HNP-02-033, Submittal of Revision 2 to the Physical Security and Safeguards Contingency Plan
| ML020990326 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 03/28/2002 |
| From: | Field R Carolina Power & Light Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| SERIAL:HNP-02-033 | |
| Download: ML020990326 (4) | |
Text
SCP&L A Progress Energy Company MAR 2 8 2002 SERIAL: HNP-02-033 10 CFR 50.54 (p)(2)
United States Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555 SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50-400/LICENSE NO. NPF-63 SUBMITTAL OF REVISION 2 TO THE PHYSICAL SECURITY AND SAFEGUARDS CONTINGENCY PLAN
Dear Sir or Madam:
In accordance with 10 CFR 50.54 (p)(2) and 10 CFR 50.4 (b)(4), Carolina Power & Light Company (CP&L) is providing Revision 2 of the Physical Security and Safeguards Contingency Plan for the Harris Nuclear Plant.
The enclosed revision does not decrease the safeguards effectiveness of the Physical Security and Safeguards Contingency Plan.
A summary description of the changes is provided in Enclosure 1. The changes to the Physical Security and Safeguards Contingency Plan include: revision of paragraphs 6.3.1 "Personnel Categories" and 6.3.2 "Badge Description".
A copy of the Physical Security and Safeguards Contingency Plan Revision 2 is provided in. contains safeguards information that requires protection in accordance with 10 CFR 73.21. Upon separation of Enclosure 2, this letter and Enclosure 1 are decontrolled.
Please refer any questions regarding this submittal to Mr. J. R. Caves at (919) 362-3137 or Mr. D. A. Braund at (919) 362-2065.
Sincerely, Manager, Regulatory Affairs Harris Nuclear Plant Harris Nuclear Plant 5413 Shearon Harris Road New Hill, NC 27562
Document Control Desk SERIAL: HNP-02-033 MGW/mgw
Enclosures:
- 1. Summary Description of Changes
- 2. Physical Security and Safeguards Contingency Plan, Revision 2 (SAFEGUARDS INFORMATION) c:
Mr. J. B. Brady, NRC Senior Resident Inspector, HNP (w/o Enclosure2)
Mr. J. M. Goshen, NRR Project Manager, HNP (w/o Enclosure 2)
Mr. L. A. Reyes, NRC Regional Administrator, Region 11 (2 copies of Enclosure 2)
Document Control Desk SERIAL: HNP-02-033 Summary Description of Changes 6.3.1 "Personnel Categories" 6.3.2 "Badge Description" Changed to read as follows:
- 1.
Authorized Licensee Employees - CP&L and other Progress Energy Employees who are afforded unescorted access.
- 2.
Authorized Non - Licensee Employees - Personnel who are afforded unescorted access, but are not employees of CP&L or Progress Energy (non-employee, no escort required).
- 3.
Escorted Personnel - Personnel (may be licensee or non licensee employees) requiring access usually of a short term nature and who are not on the authorized access list, but have been approved for access by authorized management personnel.
Changed paragraph to read as follows:
The picture on the unescorted access photo ID Security Badge is on a white background for authorized licensee employees and a blue background for authorized non-licensee employees. The photo ID security badge contains the name of the individual, a color photograph, a badge number, the company logo, a nuclear symbol, and "P" for Protected Area access only or a "V" for both Protected and Vital Area Access. A unified Corporate Access Authorization Program is administered by Progress Energy for employees of CP&L and Florida Power Corporation (FPC). The badge may also contain a magnetic stripe and a "T" to identify employees with access granted on a temporary clearance.
I 2
Document Control Desk "SERIAL: HNP-02-033 Physical Security and Safeguards Contingency Plan, Revision 2 (SAFEGUARDS INFORMATION ATTACHED)