Other: 1CAN051403, Unit 1, Reactor Vessel Internals Aging Management Program Plan, ML21019A002, ML21019A003, ML21180A030, ML21180A031, ML21224A001, ML21225A070, ML21225A071, ML21225A073, W3F1-2012-0011, Commitment Date Change for Submittal of Reactor Vessel Internals Degradation Management Program Consistent with MRP-227-A
|
MONTHYEARML1011601822010-04-16016 April 2010 License Amendment Request for Extended Power Uprate Project stage: Request L-2010-181, Withdrawal of Extended Power Uprate License Amendment Request2010-08-13013 August 2010 Withdrawal of Extended Power Uprate License Amendment Request Project stage: Withdrawal ML1035604192010-11-22022 November 2010 Transmittal of Affidavits from Westinghouse, Areva and Caldon Ultrasonica Technology Center Re License Amendment Request for Extended Power Uprate Project stage: Request ML11356A3072011-06-22022 June 2011 New York State (NYS) Pre-Filed Evidentiary Hearing Exhibit NYS000309, Final Safety Evaluation of EPRI Report, Materials Reliability Program Report 1016596 (MRP-227), Revision 0, Pressurized Water Reactor (PWR) Internals Inspection and Evalu Project stage: Approval ML12335A4702011-06-22022 June 2011 Official Exhibit - NYS000309-00-BD01 - Final Safety Evaluation of EPRI Report, Materials Reliability Program Report 1016596 (MRP-227), Revision 0, Pressurized Water Reactor (PWR) Internals Inspection and Evaluation. Project stage: Approval L-2011-255, Response to NRC Vessels & Internals Integrity Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request2011-07-0808 July 2011 Response to NRC Vessels & Internals Integrity Branch Request for Additional Information Regarding Extended Power Uprate License Amendment Request Project stage: Request W3F1-2012-0011, Commitment Date Change for Submittal of Reactor Vessel Internals Degradation Management Program Consistent with MRP-227-A2012-02-27027 February 2012 Commitment Date Change for Submittal of Reactor Vessel Internals Degradation Management Program Consistent with MRP-227-A Project stage: Other 1CAN051403, Unit 1, Reactor Vessel Internals Aging Management Program Plan2014-05-20020 May 2014 Unit 1, Reactor Vessel Internals Aging Management Program Plan Project stage: Other ONS-2015-054, Proposed License Amendment Request for the Reactor Vessel Internals Inspection Plan; LAR Number 2010-06 - Action Item No. 6 Completion Date Change2015-05-28028 May 2015 Proposed License Amendment Request for the Reactor Vessel Internals Inspection Plan; LAR Number 2010-06 - Action Item No. 6 Completion Date Change Project stage: Request ML17361A1872017-12-18018 December 2017 Electric Power Research Institute (EPRI) - Transmittal of Revision 1 to Technical Reports MRP-175 and MRP-211 Project stage: Request ML21007A0002021-01-0606 January 2021 Transmit Electric Power Research Institute Presentation Slides for Closed Meeting Regarding MRP-230 Revision 3 to NRC for Information Project stage: Meeting ML21019A0032021-01-19019 January 2021 MRP-228, Rev 4, Materials Reliability Program Inspection Standard for Pressurized Water Reactor Internals Nonproprietary Project stage: Other ML21019A0022021-01-19019 January 2021 EPRI Transmittal Letter for MRP-228, Rev 4 Project stage: Other ML21048A3152021-02-17017 February 2021 Transmit Electric Power Research Institute Presentation Slides for Closed Meeting Regarding MRP-229 Revision 4 to NRC for Information Project stage: Meeting ML21048A3162021-02-23023 February 2021 EPRI Presentation Feb 23, 2021 MRP229 Rev 4 Meeting (Non-Proprietary) Project stage: Meeting ML21225A0712021-05-31031 May 2021 2021 Technical Report 3002020103, Materials Reliability Program: Aging Management Strategies for B&W Pressurized Water Reactor Internals (MRP-231-NP, Rev. 4) Project stage: Other ML21180A0312021-05-31031 May 2021 MRP-232-NP, Revision 2, Materials Reliability Program: Aging Management Strategies for Westinghouse and Combustion Engineering PWR Internal Components Project stage: Other ML21225A0732021-06-22022 June 2021 Request for MRP-231, Revision 4 Project stage: Other ML21180A0302021-06-25025 