Title | Interim Report on Thermostatic Valve Failure on Palo Verde Edg |
Event Description | This interim report is being issued because Engine Systems, Inc. (ESI) is not able to complete an evaluation of an identified deviation within the 60 day requirement of 10CFR21.21. The evaluation is expected to be completed no later than November 30, 2009.
ESI began an evaluation of a thermostatic valve element failure on August 24, 2009. Palo Verde Nuclear Plant notified ESI of the failure as a result of a failure analysis they were performing on a thermostatic valve that had been removed from the lube oil system of their 2A-EDG. The element was in service since April 2008 and Palo Verde verified operation of the element prior to installation. The Palo Verde failure analysis determined that one of two elements within the valve was defective. The element failure was attributed to wax leakage past the diaphragm seal on one of two power pills within the element. Evidence of mechanical binding of the piston is believed to have caused the wax leakage. If the piston was jammed, the expanding wax could have over pressurized the diaphragm seal leading to wax leakage. The failure analysis noted the following to support piston binding: - The piston was initially difficult to remove from its guide tube. - A gouge was observed on the piston surface. - The rubber plug within the power pill exhibited brass machining chip debris. ESI has been coordinating with Palo Verde and the manufacturer (AMOT) to complete our evaluation and to determine if this is a generic issue or if it is an isolated incident. To date, no other similar failures with AMOT thermostatic valves have been reported to ESI. Palo Verde has Cooper Bessemer KSV-20T diesel engines that use one 6" thermostatic valve in the engine jacket water system and one in the engine lube oil system to regulate system temperatures during engine operation. The thermostatic valve is an AMOT model 6HAS. The AMOT thermostatic valve element (P/N 9760X) is the defective part. ESI did not provide any information on other nuclear power plants that have EDGs that utilize this model thermostatic valve.
This report is a follow-up to an interim report (10CFR21-0098-INT) issued by Engine Systems, Inc. (ESI) on 10/23/09 which identified a deviation with an Amot thermostatic valve element. The interim report was issued because ESI was not able to complete the evaluation within the 60 day requirement of 10CFR21. The evaluation was completed on 11/30/09 and the deviation was determined be a reportable defect as by defined by 10CFR21. The Exelon analysis also reports that similar brass machining debris was observed on the plugs from the other three power pills to varying degrees. None of the stems of these pills displayed evidence of gouging or binding. To date, no other similar failures with Amot thermostatic valves have been reported to ESI. ESI has contacted the valve manufacturer (Amot) to discuss these findings. A copy of the Palo Verde failure analysis and eleven (11) element assemblies from ESI inventory were sent to Amot for evaluation. The following elements were sent to Amot for evaluation: Qty. 8: PIN 9760 X-170' (CES PIN 2-05V-419-107) Qty. 3: PIN 9760 X-160' (CES PIN 2-05V-419-109) Both part number elements are the same except for the temperature setting ('-170' indicates 170?F nominal and '-160' indicates 160?F nominal). Upon completion of their evaluation, Amot has reported the following: Fine shavings/powder of brass was observed in some of the element pills. None of the pill stems had any evidence of gouging. The pills used in the 9760X elements are made by converting another part number pill. This conversion consists of removing the stem from the pill and performing some machining. Amot believes the brass debris may have entered the pill as a result of this conversion process. Amot has not made any changes to this conversion process in recent history and has not had reports of similar problems with these elements. Machining debris, while undesirable, was evident in other pills which did not exhibit any operability issues; therefore this is not believed to be the cause of the pill failure. The primary cause of the failure is believed to be the gouge found in the pill stem. The gouge could have occurred during the conversion process as the stem is removed and handled at that time. As a precaution, Amot has made changes to their conversion process for this pill. The drilling fixture was modified to eliminate the possibility of chips entering the pill during the machining operation. This change was made effective 10/22/09. A listing of users with the thermostatic valves that contain the Amot 9760X element is provided in the table below. Site - Thermostatic Valve - System: Braidwood - 6HAS - Lube Byron - 6HAS - Lube Nine Mile Point - 6HAS- Lube Oconee - 4HAS & 6HAS - Water Palo Verde - 6HAS - Lube & Water South Texas Project - 6HAS - Lube & Water Susquehanna - 6HAS - Lube & Water Waterford - 5HAS & 6HAS - Lube & Water Corrective Action: The element failure at Palo Verde is considered to be an isolated incident related to a gouge in the pill stem. Thus, there is no recommended corrective action for users of the Amot 9760X element. The evaluation also indicated a weakness in Amot's manufacturing process for the element pill which introduced machining debris. While not believed to be the cause of the Palo Verde element failure, machining debris within the element pill is undesirable and increases the potential for failure in the future. Users with thermostatic valves containing Amot PIN 9760X elements should be aware of this issue so that they can monitor their systems for any indications of thermostat element problems. Notified R1DO (Holody), R2DO (Guthrie), R3DO (Riemer), R4DO (Deese), NRR (Thorp) via e-mail, NRO (Tabatabai) via email.
