the motor twice. The licensees response to two significant trends was also lacking. The NRC identified an adverse trend in human performance and an adverse trend in clearance and tagging of equipment were not recognized by the licensee early on and, in both cases, the licensees response was not aggressive enough to be effective. At the time of the inspection, corrective actions were showing positive results.
Findings No findings of significance were identified.
.2 Assessment of the Use of Operating Experience (OE)
a. Inspection Scope
The inspectors reviewed the implementation of the OE program. Specifically, the inspectors reviewed implementing operating experience program procedures, attended CA program meetings to observe the use of OE information, completed evaluations of OE issues and events, and selected monthly assessments of the OE composite performance indicators. The inspectors review was to determine whether the licensee was effectively integrating OE experience into the performance of daily activities, whether evaluations of issues were proper and conducted by qualified personnel, whether the licensees program was sufficient to prevent future occurrences of previous industry events, and whether the licensee effectively used the information in developing departmental assessments and facility audits. The inspectors also assessed if corrective actions, as a result of OE experience, were identified and effectively and timely implemented.
b. Assessment The team observed that the licensee was effectively receiving and processing operating experience reports from all sources. Operating experience was being incorporated into pre-job briefings and an initiative was underway to update and improve the way operating experience was put into work packages.
Findings No findings of significance were identified.
.3 Assessment of Self-Assessments and Audits
a. Inspection Scope
The inspectors assessed the licensee staffs ability to identify and enter issues into the CA program, prioritize and evaluate issues, and implement effective corrective actions, through efforts from departmental assessments and audits.
b. Assessment The programs for self-assessments and audits were scheduled and included a broad cross section of performance areas. Procedures for performing assessments were in place and implemented providing guidance and consistency. For the audits and assessments reviewed, observations were documented and for deficiencies that were identified, issue reports were written and corrective actions taken to address them.
Overall, self-assessment was adequately performed.
Findings No findings of significance were identified.
.4 Assessment of Safety Conscious Work Environment
a. Inspection Scope
The inspectors assessed the licensees safety conscious work environment through reviews of the facilitys employee concerns program (ECP) implementing procedures, discussions with coordinators of the employee concern program, interviews with personnel from various departments, and reviews of issue reports. The inspectors also reviewed the results from a Safety Culture Survey performed in 2007.
b. Assessment The licensee had developed an anonymous survey for plant staff. Results for 2007 indicated no significant areas of weakness in a safety conscious work environment.
Inspectors noted that the survey was returned by only approximately 45 percent of the staff and did not include contractors with a long term site presence or contract security staff. Interviews by the team and the team review of the ECP program also concluded that the licensee staff was willing to raise safety concerns. The licensee has added management tools for monitoring the worker attitudes with procedures for allegations and an Employees Issues Advisory Committee.
c. Findings
No findings of significance were identified.
4OA6 Management Meetings
Exit Meeting Summary
On August 8, 2008, the inspectors presented the inspection results to Mr. Tulon, and other members of the licensee staff. The licensee acknowledged the issues presented.
The inspectors confirmed that none of the potential report input discussed was considered proprietary.
ATTACHMENT:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee
Alguire, C. Engineering
Beck, W. Regulatory Affairs Manager
Cain, T. Nuclear Oversight
Colgan, J. Chemistry
Craddic, D. Maintenance Director
Darin, S. Engineering
Kronich, C. Operations/SOS
Morris, J. Corrective Action Program Manager
Peterson, T. Regulatory Assurance
Rice, M. Engineering
Scott, T. Online Work Control Manager
Tulon, T. Site Vice President
Wagner, M. Regulatory Assurance
Williams, A Radiation Protection
Illinois Emergency Management Agency (IEMA)
C. Mathews
Nuclear Regulatory Commission
B. Cushman Reactor Engineer
LIST OF ITEMS
OPENED, CLOSED AND DISCUSSED
None Attachment
LIST OF DOCUMENTS REVIEWED