June 2021 Transmit Electric Power Research Institute Topical Report MRP-232 Revision 2 to NRC for Information Project stage: Other ML21224A0012021-08-11011 August 2021 MRP-2021-012 - Transmit Closed Session Slides on MRP-232 Rev. 2 to Us NRC Project stage: Other ML21224A0032021-08-12012 August 2021 Open Session Intro - MRP-232 Revision 2 Changes for SLR 08122021 NRC Public Meeting Project stage: Meeting ML21225A0702021-08-12012 August 2021 Transmit Electric Power Research Institute Topical Report MRP-231 Revision 4 to NRC for Information Project stage: Other ML21301A2342021-10-11011 October 2021 Transmit Electric Power Research Institute Presentation Slides for Closed Meeting Regarding MRP-231 Revision 1 to NRC for Information Project stage: Meeting ML21285A0482021-10-11011 October 2021 Transmit of Electric Power Research Institute Presentation Slides for Closed Meeting Regarding MRP-231 Revision 1 to NRC for Information Project stage: Meeting 2021-01-19
[Table View] |
Text
Entergy Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802 Tel 479-858-4704 Stephenie L. Pyle Manager, Regulatory Assurance Arkansas Nuclear One 1 CAN051403 May 20, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
REFERENCES:
Reactor Vessel Internals Aging Management Program Plan Arkansas Nuclear One - Unit 1 Docket No. 50-313 License No. DPR-51
- 1. Entergy letter dated January 31, 2000, "License Renewal Application,"
(1CAN010003) (ML003679667)
- 2. Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guidelines (MRP-227-A) December 2011
- 3. NRC letter from Robert A. Nelson (NRC) to Neil Wilmshurst (EPRI) dated December 16, 2011, "Revision 1 to the Final Safety Evaluation of EPRI Report, Materials Reliability Program Report 1016596 (MRP-227),
Revision 0, "Pressurized Water Reactor (PWR) Internals Inspection and Evaluation Guidelines" (TAC No. ME0680)
Dear Sir or Madam:
By letter dated January 31, 2000 (Reference 1), Entergy Operations, Inc. (Entergy) submitted a License Renewal Application (LRA) for Arkansas Nuclear One, Unit 1 (ANO-1). In the LRA, Entergy made the following commitment related to reactor vessel internals aging management:
New Site Activity - Involves a new inspection program beginning after May 20, 2014, and continuing through year 60. Inspections may include volumetric examination of a sample of baffle bolts and visual examination of the reactor vessel internals. A report defining the inspection program will be provided to the NRC prior to May 20, 2014.
The purpose of this transmittal is to provide the ANO-1 Reactor Vessel Internals Aging Management Program Plan for review and approval. The program plan is attached.
1 CAN051403 Page 2 of 2 This plan identifies the internals components that must be included for aging management review and identifies the augmented inspection plan for the ANO-1 reactor vessel internals.
This plan implements the EPRI Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guidelines (MRP-227-A) (Reference 2). This program was developed so that the aging effects of the reactor vessel internal components are adequately managed and provide reasonable assurance that the internals components will continue to perform their intended function through the period of extended operation.
Reference 3 provides Revision 1 of the Final Safety Evaluation of MRP-227A. As part of that evaluation, a number of action items and conditions were specified. Documented in Section 5 of the attached program plan is how ANO-1 conforms to those action items and conditions.
ANO-1 enters the period of extended operation on May 20, 2014.
This letter contains several new regulatory commitments. These commitments are listed in.
If you have any questions or require additional information, please contact me.
Sincerely, SLP/rwc
Attachment:
- 1. PWR Internals Aging Management Program Plan for Arkansas Nuclear One, Unit 1
- 2. List of Commitments cc:
Mr. Marc L. Dapas Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Peter Bamford MS O-8B3 One White Flint North 11555 Rockville Pike Rockville, MD 20852