IR 05000250/2018010
| ML18075A310 | |
| Person / Time | |
|---|---|
| Site: | Turkey Point |
| Issue date: | 03/15/2018 |
| From: | Marvin Sykes NRC/RGN-II |
| To: | Nazar M Florida Power & Light Co |
| References | |
| IR 2018010 | |
| Download: ML18075A310 (6) | |
Text
March 15, 2018
SUBJECT:
TURKEY POINT NUCLEAR GENERATING STATION - NRC EVALUATION OF CHANGES, TESTS, AND EXPERIMENTS REPORT NUMBER 05000250/2018010 AND 05000251/2018010
Dear Mr. Nazar:
On February 5, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Turkey Point Nuclear Generating Station Units 3 and 4, and the NRC inspectors discussed the results of this inspection with Robert Coffey and other members of your staff.
The results of this inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Marvin D. Sykes, Chief Engineering Branch 1 Division of Reactor Safety
Docket Nos. 50-250, 50-251 License Nos. DPR-31 and DPR-41
Enclosure:
Inspection Report 05000250/2017007 and 05000251/2017007
Inspection Report
Docket Numbers:
050000250, 05000251
License Numbers:
Report Numbers:
05000250/2018010, 05000251/2018010
Enterprise Identifier: I-2018-010-0024
Licensee:
Florida Power and Light
Facility:
Turkey Point Nuclear Generating Station, Units 3 and 4
Location:
9760 S. W. 344th Street
Homestead, FL 33035
Inspection Dates:
February 5-9, 2018
Inspectors:
Robert Patterson, Reactor Inspector (Team Lead)
Teh-Chiun Su, Reactor Inspector
Nadiyah Morgan, Reactor Inspector
Approved By:
M. Sykes, Chief
Engineering Branch 1
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Florida Power and
Lights performance by conducting a 10 CFR 50.59 inspection at Turkey Point Nuclear Generating Station Units 3 and 4, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
No findings or more than minor violations were identified.
INSPECTION SCOPE
Inspections were conducted using the appropriate portions of the inspection procedure (IP) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, conducted walkdowns and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.17T - Evaluations of Changes, Tests and Experiments
The inspectors evaluated the following samples for compliance with Title 10, Code of Federal Regulations (CFR) 50.59, Changes, tests, and experiments, from February 5, 2018, to February 9, 2018:
10 CFR 50.59 Evaluations - 71111.17T
1. 283382, Over Temperature and Over Power Rescaling
2. 281319, U3 Pressurizer Heater #11 Element Nozzle/Sleeve Repair
3. 282912, Turkey Point Unit 3 Cycle 28 Reload Design
4. 280401, U4 - RCP Seals Upgrade Project 003
5. 246870, Extended Power Uprate - Feedwater Regulating Valve Upgrade
6. 247017, U4 Replacement Of Beta Annunciator System
10 CFR 50.59 Screening/Applicability Determinations - 71111.17T
7. 0000241735, PCM-02045 Abandonment of Post-Accident Containment Ventilation and
Hydrogen Recombiner Equipment
8. 0000242126, PCM-05063 AFW Pump 'B' Lube Oil Check Valve Replacement
9. 0000274860, Change Position of ICW/CCW Heat Exchanger Outlet Isolation Valves
10. 0000278231, New Support Installation on 1" Line FOR RV-3/4-747A/B WO 40197156-05 11. 0000283348, PTN Unit 3 - Reroute 3A RCP Control Cable Out of Fire Area H 12. 0000284156, Replace U3 Snubbers in U3CYC29 13. 0000242553, PCM-10035 Installation of U4 S/G Blowdown Isolation Valve Accumulators 14. 0000272691, U4 ICW/TPCW Header Isolation Valve Actuator Replacement 15. 0000278348, N-4-1403 and N-4-1405 Local Starter Replacements 16. 0000284188, 4P241A and 4P245A TOL Change 17. PCR 02112053, EDG Pressure Switch Calibration 18. PCR 02184758, EDG Governor Adjustment 19. PCR 02132361, CCW Flow Balance Procedure
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On February 9, 2018, the inspectors presented the inspection results to Mr. Robert Coffey, and other members of the licensee staff.