Two sentences were added to address the safety hazard which is created or could be created by this defect. This defect could affect operability of the thermostatic valve within the diesel engine cooling water and/or lube oil system, resulting in elevated fluid system temperatures during engine operation. Engine performance and/or load carrying capability could be impacted with the possibility of eventual engine failure, thereby preventing the emergency diesel generator from performing its safety related function. Notified R1DO (Powell), R2DO (Sykes), R3DO (Peterson), R4DO (Lantz), PART 21 GROUP via e-mail.
The report was updated to revise part numbers for Oconee, Waterford and Laguna Verde (Mexico). Affected users added include the following: Susquehanna 5th EDG and Ergytech/Iberdroia (Spain). Notified R1DO (Schmidt), R2DO (Desai), R3DO (Riemer), R4DO (Farnholtz) and PART 21 GROUP via e-mail. |
Where | |
---|---|
Engine Systems, Inc Rocky Mount, North Carolina (NRC Region 1) | |
Organization: | Engine Systems, Inc |
Reporting | |
10 CFR 21.21 | |
Time - Person (Reporting Time:+1452.53 h60.522 days <br />8.646 weeks <br />1.99 months <br />) | |
Opened: | Paul Stepantschenko 16:32 Oct 23, 2009 |
NRC Officer: | Bill Huffman |
Last Updated: | Dec 1, 2011 |
45459 - NRC Website | |
Engine Systems, Inc with 10 CFR 21.21, Notification of failure to comply or existence of a defect and its evaluation | |
WEEKMONTHYEARENS 476852012-02-17T05:00:00017 February 2012 05:00:00
[Table view]10 CFR 21.21, Notification of failure to comply or existence of a defect and its evaluation Missing Upper Mounting Pads on Subcover Assemblies ENS 476352011-12-01T05:00:0001 December 2011 05:00:00 10 CFR 21.21, Notification of failure to comply or existence of a defect and its evaluation ENS 467602011-04-15T04:00:00015 April 2011 04:00:00 10 CFR 21.21, Notification of failure to comply or existence of a defect and its evaluation Potential Defect in Magnetrol Level Switch from Engine Systems Incorporated ENS 454592009-08-24T04:00:00024 August 2009 04:00:00 10 CFR 21.21, Notification of failure to comply or existence of a defect and its evaluation Interim Report on Thermostatic Valve Failure on Palo Verde Edg ENS 453262009-08-17T04:00:00017 August 2009 04:00:00 10 CFR 21.21, Notification of failure to comply or existence of a defect and its evaluation Part 21 - Faulty Emergency Diesel Generator Start-Up Solenoid Valve ENS 453352009-08-14T04:00:00014 August 2009 04:00:00 10 CFR 21.21, Notification of failure to comply or existence of a defect and its evaluation Part 21 Involving Woodward Governors Using Unapproved Supplier Integrated Circuits 2012-02-17T05:00:00 | |