CP-200900253, Transmittal of the CPNPP Second-Half 2008 Fitness-For-Duty Program Performance Data
| ML090560524 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 02/03/2009 |
| From: | Blevins M Luminant Generation Co, Luminant Power |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| CP-200900253, TXX-09028 | |
| Download: ML090560524 (7) | |
Text
Mike Blevins Executive Vice President
& Chief Nuclear Officer Mike, Blevins@Luminant~com Luminant Power P 0 Box 1002 6322 North FM 56 Glen Rose, TX 76043 Luminant T 254 897 5209 C 817 559 9085 F 254 897 6652 CP-200900253 Log # TXX-09028 Ref. #
10CFR26.71 February 3, 2009 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION DOCKET NOS. 50-445 AND 50-446 TRANSMITTAL OF THE CPNPP SECOND-HALF 2008 FITNESS-FOR-DUTY PROGRAM PERFORMANCE DATA
Dear Sir or Madam:
Pursuant to 10CFR26.71, Luminant Generation Company LLC (Luminant Power) hereby submits the CPNPP Fitness-For-Duty Program Performance Data for the six month period of July 1, 2008 through December 31, 2008.
The data required by 10CFR26.71(d) are provided on standard forms with the exception of the summary of management actions and the list of events reported, which are provided on a separate page entitled "Summary of Management Actions and Statistical Analysis for Reporting Period."
ytcU(
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway - Comanche Peak Diablo Canyon Palo Verde
- San Onofre 7 South Texas Project - Wolf Creek
U. S. Nuclear Regulatory Commission TXX-09028 Page 2 of 2 02103/2009 This communication contains no new licensing basis commitments regarding Comanche Peak Units 1 and 2.
Should you have any questions, please contact Jim Barnette, Consulting Licensing Analyst at (254) 897-5866 or Bob Kidwell, Nuclear Security Supervisor at (254) 897-5310.
Sincerely, Luminant Generation Company LLC Mike Blevins X.L L& -L I
Attachments -,
1 Fitness-For-Duty Program Performance Data 2 Summary of Management Actions and Statistical Analysis for Reporting Period c -
E. E. Collins, Region IV B. K. Singal, NRR Resident Inspectors, Comanche Peak
Attachment I to TXX-09028 Fitness-For-Duty Program Performance Data r
Fitness For Duty Program Performance Data Personnel Subject to IOCFR26 (NUMARC Rev. Date 1/92) 6 Months 07/01/2008 to 12/31/2008 Company Luminant Power Contact Name Cuttoffs: Screen / Confirmation (ng/ml)
Marijuana 50 / 15 Cocaine 300 / 150 Opiates 300/300 Location Comanche Peak Phone o Appendix A to IOCFR26 Amphetamines Phencyclidine Alcohol 1000/500 25/ 25
(.04% BAC)
Short-Term Contractor Average Number with' Licensee Employees Unescorted Access 1514 755.9722222222 Long-Term Contractor Employees 2.879629629630 Short-Term Contractor Employees 729,4907407407 Number Number Number Number Number Number Tested FOLLOW-UP FOR CAUSE - OB FOR CAUSE - PA PRE-ACCESS 6
RANDOM 193 OTHER Number Positive Number Tested Number Positive w-0 Number Tested 27067 Number Positive FT7 Totals 220 0
0 f~~
1202 8f~
Page 1 of 2
01/19/2009 13:53:12
Breakdown of Confirmed Positive Tests for Specific Substances Licensee Employee Short Term Contractor MARIJUANA COCAINE OPIATES AMPHETAMINES PCP ALCOHOL REFUSED Page 2 of 2
01/19/2009 13:53:12 to TXX-09028 Summary of Management Actions and Statistical Analysis for Reporting Period
Summary of Management Actions and Statistical Analysis for Reporting Period - July2008 - December 2008 Analysis of the data indicates that we randomly tested 26.9% of the average eligible population during the period of this report. Overall, we tested 56% of the average population for calendar year 2008.
Due to an influx of support personnel in support of a refueling outage during this reporting period, we had a total of eight positive drug tests, all of which were short term contractor employees. There were no reportable events associated with the testing and no events were reported by telephone in accordance with 10CFR26 or 10CFR73.
In addition, Luminant Power submitted blind performance specimens in accordance with 10CFR26, Appendix A, Section 2.8(e)(2), requirements. There were no reportable events associated with the performance specimen testing.
Page I of I
(