1CAN021503, Responses to Request for Additional Information Reactor Vessel Internals Aging Management Program Plan

From kanterella
Jump to navigation Jump to search

Responses to Request for Additional Information Reactor Vessel Internals Aging Management Program Plan
ML15043A102
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 02/10/2015
From: Pyle S
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
1CAN021503
Download: ML15043A102 (13)


Text

Entergy Entergy Operations, Inc.

1448 S.R. 333 Russeliville, AR 72802 Tel 479-858-4704 Stephenie L. Pyle Manager, Regulatory Assurance Arkansas Nuclear One 1CAN021503 February 10, 2015 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555

SUBJECT:

Responses to Request for Additional Information Reactor Vessel Internals Aging Management Program Plan Arkansas Nuclear One, Unit 1 Docket No. 50-313 License No. DPR-51

REFERENCES:

1 Entergy letter to NRC, "Reactor Vessel Internals Aging Management Program Plan," dated May 20, 2014 (1CAN051403) (ML14141A554) 2 NRC email to Entergy, dated December 2, 2014, "Requests for Additional Information - Reactor Vessel Internals Aging Management Plan - ANO-1

-TAC No. MF4201"

Dear Sir or Madam:

Entergy Operations, Inc. (Entergy) submitted the Arkansas Nuclear One, Unit 1 (ANO-1)

Reactor Vessel Internals Aging Management Program Plan (Reference 1) to fulfill a commitment made as part of the ANO-1 License Renewal Application. The plan identified the internals components that must be included for aging management review and identifies the augmented inspection plan for the ANO-1 reactor vessel internals.

The NRC Staff has reviewed the submittal and developed a request for additional information (RAI). This request was provided via Reference 2. The purpose of this submittal is to provide the requested information.

The responses to the RAIs were provided by Structural Integrity Associates, Inc. (SI) (author of the ANO-1 Aging Management Program Plan) and AREVA (manufacturer of the ANO-1 reactor vessel internals).

Attachment 2 to this letter contains proprietary information - Attachment 2 is withheld from public disclosure per 10 CFR 2.390.

ý009

1CAN021503 Page 2 of 3 SI developed the responses to RAls 6(a, c, d, and e), 9, 10, 14, 15, and 16. These responses are provided in Attachment 1 to this submittal.

AREVA document ANP-3383P, Revision 0, "Response to Request for Additional Information for the Reactor Pressure Vessel Internals Aging Management Program Plan for Arkansas Nuclear One Unit 1," has been prepared with the responses to the remaining requests. The information contained in the AREVA document is considered proprietary to AREVA. Attachment 2 is the proprietary version of the document. A non-proprietary version of the AREVA document is included in Attachment 3. AREVA requests that the proprietary information be withheld from public disclosure in accordance with 10 CFR 2.390. AREVA has provided Entergy with authorization to provide the proprietary information. An affidavit by the information owner, AREVA, supporting the request for non-disclosure is provided in Attachment 4; Therefore, Entergy requests that Attachment 2 of this submittal be withheld from public disclosure in accordance with 10 CFR 2.390. It should be noted that the information contained in is not considered proprietary.

Several new regulatory commitments have been identified in this letter. These commitments are listed in Attachment 5.

If you have any questions or require additional information, please contact me.

Sincerely, SLP/rwc Attachments

1. Structural Integrity Associates, Inc. document 1401460.402.RO, "Responses to Requests for Additional Information on the Reactor Vessel Internals Aging Management Program for Arkansas Nuclear One, Unit 1,"
2. AREVA document ANP-3383P, "Response to Request for Additional Information for the Reactor Pressure Vessel Internals Aging Management Program Plan for Arkansas Nuclear One Unit 1," PROPRIETARY
3. AREVA document ANP-3383NP, "Response to Request for Additional Information for the Reactor Pressure Vessel Internals Aging Management Program Plan for Arkansas Nuclear One Unit 1," NON-PROPRIETARY
4. Affidavit
5. List of Commitments Attachment 2 to this letter contains proprietary information - Attachment 2 is withheld from public disclosure per 10 CFR 2.390.

