Text
L*Rafael Flores Lumi~nant Power Senior Vice President P0O Box 1002 Chief Nuclear Officer 6322 North FM 56 RafaeIFlores@Luminant.com Glen Rose, TX 76043 Lum i antF 254 89756652 CP-201501126 TXX-15 164 December 14, 2015 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT DOCKET NOS. 50-445 AND 446 LICENSE RENEWAL APPLICATION SUBMITTAL SCHEDULE REVISION
REFERENCES:
- 1. Letter logged STARS-13010 dated December 2, 2013, from Karl A. (Tony) Harris to the NRC submitting STARS Alliance License Renewal Application Submittal Schedule Revision (Ascension No. ML14167A301)
- 2. NRC Regulatory Issue Summary 2009-006 Importance of Giving NRC Advance Notice of Intent to Pursue License Renewal
Dear Sir or Madam:
Per Reference 1, STARS provided the revised submittal schedule for license renewal application for STARS Alliance member stations. Luminant Generation Company, LLC (Luminant Power) was referred to in Reference 1 as STARS Station 6. Luminant Power with the Comanche Peak Nuclear Power Plant (CPNPP) is no longer a member of the STARS Alliance. Reference 2 requested that licensees provide a written, voluntary submission of licensee's plans regarding license renewal. The purpose of this letter is to formally notify the NRC of the change to the submittal schedule for CPNPP.
STARS Station 6 is shown on the NRC License Renewal website to be submitting an application between July and September 2018. As stated above, CPNPP was STARS Station 6 however Luminant Power is no longer part of the STARS Alliance. The revised license renewal application submittal date for CPNPP is now scheduled for the second quarter of 2022.
This communication contains no new licensing basis commitments regarding Comanche Peak Unit 1 and Unit 2.
"'I U. S. Nuclear Regulatory Commission
~TXX-15 164 Page 2 of 2 12/14/2015 Should you have any questions, please contact Mr. Jack Hicks at (254) 897-6725.
Sincerely, Luminant Generation Company LLC Rafael Elores By:
Thoma
. McCool Vice President, Engineering and Support c -
Marc L. Dapas, Region IV Balwant K. Singal, NRR Christopher G. Miller, Director, Division of License Renewal Resident Inspectors, Comanche Peak Steve Coppock, STARS Alliance
L*Rafael Flores Lumi~nant Power Senior Vice President P0O Box 1002 Chief Nuclear Officer 6322 North FM 56 RafaeIFlores@Luminant.com Glen Rose, TX 76043 Lum i antF 254 89756652 CP-201501126 TXX-15 164 December 14, 2015 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT DOCKET NOS. 50-445 AND 446 LICENSE RENEWAL APPLICATION SUBMITTAL SCHEDULE REVISION
REFERENCES:
- 1. Letter logged STARS-13010 dated December 2, 2013, from Karl A. (Tony) Harris to the NRC submitting STARS Alliance License Renewal Application Submittal Schedule Revision (Ascension No. ML14167A301)
- 2. NRC Regulatory Issue Summary 2009-006 Importance of Giving NRC Advance Notice of Intent to Pursue License Renewal
Dear Sir or Madam:
Per Reference 1, STARS provided the revised submittal schedule for license renewal application for STARS Alliance member stations. Luminant Generation Company, LLC (Luminant Power) was referred to in Reference 1 as STARS Station 6. Luminant Power with the Comanche Peak Nuclear Power Plant (CPNPP) is no longer a member of the STARS Alliance. Reference 2 requested that licensees provide a written, voluntary submission of licensee's plans regarding license renewal. The purpose of this letter is to formally notify the NRC of the change to the submittal schedule for CPNPP.
STARS Station 6 is shown on the NRC License Renewal website to be submitting an application between July and September 2018. As stated above, CPNPP was STARS Station 6 however Luminant Power is no longer part of the STARS Alliance. The revised license renewal application submittal date for CPNPP is now scheduled for the second quarter of 2022.
This communication contains no new licensing basis commitments regarding Comanche Peak Unit 1 and Unit 2.
"'I U. S. Nuclear Regulatory Commission
~TXX-15 164 Page 2 of 2 12/14/2015 Should you have any questions, please contact Mr. Jack Hicks at (254) 897-6725.
Sincerely, Luminant Generation Company LLC Rafael Elores By:
Thoma
. McCool Vice President, Engineering and Support c -
Marc L. Dapas, Region IV Balwant K. Singal, NRR Christopher G. Miller, Director, Division of License Renewal Resident Inspectors, Comanche Peak Steve Coppock, STARS Alliance