DOCUMENTS REVIEWED
Procedures
EN-AA-203-1201, 10 CFR Applicability and 10 CFR 50.59 Screening Reviews, Rev. 12
EN-AA-203-1202, 10 CFR 50.59 Evaluation, Rev. 1
0-OSP-040.19, Low Power Physics Testing, Rev. 5A
3-OSP-019.2, Intake Cooling Water System Flowpath Verification, Rev. 5
4-OSP-019.2, Intake Cooling Water System Flowpath Verification, Rev. 4
3-OSP-030.9, Component Cooling Water System Flow Balance, Rev. 6A
0-ADM-232, Time Critical Operator Action Program, Rev. 8
3-EOP-ES-1.4, EOP, Transfer to Hot Leg Recirculation, Rev. 4
3-ONOP-033.3, Accident Involving New or Spent Fuel, Rev. 7
4-ARP-097.DG, Diesel Generator Panel Annunciator Response Page 87, Dated 2/14/17
4-SMI-023.6, EDG Pressure Switch Calibration, Rev. 4
4-SMI-023.6, EDG Pressure Switch Calibration, Rev. 5
EN-AA-205-1104, Standard Design Process, Rev. 0
Drawings
5610-J-844, S/G A Steam/Feed-water Flow Match Protection, Rev. 5
5613-E-26, Feed-water and Condensate Feed-water Check Valve, Sheet 22A, Rev. 3
5613-M-3074, Feed-water System, Sheet 3, Rev. 35
5614-M-16A-14, EDG 4K4B Fuel System, Sheet 1B, Rev., 4
5610-000-DB-001, Selected Licensing Issues, Rev. 21
Calculations
2-9221002, TP-3 Pressurizer Heater Sleeve Penetration Modification One Cycle Justification,
Rev. 0
PTN-3FJF-15-154, Turkey Point Unit 3 Cycle 28 - Technical Specifications Review, Rev. 0
PTN-BFSM-02-015, AOV Program Steam Generator Blowdown Control Valve/Actuator
Capability, Rev. 1
PTN-3OHC-14-001, RCP A,B & C Seal Leak Off Pipe Stress Calculation, Rev. 9
CRs (Condition Reports)
2089524
243589
2040372
2053850
2132361
2104882
2112053
243596
239726
2191208
236913
215220
2184758
UFSAR Section 4.2.2, Components
UFSAR Section 4.2.13, References
UFSAR Sections 7.2, 7.3, 7.4, 7.5 and 7.8
Work Orders
40125939-01
35003848-13
35003848-07
40526739-01
40523051-01
40523050-01
40518623-01
Miscellaneous Documents
NRC Safety Evaluation for the Turkey Point Relief Request No. 1, Rev. 1
51-9220957, Corrosion Evaluation for Turkey Point Unit 3 Pressurizer Heater Sleeve
Penetration Modification, Rev. 0
NRC Safety Evaluation for the Turkey Point License Amendment Request regarding Optimized
ZIRLO Fuel Rod Cladding Material
NF-NEXT-15-189, Turkey Point Unit 3 Cycle 28 Safety Input Letter, Rev. 0
MSP 05-063, AFW Pump B Lube Oil - Foot Valve Replacement
NRC Safety Evaluation for the Turkey Point License Amendment Request regarding Snubbers
PC/M 10-035, Installation of U4 S/G Blowdown Isolation Valve Accumulators, Rev. 9
5614-M-313, Turkey Point Unit 4 Set Point List, Rev. 87
CD-01.11 Document Status Report, Dated 01/30/2018
CC-12808-1, CFC, Electric Motor Starter, Rev. 0
Feed-water Control Using Yokogawa YS1700 Single Loop Controller, Application Design
Description, Dated 4/22/14
PC/M 02-045, Abandonment of Post-Accident Containment Vent & Hydrogen Re-combiner, R 0
PC/M 02-045, Abandonment of Post-Accident Containment Ventilation and Hydrogen Re-
combiner Equipment 50.59 evaluation, Rev. 0
PCR 2112053, 4-SMI-023.6, EDG Pressure Switch Calibration, Rev. 0
SPEC-IC-079, U3 and 4 Annunciator Replacement Software Specifications, Rev. 1
YS1500 Indicating Controller, 3rd Edition
WCAP-15603-NP, WOG 2000 RCP Seal Leakage Model (Non-Proprietary), Rev. 1
Corrective Action Documents Written as a Result of the Inspection
AR 2248526, Type In ECs 278348 and 278664
AR 2248134, Unit 4 EDG Fuel Strainer DPS Alarm Set-point Change