1CAN021503 Page 3 of 3 cc: Mr. Marc L. Dapas Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Ms. Andrea E. George MS O-8B1 One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mr. Bernard R. Bevill Arkansas Department of Health Radiation Control Section 4815 West Markham Street Slot #30 Little Rock, AR 72205 Attachment 2 to this letter contains proprietary information - Attachment 2 is withheld from public disclosure per 10 CFR 2.390.

Attachment 1 1 CAN021503 Structural Integrity Associates, Inc. document 1401460.402.R0 Responses to Requests for Additional Information on the Reactor Vessel Internals Aging Management Program for Arkansas Nuclear One, Unit I

5215 Hellyer Ave.

Suite 210 San Jose, CA 95138-1025 Phone: 408-978-8200 Fax: 408-978-8964 www.structint.com clohse@structint.com February 5, 2015 Report No. 1401460.402.RO Quality Program: 0 Nuclear D Commercial Christopher Walker Arkansas Nuclear One Generating Station 1448 State Road 333 Russellville, AR 72802

Subject:

Responses to Requests for Additional Information on the Reactor Vessel Internals Aging Management Program for Arkansas Nuclear One, Unit 1

Dear Chris:

Here are the responses to the NRC requests for additional information (RAIs) on the reactor vessel internals (RVI) aging management program (AMP) for RAIs 6 (a, c, d, e), 9, 10, 14, 15, and 16 for Arkansas Nuclear One, Unit I (ANO- 1).

1.0 INTRODUCTION

SI previously developed the RVI AMP for ANO-1 in May of 2014, which was submitted to the NRC as part of ANO- l's license renewal commitment. SI has provided responses to RAIs 6 (a, c, d, e), 9, 10, 14, 15, and 16 which are contained in the following sections.

2.0 RAI RESPONSES 2.1 EVIB-RAI-6 Section 5.2 of the ANOI RPV internalsAMP states that the above orphan components will undergo a future screening and characterization,and based on the screening results, they will be removedfrom fiture inspections if they screen out, or added to the primary or expansion categoriesif they screen in. Further,it is statedthat, until that time when the above components are screened and characterized,these components will be inspected during the 10-yearISI intervals based on their aging effects.

(a) Please identify the calendaryear when these orphan components will be screened andcharacterized.

(b) Pleaseprovide additionaldetails regardingthe screening and characterizationprocessfor the above orphan components, including whether this process will be consistent with that performedfor MRP-189, Rev. 1.

Toll-Free 877-474-7693 Akron, OH Austin,'TX Charlotte, NC Chattanooga, TN 330-899-9753 512-533-9191 704-597-5554 423-553-1180 Chicago, IL Denver, CO San Diego, CA San Jose, CA State College, PA Toronto, Canada 877-474-7693 303-792-0077 858-455-6350 408-978-8200 814-954-7776 905"29-9817

Christopher Walker February 5, 2015 Report No. 1401460.402.RO Page 2 of 9 Section 5.2 of the ANOI RPV internalsAMP lists the aging effects for the orphan components and states that, basedon a review of these aging affects, the orphan components will be visually inspected (VT-3) during the JO-year ISI inspections.

(c) Please state whether previous VT-3 or other inspections have been performedfor these components, and discuss the results of these inspections if any. Based on the aging effects for the components described in Section 5.2, pleasejustify the adequacy of performing VT-3 visual examinations on a JO-yearISI interval.

(d)Pleasestate whether the VT-3 examinations are intendedas an interim measurefor aging management until the screening and characterizationis complete.

(e) Since these components are currently designatedto receive a VT-3 examination every J O-yearISI interval and were included in the ANO, Unit 1 ASME Code,Section XI ISI Program,please explain why they are not currently inchlded in Table 5-3, "B& W Plants Existing Program Componentsfrom ARE VA Guidance," of the RPV internalsAMP.

