Monthly Operating Rept for Nov 1996 for Crystal River Unit 3
ML20132C388
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 11/30/1996
From: Dao T, Kelley L
FLORIDA POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
3F1296-03, 3F1296-3, NUDOCS 9612180321
Download: ML20132C388 (5)


Text

Florida Power CORPORATION EM*

December 13, 1996 3F1296-03 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Monthly Operating Report

Dear Sir:

Attached is the Crystal River Unit-3 November 1996 Monthly Operating Report.

This report is submitted in accordance with Technical Specification 5.7.1.2.

Since ly, Larr ~ y Director, Nuclear Operation / L Site Support LCK/ff Attachment xt: Regional Administrator, Region II F Senior Resident Inspector < g)(,

NRR Project Manager p-0500 02 DR DO  !

R PDR CRYSTAL RIVER ENERGY COMPLEX: 15760 W Power une St . Crystal River, Florida 344284708 e (352) 7954486 A Flanda Progress Company l

i

- . ~ . - . . - ._- . - _ . . -.. - . - - - . . - . . _ - - . . - - . . . . - . . . - _ . .

OPERATING DATA REPORT DOCKET NO. 50-302 UNIT FLCRP-3 DATE DEC 2,1996 I COMPLETED BY T V Dao i TELEPHONE (352) 795-6486 OPERATING STATUS f 1..

U NIT N AM E:.. . . .... . . . .. ... . .. . .. .. . . . . .

CRYSTAL RIVER UNIT 3

2. REPORTING PERIOD:.. ....... .. . ..

. ... .. NOVEMBER -

t

3. LICENSEDTHERMAL POWER (MWt):. ........ .... 2544' 4.

NAMEPLATE RATING (GROSS MWe):... . ... ..- ... ... .. 890 l 5. DESIGN ELECTRICAL RATING (NETMWe):. . .. ...., . - 825 )

- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe):.. 860 i

7. MAXIMUM DEPENDABLE CAPACITY (NET MWe):.... . 818
i
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE i

l i l .

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe): N/A I
10. REASONS FOR RESTRICTIONS,IF ANY:

N/A THIS MONTH i YR. TO DATE CUMULATIVE .

j 11. HOURS IN REPORTING PERIOD 720.0' 8,040.0 -

! 172.872.0

13. NUMBER OF HOURS REACTOR WAS CRITICAL 'O.04 3,308.1 - 117.416.2-  ;
13. REACTOR RESERV.*: SHUTDOWN HOURS 0.0 ' O.0 1,280.C '
14. HRS GENERATOR ON LINE j

10.0 - 3.109.5- ' 115,328.7L

15. UNIT RESFi% i SHUTDOWN HOURS 0.0 " 0.0 $ 'O.0- I
16. GROSS THERMAL ENERGY GENERATED (MWH) 0 7.465.0522 268.847.210 i
17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 01 2.547,840 91,894.033
18. NET ELECTRICAL ENERGY GENERATED (MWH) 0 2.417.371 87,402,384 -
19. UNIT SERVICE FACTOR 0.0% 38.7 % 66.7 % t
20. UNIT AVAILABLE FACTOR 0.0% 38.7 % 66.7 %
21. UNIT CAPACITY FACTOR (using MDC net) 0.0% 36.8 % 62.6 %
22. UNIT CAPACITY FACTOR (using DER net) 0.0% - 36.4% 61.3 %

! 83 UNIT FORCED OUTAGE RATE h 100.0 % 46.7% 16.6 %

24. SHUTDOWNS SCHEDULED OVER NEXT SIX MONTHS (TYPE, DATE, AND DURATION OF EACH):

Continuation of the Lube oil outage until February 28,1997 to implement modifications to improve various safety margins.

25. IF SHUTDOWN AT END OF REPORT PERIOD. ESTIMATED DATE OF STARTUP; 5

FEBRUARY 28.1997 '

28. I fNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

HIS ITEM IS NOT APPLICABLE TO CR-3 FORECAST

ACHIEVED '

INmAL CRITICALITY NA NA

  • INmAL ELECTRICITY NA NA COMMERCIAL OPERATION NA NA e

1

AVERAGE DAILY UNIT POWER LEVEL -t t

DOCKET NO. 50-302 UNIT FLCRP-3 DATE DEC 2,1996  ;

COMPLETED BY T V Dao TELEPHONE (352)795-6486 i

MONTH NOVEMBER DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1 0 17 0 l

2 0 18 0 3 0 19 'O l 4 0 20 0' l

l 5 0 21 0 6 0 22 0- )

7 0: 23 0. I 8 'O 24 0 l 9 0' 25 0 10 0 26 0 11 0- 27 0 12 0-- 28 0' 13 0 29 0 14 0 30 0 15 -0 31 N/A ,

16 0

!' INSTRUCTIONS:

l On this format, list the daily average unit power level in MWe-Net for each day in the I

! reporting month. Compute to the nearest whole megawatt.  ;

s l

i

l l

UNIT SHUTDOWNS AND POWER REDUCTIONS .

DOCKET NO. 50-302 UNIT FLCRP-3 g, REPORT MONTH. NOVEMBER DATE DEC 2,1996 COMPLETED BY T V Dao TELEPHONE . (352)795-6486 NO. DATE TYPE (1) DURATION REASON (2) MET 110D OF LICENSEE SYSTEM COMPONENT CAUSE AND CORRECTIVE

~

ilOURS SHUTTING EVENT CODE (4) CODE (5) ACTION TO PREVENT DOWN REACTOR (3) REPORT # RECURRENCE 96-28 961101 F 720 D 4 ~96-020-00 EE ENGINE Reactor remained in cold shutdown to prepare for modifications to improve various safety margins.

I 1

l 1 2 3 4 5 F: FORCED NASoft METHOO EXHIBIT G ,mm w:sar3*tS EXHIBIT I- SAME SOURCE S- SCHEDULED A-EQUIPMENT FAILURE 1-MANUAL FOR PNPARATION OF DATA B-MAINTENANCE OR TEST 2-M ANUAL SCRAM ENTRY SHEETS FOR LICENSEE C-REFUELING MUTO SCRAM EVENT REPORT (LEFg FILE 1 D-REGULATORY NSTRICTION 4-CONTINUED (NUREG-.0 t e t)

E-OPERATOR TRANNG & 5-REDUCED LOAD LICENSE ADMINISTRATION 9-OTHER F-ADMHSTRATION 0-OPERATIONAL ERROR (EXPLAIN)

H-OTHER

MONTHLY OPERATIONAL

SUMMARY

STATEMENT DOCKET NO. 50-302 UNrT FLCRP-3 DATE DEC 2.1996 COMPLETED BY T V Dao TELEPHONE (352) 795-6486 MONTH: NOVEMBER

SUMMARY

STATEMENT:

Crystal River remained in cold shutdown through November to resolve the emergency diesel generator maximum electricalloading issue and to prepare for modifications to improve various safety margins.