ENS 40480
From kanterella
Jump to navigation
Jump to search
ENS Event | |
|---|---|
22:00 Jan 25, 2004 | |
| Title | High Differential Pressure in Auxiliary Building |
| Event Description | On January 25, 2004, during troubleshooting of high differential pressure in the Unit 1 Auxiliary Building, the 1ABF13 fire damper was found closed at approximately 1700 (EST) hours. The 1ABF13 fire damper was re-opened and system flows and differential pressure were verified to be normal at approximately 1950 hours0.0226 days <br />0.542 hours <br />0.00322 weeks <br />7.41975e-4 months <br />.
On January 26, 2004, at 1500 hours0.0174 days <br />0.417 hours <br />0.00248 weeks <br />5.7075e-4 months <br />, a determination was made that with the 1ABF13 fire damper closed, filtration of the effluents from the pipe chase and RHR areas could not be processed through the HEPA-Charcoal absorber. This condition did not meet the assumptions of the Salem dose analysis and is being reported under the requirement of 10CFR50.72(b)(3)(v)(D). The licensee notified the NRC Resident Inspector. |
| Where | |
|---|---|
| Salem New Jersey (NRC Region 1) | |
| Reporting | |
| 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | |
| LER: | 05000272/LER-2003-005 Regarding Condition Prohibited by Technical Specifications: Auxiliary Building Ventilation System Fire Damper Found Out of Position |
| Time - Person (Reporting Time:+19.18 h0.799 days <br />0.114 weeks <br />0.0263 months <br />) | |
| Opened: | Joseph Shisler 17:11 Jan 26, 2004 |
| NRC Officer: | Bill Gott |
| Last Updated: | Jan 26, 2004 |
| 40480 - NRC Website
Loading map... | |
Unit 1 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (100 %) |
| After | Power Operation (100 %) |