Responses to EVIB-RAI-6 6(a)

The screening and categorization is expected to be completed in 2015.

6(c)

The Reactor Vessel Level Monitoring System (RVLMS) probe supports and subcomponents (i.e., brazement guide assembly j-bolt and nut) were identified in the aging management review as being potentially susceptible to cracking and stress relaxation.

Part of the ANO-1 surveillance specimen holder tube (SSHT) was removed in 1976. The upper SSHT assembly and some of the brackets and their bolts are still installed in the ANO-1 reactor vessel. Although the specimens have been removed and these components are not required to maintain their integrity for the specimens, these components must not become loose parts. Therefore, cracking and stress relaxation are applicable aging effects for the ANO-1 SSHT bolting.

The thermal shield and thermal shield upper restraint assemblies were not evaluated previously (in BAW-2248) but are fabricated from the same materials and exposed to the same environment as other core barrel assembly items. The applicable aging effects include cracking and reduction of fracture toughness.

In prior Section XI, 10-year ISI examinations for B-N-3 components in ANO- 1, visual (VT-3) examination methods were performed of the remaining portions of the SSHT assembly still in place as well as the thermal shield and restraints. No relevant conditions were detected. This technique is adequate for detection of broken or loose parts from the bolted structures, and, therefore, VT-3 is the appropriate inspection method.

The other orphan components (i.e., brackets, bolts and nuts) were not included in the Section XI, 10-year ISI examinations since they are not considered to be B-N-3 (Removal Core Support Structures) and had not previously been identified as having potential aging concerns.

C StructuralIntegrity Associates, Inc?

Christopher Walker February 5, 2015 Report No. 1401460.402.RO Page 3 of 9 Using a VT-3 technique is adequate for detection of broken or loose parts from the bolted structures, and, therefore, VT-3 is the appropriate inspection method.

6(d)

Yes, these upcoming VT-3 examinations are intended to be an interim measure until screening and categorization of the orphan components have been completed. As indicated above in the response to EVIB-RAI-6(a), the screening and categorization process for the orphan components is expected to be completed in 2015.

6(e)

The orphan components were identified for ANO- 1 as part of the aging management review for license renewal. These components include:

" Reactor vessel level monitoring system (RVLMS) components internal to the reactor vessel The ANO-1 reactor vessel internals have an additional component function, which is to support the RVLMS probes. Cracking and stress relaxation were identified as aging effects for the RVLMS brazement guide assembly j-bolt and nut.

" Remaining portions of surveillance specimen holder tubes (SSHT)

Although all the specimens have been removed, portions of the shroud tube and the supports that are bolted to the core support shield remain in place. These components have the function of remaining secured to prevent loose parts in the reactor coolant system. Cracking and stress relaxation were identified as aging effects for the SSHT bolting.

" Thermal shield and thermal shield upper restraint Support the intended function of providing gamma and neutron shielding. Cracking and reduction of fracture toughness were identified as aging effects for the thermal shield and thermal shield upper restraint assemblies.

These orphan components have been put into a special category separate from the Existing Program Components. See Table 5-6 of the AMP. These orphan components have been placed in a separate category until the screening and categorization process is completed. At that time, the components will be placed in the appropriate category (primary, expansion, or no additional measures) based on the results of the screening and categorization. As indicated above in the response to EVIB-RAI-6(a), the screening and categorization process for the orphan components is expected to be completed in 2015.

VStructural Integrity Associates, Inc.O

Christopher Walker February 5, 2015 Report No. 1401460.402.RO Page 4 of 9 2.2 EVIB-RAI-9 Table 5-3 of the ANO1 RPV internalsA MP provided the B& W existingprogram inspection criteriafor the core support shield vent valve miscellaneous locking devices for the originaland modified design - VT-3 visual examination of the locking devices on the JO-yearIS1 intervalper the requirementsof the ASME Code,Section XI. Pleasestate whether these VT-3 examinationswere performed as part of the ASME Code,Section XI, JO-year interval inservice inspections during the original40-year licensed operating term. Pleaseidentify and discuss any relevant indicationsfor the ASME Code, Section VT-3 examinations of these items.

