ENS 46723
From kanterella
Jump to navigation
Jump to search
ENS Event | |
|---|---|
20:00 Apr 4, 2011 | |
| Title | Scaffolding Affecting Safety Related Equipment |
| Event Description | At 1500 [CDT], a concern was raised with regard to scaffolding that had been constructed around safety related equipment in the Auxiliary Building which contains both trains of safety injection and containment spray. As a result T.S. 2.0.1 was entered (which is the Fort Calhoun equivalent to standard T.S. 3.0.3). The scaffolding in question was removed and the equipment was returned to operable status and T.S. 2.0.1 was exited at 1726 [CDT].
The NRC Resident Inspector has been notified.
Following the initial report, Fort Calhoun performed a seismic analysis of the impact of the scaffolding previously reported to determine if the equipment in the room would be capable of performing its required safety functions. The evaluation determined that the safety related function of the affected equipment would be able to be accomplished. Therefore, this event is being retracted. Notified R4DO (Haire). The licensee has notified the NRC Resident Inspector of this retraction. |
| Where | |
|---|---|
| Fort Calhoun Nebraska (NRC Region 4) | |
| Reporting | |
| 10 CFR 50.72(b)(3)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.72(b)(3)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | |
| Time - Person (Reporting Time:+-0.15 h-0.00625 days <br />-8.928571e-4 weeks <br />-2.0547e-4 months <br />) | |
| Opened: | Erick Matzke 19:51 Apr 4, 2011 |
| NRC Officer: | Dong Park |
| Last Updated: | May 27, 2011 |
| 46723 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 46723\u003C/a\u003E - \u003Ca href=\"/Fort_Calhoun\" title=\"Fort Calhoun\"\u003EFort Calhoun\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EScaffolding Affecting Safety Related Equipment\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 46723 - Fort Calhoun\n","link":"","lat":41.520963888888886,"lon":-96.07684444444445,"icon":"/w/images/6/6a/Omaha_Public_Power_District_icon.png"}],"imageoverlays":null} | |
Unit 1 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (100 %) |
| After | Power Operation (100 %) |
Retrieved from "https://kanterella.com/w/index.php?title=ENS_46723&oldid=87564"