ENS 54309
From kanterella
Jump to navigation
Jump to search
ENS Event | |
|---|---|
07:00 Mar 3, 2019 | |
| Title | Part 21 - Ge Hitachi Primary Contact Finger Surface Defect |
| Event Description | On March 3, 2019, during overhaul activities of the medium voltage power (Magne-blast) circuit breakers, three General Electric Hitachi (GEH) Stationary Primary Contact Fingers Q0114C5382P002 were identified as having contact surfaces with a finish that was rough and unlike the typically smooth finish provided on electrical contact surfaces. These Stationary Primary Contact Fingers are the primary current carrying device for the circuit breaker.
On October 1, 2019, Arizona Public Service Company (APS) completed an evaluation of a deviation, and concluded the condition represented a defect under 10 CFR 21. On October 4, 2019, the Palo Verde Nuclear Generating Station Vice President, Nuclear Engineering, was notified of a defect of GEH Stationary Primary Contact Fingers which met the reporting criteria of 10 CFR 21.21. There are no medium voltage power (Magne-blast) circuit breakers with stationary primary contact fingers impacted by this condition installed in the plant. APS concluded this condition, if installed, could result in the breaker failing to perform its safety function and thus could create a substantial safety hazard. The NRC resident inspector has been informed. |
| Where | |
|---|---|
| Palo Verde Arizona (NRC Region 4) | |
| Reporting | |
| 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect | |
| Time - Person (Reporting Time:+5169.75 h215.406 days <br />30.772 weeks <br />7.082 months <br />) | |
| Opened: | Lorraine Weaver 15:45 Oct 4, 2019 |
| NRC Officer: | Jeff Herrera |
| Last Updated: | Oct 4, 2019 |
| 54309 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 54309\u003C/a\u003E - \u003Ca href=\"/Palo_Verde\" title=\"Palo Verde\"\u003EPalo Verde\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EPart 21 - Ge Hitachi Primary Contact Finger Surface Defect\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 54309 - Palo Verde\n","link":"","lat":33.386894444444444,"lon":-112.86263333333333,"icon":"/w/images/9/93/Arizona_Public_Service_icon.png"}],"imageoverlays":null} | |
Unit 1 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (100 %) |
| After | Power Operation (100 %) |
Unit 2 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (100 %) |
| After | Power Operation (100 %) |
Unit 3 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (97 %) |
| After | Power Operation (97 %) |
WEEKMONTHYEARENS 546212020-03-19T07:00:00019 March 2020 07:00:00
[Table view]10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 Notification - Transducer Defect ENS 543092019-03-03T07:00:0003 March 2019 07:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Ge Hitachi Primary Contact Finger Surface Defect ENS 526702017-04-05T07:00:0005 April 2017 07:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Circuit Breaker Defect Discovered During Current Injection Testing 2020-03-19T07:00:00 | |