Response to EVIB-RAI-9 The previous 10-year ISI exams were reviewed. The vent valves were examined as part of the VT-3 exam performed in the vessel. The examination in 2008 noted raised metal in two locations. These indications were already known and previously dispositioned during the visual exams that are performed on all vent valves during each refueling outage. See response to EVIB-RAI-1 (a).

2.3 EVIB-RAI-10 Table 5-3 of the ANO1 RPV internalsAMP, "Note 1 "describes additionalvent valve testing and examinations for leakage and degradationin the valve components, which are to be performed in accordancewith the plant 's TS or the inservice testing programs.Please identify the applicableTS requirementsand/or inservice testing program requirementsfor the additionaltesting and examination of the vent valve components.

Response to EVIB-RAI-10 The inservice testing program specifies that the vent valves shall be stroke tested in the open and closed directions. There are three requirements that are to be performed every 18 months (every refueling outage as ANO-1 is on an 18 month cycle) for all of the vent valves. These requirements for testing of the valves are contained in ANO- I's technical requirements manual.

1. Conduct a remote visual inspection of visually accessible surfaces of each reactor internals vent valve body and disc surfaces and evaluate any observed surface irregularities.
2. Verify each reactor internals vent valve is not stuck in an open position.
3. Verify through manual activation that each reactor internals vent valve is fully open with a force _<400 lbs (applied vertically upward).

2.4 EVIB-RAI-14 Applicant/LicenseeAction Item 6 of the NRC staff SE for MRP-227-A requires the licensee tojustify the acceptability of each of the inaccessibleB& W expansion componentsfor continued operation by performing an evaluation, orpropose a schedulefor replacement of the components. Thie inaccessibleB& W components are:

  • the core barrelcylinder and welds,
  • theformerplates, and
  • the bolting (core barrel-to-formerbolts, internaland external baffle-to-bajfle bolts, and associated locking devices),

rStructuralIntegrity Associates, Inc?

Christopher Walker February 5, 2015 Report No. 1401460.402.RO Page 5 of 9 For the above inaccessiblecomponents, the licensee provided a regulatory commitment to submit an evaluation, schedule jbr replacement, orjustificationibrsome other alternativeprocess to the NRC by the end of one year from the initial inspection of the linked primaty component items, if these inspections indicateaging that meets the expansioncriteriafor the linked primarycomponents.

As stated in Section 4.2.6 of the MRP-227-A NRC staff SE, the justificationfor the continued operabilityof the above inaccessible componentsfor the periodof extended operationand, if necessary, schedulefor replacement of these components must be providedfor NRC review and approvalas part of the licensee's applicationto implement MRP-22 7-A.

a) Therefore, in order to complete its evaluation of the ANO] RPV internalsAMP, the NRC staff requests that the licenseeprovide the irjbrmationrequiredby Action Item 6 of the MRP-227-A NRC staff SE.

Specifically, the staff requests that the licenseejustij' the acceptabilityof the inaccessiblecomponents for continued operationthrough the period of extended operation by performing an evaluation and, if necessary,provide a schedulefor replacement of the componentsfor staff review and approval.

b) If the licensee cannotjustify the acceptability of the inaccessiblecomponentsfor continued operation through the period of extended operationby performingan evaluation and, if necessary,providing a schedulefor replacement of the components,for staff review and approvalas partits current application,the staff requests that the licensee propose an alternativeprocessfor ensuring the operabilityof the inaccessiblecomponents during the period of extended operation.

