ENS 55609
ENS Event | |
---|---|
18:58 Oct 17, 2021 | |
Title | 60 Day Optional Telephonic Notification for Invalid Specified Actuation of Containment Isolation Train |
Event Description | This 60-day telephone notification is provided in accordance with 10 CFR 50.73(a)(1) to report one invalid actuation of the Unit 1 Containment Isolation System Train "A" in accordance with 10 CFR 50.73(a)(2)(iv)(A).
On October 17, 2021 at approximately 1358 [EDT], a DC breaker was opened to perform an inspection of a Containment Isolation (CI) rack. A CI signal was produced and resulted in a loss of Letdown during filling and venting the Reactor Coolant System (RCS) with the RCS at 344 psig. RCS pressure began to rise, and prompt actions were taken by the Control Room to secure a Charging Pump within 20 seconds. The RCS pressure rise continued and both Pressure Operated Relief Valves cycled at 409.9 psig as designed, lowering RCS pressure. The CI Train "A" was not part of a pre-planned sequence and the event resulted in the invalid actuation of Train "A" Containment Isolation valves in more than one system. All valves functioned successfully. The DC breaker was closed, CI signal reset, and associated CI valves re-opened. All systems functioned as required and returned to normal service. The NRC Senior Resident Inspector has been notified. |
Where | |
---|---|
Ginna New York (NRC Region 1) | |
Reporting | |
10 CFR 50.73(a)(1), Submit an LER, Invalid Actuation | |
Time - Person (Reporting Time:+912.43 h38.018 days <br />5.431 weeks <br />1.25 months <br />) | |
Opened: | Wade Weber 20:24 Nov 24, 2021 |
NRC Officer: | Brian P. Smith |
Last Updated: | Nov 24, 2021 |
55609 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 55609\u003C/a\u003E - \u003Ca href=\"/Ginna\" title=\"Ginna\"\u003EGinna\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E60 Day Optional Telephonic Notification for Invalid Specified Actuation of Containment Isolation Train\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 55609 - Ginna\n","link":"","lat":43.277569444444445,"lon":-77.30936388888888,"icon":"/w/images/b/be/Constellation_icon.png"}],"imageoverlays":null} | |
Unit 1 | |
---|---|
Reactor critical | Not Critical |
Scram | No |
Before | Cold Shutdown (0 %) |
After | Power Operation (100 %) |
WEEKMONTHYEARENS 556092021-10-17T18:58:00017 October 2021 18:58:00
[Table view]10 CFR 50.73(a)(1), Submit an LER 60 Day Optional Telephonic Notification for Invalid Specified Actuation of Containment Isolation Train ENS 516042015-10-21T05:29:00021 October 2015 05:29:00 10 CFR 50.73(a)(1), Submit an LER Diesel Generator Start Due to Invalid Signal ENS 502312014-05-08T17:20:0008 May 2014 17:20:00 10 CFR 50.73(a)(1), Submit an LER 60-Day Telephonic Notification of Invalid Specified System Actuation ENS 470942011-06-03T04:39:0003 June 2011 04:39:00 10 CFR 50.73(a)(1), Submit an LER Invalid Actuation of Emergency Diesel Generator ENS 469662011-04-25T01:44:00025 April 2011 01:44:00 10 CFR 50.73(a)(1), Submit an LER 60 Day Optional Notification of Invalid Start of Emergency Diesel Generator. ENS 466242010-12-29T05:00:00029 December 2010 05:00:00 10 CFR 50.73(a)(1), Submit an LER Invalid System Actuation Due to Operator Error ENS 443202008-05-10T01:32:00010 May 2008 01:32:00 10 CFR 50.73(a)(1), Submit an LER Invalid Auxiliary Feedwater System Actuation ENS 403322003-10-08T07:16:0008 October 2003 07:16:00 10 CFR 50.73(a)(1), Submit an LER Invalid Safety Injection Signal During Surveillance Testing at Ginna ENS 403312003-09-27T20:44:00027 September 2003 20:44:00 10 CFR 50.73(a)(1), Submit an LER Invalid Partial Safety Injection Signal During Surveillance Testing at Ginna 2021-10-17T18:58:00 | |