IR 05000254/1983014

From kanterella
Jump to navigation Jump to search
Corrected Page 1 to IE Insp Repts 50-254/83-14 & 50-265/83-12 on 830419-20.No Noncompliance Noted.Major Areas Inspected:Licensee Action Re IE Bulletin 80-11, Masonry Wall Design
ML20023E087
Person / Time
Site: Quad Cities  
Issue date: 06/02/1983
From: Norton J, Williams C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20023E074 List:
References
50-254-83-14, 50-265-83-12, IEB-80-11, NUDOCS 8306070190
Download: ML20023E087 (1)


Text

{{#Wiki_filter:. . U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-254/83-14(DE); 50-265/83-12(DE) Docket No. 50-254; 50-265 License No. DPR-29; DPR-30 Licensee: Commonwealth Edison Company P.O. Box 767 Chicago, IL 60690 Facility Name: Quad Cities Nuclear Power Station, Units 1 & 2 Inspection At: Cordova, IL Inspection Corducted: April 19 and 20, 1983 [WMb M //'A/[[ Inspector: J. T. Norton ' / ' "

. Approved By: . C. Williams, Chief D Plant Systems Section Inspection Summary Inspection on April 19 and 20, 1983 (Report No. 50-254 /83-14 (DE) ; 50-265/83-12(DE)) Areas Inspected: Licensee action relative to Bulletin 80-11 " Masonry Wall Design". The inspection involved a total of 11 inspector-hours onsite by one NRC inspector.

Results: No items of noncompliance or deviations were identified.