Responses to EVIB-RAI-14 14(a)

This action will require further assessment of the flaw tolerance or functionality of the following components in the degraded condition:

" the core barrel cylinder and welds

  • the former plates, and

" the bolting (core barrel-to-former bolts, internal and external baffle-to-baffle bolts, and associated locking devices)

It is well known that the bolted configurations in the RV internals are highly redundant structures and that the structural integrity and functionality can be maintained with a fraction of the bolts remaining intact. Also, the core barrel cylinder and welds and the former plates must be capable of maintaining core support and alignment in the event of an accident condition so that the reactor may be shut down safely.

With regard to the acceptability of the inaccessible components by analyses, work is ongoing to evaluate these components to demonstrate no loss of functionality. Specifically, for the core barrel cylinder, this inaccessible component is an expansion item linked to cracking in the baffle plate. The goal of this evaluation is to show that the core barrel cylinder (and vertical and circumferential seam welds) will maintain functionality during the period of extended operation, through analyses/evaluations that confirm 1) the likelihood of a manufacturing defect is low, 2) susceptibility to SCC and IASCC is unlikely, 3) failure due to irradiation embrittlement is unlikely, and 4) even in the unlikely event of a failure of the core barrel cylinder, the reactor will still be able to shut down safely. For the barrel-to-former and baffle-to-baffle bolts, these inaccessible components are linked to baffle-to-former bolt cracking. The goal of this functionality evaluation is to show that the core barrel assembly VStructural Integrity Associates, Inc?

Christopher Walker February 5, 2015 Report No. 1401460.402.RO Page 6 of 9 bolting will maintain its function for a given period of operation, as limited by degraded core barrel-to-former and baffle-to-baffle bolts. For the former plates, this inaccessible component is an expansion item linked to cracking in the baffle plate. The goal of the evaluation is to show that the former plates will maintain functionality during the period of extended operation. These evaluations will be submitted by the end of 2016.

14(b)

There is no proposed alternative at this time. However, depending on the outcome of the inspections of the primary components and the evaluations of functionality of the inaccessible components noted above, ANO-1 will make a determination about the need for additional actions related to these components.

2.5 EVIB-RAI-15 Applicant/Licensee Action Item 7 of the NRC staff SE for MRP-227-A requires the licensee to develop plant-specific analyses to be appliedfor theirfacilities to demonstrate that RP V internals components that may be fabricatedfiom cast austeniticstainless steel (CASS), martensiticstainless steel or precipitationhardened stainless steel, will maintain theirfinctionality during the period of extended operation,consideringpossible loss offracture toughness in these components due to thermal and irradiationembrittlement and limitations on accessibilit for inspection and the resolution/sensitivityof the inspection techniques. The action item states that the licensee shall include the plant-specific analysis as part of their submittal to apply MRP-227-A.

In the response to Applicant/Licensee Action Item 7, Section 5.7 of the ANO1 RPV internals AMP provides information indicatingthatfuture analyticalevaluations will be performedfor assessing the effects of reduction in fracture toughness, due to thermal and irradiationembrittlement, on the CASS andprecipitationhardened stainless steel RPV internals components at ANO, Unit 1. The ANO, Unit 1, CASS andprecipitationhardened stainless steel components requiring these analyticalevaluationsfor demonstratingfinctionality during the periodof extended operation are:

" CASS Components:

o Control Rod Guide Tube Assembly Spacer Castings o Core Support Shield Assembly Vent Valve Bodies o Incore MonitoringInstrumentationGuide Tube Assembly Spider Castings

  • PrecipitationHardenedStainless Steel Components:

o Core Support Shield Assembly Vent Valve RetainingRings.

The licensee providedregulatory commitments to complete the analyticalevaluations of these components 12 months priorto the second refueling outage after entering the periodof extended operation.

As statedin Section 4.2.7 of the MRP-22 7-A NRC Staff SE, the plant-specificanalysis of these components required by this action item shall be includedas part of licensees' submittals to implement MiRP-227-A.

a) Therefore, in order to complete its evaluationof the ANO1 RPV internalsAMP, the NRC staff requests that the licensee provide the information required by Action Item 7 of the MRP-227-A NRC staff SE.

