3F1296-03, Monthly Operating Rept for Nov 1996 for Crystal River Unit 3
| ML20132C388 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 11/30/1996 |
| From: | Dao T, Kelley L FLORIDA POWER CORP. |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| References | |
| 3F1296-03, 3F1296-3, NUDOCS 9612180321 | |
| Download: ML20132C388 (5) | |
Text
Florida Power CORPORATION EM*
December 13, 1996 3F1296-03 U. S. Nuclear Regulatory Commission Attn:
Document Control Desk Washington, DC 20555-0001
Subject:
Monthly Operating Report
Dear Sir:
Attached is the Crystal River Unit-3 November 1996 Monthly Operating Report.
This report is submitted in accordance with Technical Specification 5.7.1.2.
Since ly, Larr ~
y Director, Nuclear Operation /
L Site Support LCK/ff Attachment F
xt:
Regional Administrator, Region II g)(,
Senior Resident Inspector NRR Project Manager p-DR DO 0500 02 R
PDR CRYSTAL RIVER ENERGY COMPLEX: 15760 W Power une St. Crystal River, Florida 344284708 e (352) 7954486 A Flanda Progress Company i
-. ~. -.. -
OPERATING DATA REPORT DOCKET NO.
50-302 UNIT FLCRP-3 DATE DEC 2,1996 I
COMPLETED BY T V Dao i
TELEPHONE (352) 795-6486 f
OPERATING STATUS 1.. U NIT N AM E:........................
CRYSTAL RIVER UNIT 3
- 2. REPORTING PERIOD:............
...... NOVEMBER -
- 3. LICENSEDTHERMAL POWER (MWt):.
t
............ 2544' 4.
NAMEPLATE RATING (GROSS MWe):.........-........ 890
)
l
- 5. DESIGN ELECTRICAL RATING (NETMWe):........,. - 825
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe):.. 860 i
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWe):..... 818 i
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE i
l i
l
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):
N/A
- 10. REASONS FOR RESTRICTIONS,IF ANY:
N/A i
THIS MONTH YR. TO DATE CUMULATIVE j
- 11. HOURS IN REPORTING PERIOD 720.0' 8,040.0 -
172.872.0
- 13. NUMBER OF HOURS REACTOR WAS CRITICAL
'O.04 3,308.1 -
117.416.2-
- 13. REACTOR RESERV.*: SHUTDOWN HOURS 0.0 '
O.0 1,280.C '
j
- 14. HRS GENERATOR ON LINE 10.0 -
3.109.5-
' 115,328.7L
- 15. UNIT RESFi% i SHUTDOWN HOURS 0.0
" 0.0 $
'O.0-I
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 0 7.465.0522 268.847.210 i
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 01 2.547,840 91,894.033
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 0 2.417.371 87,402,384 -
- 19. UNIT SERVICE FACTOR 0.0%
38.7 %
66.7 %
- 20. UNIT AVAILABLE FACTOR t
0.0%
38.7 %
66.7 %
- 21. UNIT CAPACITY FACTOR (using MDC net) 0.0%
36.8 %
62.6 %
- 22. UNIT CAPACITY FACTOR (using DER net) 0.0%
- 36.4%
61.3 %
h 83 UNIT FORCED OUTAGE RATE 100.0 %
46.7%
16.6 %
- 24. SHUTDOWNS SCHEDULED OVER NEXT SIX MONTHS (TYPE, DATE, AND DURATION OF EACH):
Continuation of the Lube oil outage until February 28,1997 to implement modifications to improve various safety margins.
- 25. IF SHUTDOWN AT END OF REPORT PERIOD. ESTIMATED DATE OF STARTUP; FEBRUARY 28.1997 5
- 28. I fNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
HIS ITEM IS NOT APPLICABLE TO CR-3 FORECAST ACHIEVED INmAL CRITICALITY NA NA INmAL ELECTRICITY NA NA COMMERCIAL OPERATION NA NA e
1
AVERAGE DAILY UNIT POWER LEVEL
-t t
DOCKET NO.
50-302 UNIT FLCRP-3 DATE DEC 2,1996 COMPLETED BY T V Dao TELEPHONE (352)795-6486 i
MONTH NOVEMBER DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
(MWe-Net) 1 0
17 0
l 2
0 18 0
3 0
19
'O l
4 0
20 0'
l l
5 0
21 0
6 0
22 0-
)
7 0:
23 0.
8
'O 24 0
l 9
0' 25 0
10 0
26 0
11 0-27 0
12 0--
28 0'
13 0
29 0
14 0
30 0
15
-0 31 N/A 16 0
INSTRUCTIONS:
l On this format, list the daily average unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
s i
l l
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
50-302 UNIT FLCRP-3 g,
REPORT MONTH. NOVEMBER DATE DEC 2,1996 COMPLETED BY T V Dao TELEPHONE
. (352)795-6486 NO.
DATE TYPE (1)
DURATION REASON (2)
MET 110D OF LICENSEE SYSTEM COMPONENT CAUSE AND CORRECTIVE ilOURS SHUTTING EVENT CODE (4)
CODE (5)
ACTION TO PREVENT
~
DOWN REACTOR (3) REPORT #
RECURRENCE 96-28 961101 F
720 D
4
~96-020-00 EE ENGINE Reactor remained in cold shutdown to prepare for modifications to improve various safety margins.
I 1
l 1
2 3
4 5
F: FORCED NASoft METHOO EXHIBIT G,mm w:sar3*tS EXHIBIT I-SAME SOURCE S-SCHEDULED A-EQUIPMENT FAILURE 1-MANUAL FOR PNPARATION OF DATA B-MAINTENANCE OR TEST 2-M ANUAL SCRAM ENTRY SHEETS FOR LICENSEE C-REFUELING MUTO SCRAM EVENT REPORT (LEFg FILE 1
D-REGULATORY NSTRICTION 4-CONTINUED (NUREG-.0 t e t)
E-OPERATOR TRANNG &
5-REDUCED LOAD LICENSE ADMINISTRATION 9-OTHER F-ADMHSTRATION 0-OPERATIONAL ERROR (EXPLAIN)
H-OTHER
MONTHLY OPERATIONAL
SUMMARY
STATEMENT DOCKET NO.
50-302 UNrT FLCRP-3 DATE DEC 2.1996 COMPLETED BY T V Dao TELEPHONE (352) 795-6486 MONTH: NOVEMBER
SUMMARY
STATEMENT:
Crystal River remained in cold shutdown through November to resolve the emergency diesel generator maximum electricalloading issue and to prepare for modifications to improve various safety margins.