ENS 57041
ENS Event | |
---|---|
10:48 Mar 13, 2024 | |
Title | |
Event Description | The following information was provided by the licensee via email and phone:
At 0548 CDT on March 13, 2024, during a planned [high pressure coolant injection] HPCI maintenance window, a condition was identified not associated with the planned maintenance which caused HPCI to be inoperable. Specifically, the HPCI auxiliary oil pump start stop pressure switch could not be adjusted into calibration. Further investigation found that the pressure switch was not mounted as designed. Since HPCI is a single train system, this is a condition that could have prevented the fulfillment of a safety function; therefore, this condition is being reported as an eight-hour, non-emergency notification per 10 CFR 50.72(b)(3)(v)(D). The condition was corrected prior to HPCI being declared operable on March 15, 2024. The reason for the delay in the event notification beyond 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> from the event time was due to not recognizing the need to report the condition while in a planned HPCI maintenance window. The NRC Senior Resident Inspector has been notified. |
Where | |
---|---|
Cooper Nebraska (NRC Region 4) | |
Reporting | |
10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | |
LER: | 05000298/LER-2024-005 High Pressure Coolant Injection Pressure Switch Installation Causes Condition That Could Have Prevented Fulfillment of a Safety Function and a Condition Prohibited B Technical |
Time - Person (Reporting Time:+198.1 h8.254 days <br />1.179 weeks <br />0.271 months <br />) | |
Opened: | Brian Stander 16:54 Mar 21, 2024 |
NRC Officer: | Ian Howard |
Last Updated: | Mar 21, 2024 |
57041 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 57041\u003C/a\u003E - \u003Ca href=\"/Cooper\" title=\"Cooper\"\u003ECooper\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EHigh Pressure Coolant Injection (HPCI) Inoperable\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 57041 - Cooper\n","link":"","lat":40.359658333333336,"lon":-95.65465277777778,"icon":"/w/images/7/79/Entergy_icon.png"}],"imageoverlays":null} | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Power Operation (100 %) |