Specifically, the staff requests that the licensee provide plant-specificanalyses to demonstrate that the above CASS and precipitationhardenedstainless steel RP V internalcomponents will maintain their functionality during the period of extended operation, consideringpossible loss offracture toughness in these components due to thermal and irradiationembrittlement and limitationson accessibilityfor inspection and the resolution/sensitivityof the inspection techniques.

VStructural Integrity Associates, Inc.

Christopher Walker February 5, 2015 Report No. 1401460.402.RO Page 7 of 9 b) If the licensee cannotprovide the plant-specificanalysis of the CASS and precipitationhardened stainless steel RPV internalcomponents requiredby Action Item 7for staff review and approvalas part its current application,the staff requests that the licensee propose an alternativeprocessfor ensuringthat thefinctionality of these components will be maintainedduring the period of extended operation,consideringpossible loss offiacture toughness in these components due to thermal and irradiationembrittlement and limitations on accessibilityfor inspection and the resolution/sensitivity of the inspection techniques.

Responses to EVIB-RAI-15 15(a)

A revised screening and evaluation method for combined thermal and irradiation embrittlement of CASS has been proposed by the industry for NRC consideration and review.

The continuing dialogue between the industry and NRC regarding these synergistic effects for CASS items may result in a different method to screen the CASS components. Pending the outcome of these discussions, this revised approach would be applicable for the ANO-1 CASS internals components. This two-phase screening approach will be applied to the ANO- I CASS RV internals in order to identify and then prioritize which components may require further attention.

In the interim, ANO will perform additional studies of the CASS and PH stainless steel materials for the components identified here.

In order to confirm that the CASS and PH materials in the RV internals for ANO-I can maintain functionality in the degraded condition, a multi-phase effort will be performed. The first task will be to identify susceptible RVI components using the screening criteria.

Additional tasks are as follows:

" CRGT Spacer Castings - analyses will consider potential of failure based on the degree of susceptibility to embrittlement and magnitude of stresses present and plant-specific functionality.

  • Core Support Shield Vent Valve Bodies - ferrite content has been determined to be below the screening criteria.

" IMI Spider Castings - an assessment will be performed of the potential of failure based on the degree of susceptibility to embrittlement and magnitude of stresses present for the IMI guide tube spiders.

" Core Support Shield Vent Valve Retaining Rings - an assessment will be performed of the potential of failure based on the degree of susceptibility to embrittlement and magnitude of stresses present for the vent valve retaining rings and plant-specific functionality.

These evaluations will be submitted by September 2015.

ýStructuralIntegrity Associates, Inc!

Christopher Walker February 5, 2015 Report No. 1401460.402.RO Page 8 of 9 15(b)

There is no proposed alternative at this time. However, if functionality cannot be assured by these analyses, additional options will be identified to ensure functionality of these components after having completed the tasks described above in the response to EVIB-RAI-15(a).

2.6 EVIB-RAI-16 In orderfor the NRC staff to verify the adequacy of the program implementation scheduleprovided in Table 5-6 of the ANO1 RPV internals AMP, please confirm that the length of the ANO, Unit 1, refueling cycle corresponds to 18 months. In additionplease specify the projected calendaryears correspondingto ANO, Unit 1, refueling outages JR26 and 1R33.

Response to EVIB-RAI-16 ANO-1 is on an 18 month refueling cycle. Refueling outage 1R26 will occur in 2016 and refueling outage 1R33 is projected to occur in 2027.

VStructural Integrity Associates, Inc.!

Christopher Walker February 5, 2015 Report No. 1401460.402.RO Page 9 of 9 Prepared by: Reviewed by:

2-5-15 2-5-15 Chris Lohse, P.E. Date Timothy Griesbach Date Senior Consultant Senior Associate Approved by:

2-5-15 Chris Lohse, P.E. Date Senior Consultant rStructuralIntegrity Associates, Inc!