MONTHYEARBVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-003, Pre-Notice of Disbursement from Decommissioning Trust2023-01-31031 January 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-030, Documentary Evidence of Performance Bond2022-12-30030 December 2022 Documentary Evidence of Performance Bond BVY 22-028, Re Proof of Financial Protection2022-11-28028 November 2022 Re Proof of Financial Protection BVY 22-027, Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station2022-11-11011 November 2022 Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station BVY 22-026, Pre-Notice of Disbursement from Decommissioning Trust2022-10-31031 October 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-025, Pre-Notice of Disbursement from Decommissioning Trust2022-10-0404 October 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-023, Pre-Notice of Disbursement from Decommissioning Trust2022-09-0101 September 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-022, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-22022 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-16016 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-020, Pre-Notice of Disbursement from Decommissioning Trust2022-08-0101 August 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-019, Pre-Notice of Disbursement from Decommissioning Trust2022-07-0606 July 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-013, Notification of Revised Decommissioning Cost Estimate2022-06-17017 June 2022 Notification of Revised Decommissioning Cost Estimate BVY 22-018, Pre-Notice of Disbursement from Decommissioning Trust2022-06-0808 June 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-015, 2021 Radiological Environmental Operating Report2022-05-0505 May 2022 2021 Radiological Environmental Operating Report BVY 22-017, Pre-Notice of Disbursement from Decommissioning Trust2022-05-0505 May 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-014, 2021 Radiological Effluent Release Report2022-04-28028 April 2022 2021 Radiological Effluent Release Report BVY 22-012, Biennial Report for Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d)2022-04-12012 April 2022 Biennial Report for Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d) BVY 22-011, Pre-Notice of Disbursement from Decommissioning Trust2022-04-0404 April 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-009, Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 20212022-03-23023 March 2022 Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 2021 BVY 22-008, Pre-Notice of Disbursement from Decommissioning Trust2022-02-24024 February 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-005, ISFSI Decommissioning Funding Plan2022-02-24024 February 2022 ISFSI Decommissioning Funding Plan 2024-01-04
[Table view] |
Text
Entergy Nuclear Operations, Inc.
Vermont Yankee 320 Governor Hunt Road Entergy Vernon, VT 05354 Tel 802 257 7711 Robert J. Wanczyk Licensing Manager BVY 12-053 July 2, 2012 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Vermont Yankee Registration of Spent Fuel Cask Use Vermont Yankee Nuclear Power Station Docket No. 50-271 License No. DPR-28 Dear Sir or Madam; Entergy Nuclear Operations, Inc. operates the Vermont Yankee (VY) Independent Spent Fuel Storage Installation in accordance with the general license provisions of 10 CFR
- 72. The conditions of 10 CFR 72.212 require the registration of a spent fuel cask within 30 days of using a cask for storage of spent nuclear fuel. The fuel contained in the cask is from the VY Nuclear Power Station.
Accordingly, this letter hereby registers the use of the thirteenth VY dry fuel storage cask. This letter also provides the following registration information:
Thirteenth VY Spent Fuel Cask System Date placed in use: June 29, 2012 Licensee's Name Entergy Nuclear Operations, Inc.
Licensee's Address Vermont Yankee 320 Governor Hunt Road Vernon, VT 05354 10CFR50 Docket Number 50-271 10CFR72 Docket Number 72-59 Cask Model Number HI-STORM 100 Cask Certificate Number 1014 Amendment 2 Holtec FSAR Version Revision 4 MPC Serial Number 365 HI-STORM Overpack Serial Number 572 Number of Fuel Bundles 68 P P"::ýz a (0
BVY 12-053 / page 2 of 2 There are no regulatory commitments being made in this submittal.
Should you have any questions concerning this transmittal, please contact me at (802) 451-3166.
Sincerely, RJW/jmd cc: Mr. William M. Dean Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713 Director, Spent Fuel Project Office Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555 Mr. Richard V. Guzman, Project Manager Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O8C2A Washington, DC 20555 USNRC Resident Inspector Entergy Nuclear Vermont Yankee, LLC 320 Governor Hunt Road Vernon, VT 05354 Ms. Elizabeth Miller, Commissioner VT Department of Public Service 112 State Street - Drawer 20 Montpelier, VT 05620-2601