Progress Energy July 25, 2012 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50-400/RENEWED LICENSE NO. NPF-63 SERIAL: HNP-12-083 NRC REGULATORY ISSUE
SUMMARY
2012-07, PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS Ladies and Gentlemen:
As requested by NRC Regulatory Issue Summary 2012-07, "Preparation and Scheduling of Operator Licensing Examinations," Carolina Power & Light Company is providing the enclosed completed NRC Form 536, "Operator Licensing Examination Data," for the Harris Nuclear Plant.
If you have any questions regarding the information provided, please contact Mr. Arthur Sylvester at (919) 362-3252.
DHC/mgw
Enclosure:
NRC Form 536 Sincerely, D. H. Corlett Supervisor - Licensing/Regulatory Programs Harris Nuclear Plant c:
Mr. J.D. Austin (NRC Senior Resident Inspector, HNP)
Ms. A. T. Billoch Colon (NRC Project Manager, HNP)
Mr. M. T. Widmann (NRC Chief, Operations Branch, Region II)
Progress Energy Carolinas, Inc.
Harris Nuclear Plant P 0 Box 165 New Hill, NC 27562
NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 09/30/2014 (9-2011)
Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
This information collection is used to plan budgets and resources for operator OPERA TOR LICENSING examinations. Send comments regarding burden estimate to the lnfonmation Services Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-EXAMINATION DATA mail to lnfocollects.Resource@nrc.gov, and to the Desk Officer, Office of lnfonmation and Regulatory Affairs, NEOB-10202, (3150-0131 ), Office of Management and Budget, Washington, DC 20503.
If a means used to impose an infonmation collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
FACILITY NRC REGION Harris Nuclear Plant II A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2014 CY201 5 CY2016 CY2017 ESTIMATED NUMBER OF LICENSEE-PREPARED 1
1 1
0 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0
0 0
0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2014 CY2015 CY2016 CY2017 NUMBER OF REACTOR 8
8 8
0 OPERATORS NUMBER OF SENIOR REACTOR 4
4 4
0 OPERATORS -INSTANT NUMBER OF SENIOR REACTOR 4
4 4
0 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0
0 0
0 OPERATORS-LIMITED PROPOSED DATES PRIMARY DATE 11/3/14 3/9/1 5 8/22/16 N/A ALTERNATE DATE 11/10/14 3/16/15 8/29/16 N/A
- c. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2014 CY 2015 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0
0 0
0 12 0
0 0
CANDIDATES NRC FORM 536 (9-2011)