Category:Letter type:
MONTHYEAR0CAN102401, Response to Request for Additional Information - Arkansas Nuclear One – Units 1 and 2, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzle2024-10-16016 October 2024 Response to Request for Additional Information - Arkansas Nuclear One – Units 1 and 2, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles 2CAN102401, Cycle 31 Core Operating Limits Report (COLR)2024-10-14014 October 2024 Cycle 31 Core Operating Limits Report (COLR) 1CAN082401, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 1 Thirty-First Refueling Outage (1R312024-08-13013 August 2024 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 1 Thirty-First Refueling Outage (1R31 2CAN072401, Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02)2024-07-19019 July 2024 Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02) 0CAN072401, Annual 10 CFR 50.46 Report for Calendar Year 2023 Emergency Core Cooling System Evaluation Changes2024-07-0808 July 2024 Annual 10 CFR 50.46 Report for Calendar Year 2023 Emergency Core Cooling System Evaluation Changes 1CAN072401, Request for Review and Approval of Changes to the Safety Analysis Report and to a Confirmatory Order Clarifying an Alternate Means of Compliance for Pressurizer Heaters Emergency Power Supply2024-07-0202 July 2024 Request for Review and Approval of Changes to the Safety Analysis Report and to a Confirmatory Order Clarifying an Alternate Means of Compliance for Pressurizer Heaters Emergency Power Supply 0CAN062403, Groundwater Protection Initiative - Voluntary Special Report for Tritium Levels2024-06-25025 June 2024 Groundwater Protection Initiative - Voluntary Special Report for Tritium Levels 0CAN062402, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles2024-06-0606 June 2024 Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles 0CAN052401, – Units 1 and 2, Submittal of Annual Radiological Environmental Operating Report for 20232024-05-13013 May 2024 – Units 1 and 2, Submittal of Annual Radiological Environmental Operating Report for 2023 1CAN052401, Cycle 32 Core Operating Limits Report2024-05-0404 May 2024 Cycle 32 Core Operating Limits Report 2CAN042403, Response to the Request for Additional Information Regarding ANO-2 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended C2024-04-24024 April 2024 Response to the Request for Additional Information Regarding ANO-2 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended C 0CAN042402, Annual Occupational Radiation Exposure Report for 20232024-04-23023 April 2024 Annual Occupational Radiation Exposure Report for 2023 0CAN042401, Radioactive Effluent Release Report for the 2023 Calendar Year2024-04-15015 April 2024 Radioactive Effluent Release Report for the 2023 Calendar Year 2CAN042402, Special Report of Non-functional Main Steam Line Radiation Monitor2024-04-11011 April 2024 Special Report of Non-functional Main Steam Line Radiation Monitor 2CAN042401, Request to Revise Typographical Errors in Arkansas Nuclear One, Unit 2 Technical Specifications2024-04-0404 April 2024 Request to Revise Typographical Errors in Arkansas Nuclear One, Unit 2 Technical Specifications 2CAN012401, U.S. Additional Protocol2024-01-17017 January 2024 U.S. Additional Protocol 2CAN012403, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42024-01-11011 January 2024 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN012401, Registration of Cask Use2024-01-10010 January 2024 Registration of Cask Use 1CAN122301, Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037)2023-12-14014 December 2023 Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037) 2CAN112302, Submittal of Amendment 31 to Safety Analysis Report2023-11-16016 November 2023 Submittal of Amendment 31 to Safety Analysis Report 0CAN102303, Registration of Cask Use2023-10-24024 October 2023 Registration of Cask Use 0CAN102302, (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 32023-10-11011 October 2023 (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 3 0CAN102301, Evacuation Time Estimate (ETE) Study2023-10-0404 October 2023 Evacuation Time Estimate (ETE) Study 1CAN092301, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-09-21021 September 2023 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN092302, Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2023-09-14014 September 2023 Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 2CAN092301, Reply to a Notice of Violation2023-09-0808 September 2023 Reply to a Notice of Violation 0CAN092301, Emergency Plan Implementing Procedure Revision2023-09-0505 September 2023 Emergency Plan Implementing Procedure Revision 0CAN082301, Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 03412023-08-17017 August 2023 Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 0341 2CAN082301, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29)2023-08-10010 August 2023 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29) 0CAN072301, Registration of Cask Use2023-07-18018 July 2023 Registration of Cask Use 1CAN062304, Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2023-06-29029 June 2023 Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 0CAN062301, Status of Actions to Return to Compliance2023-06-26026 June 2023 Status of Actions to Return to Compliance 0CAN062302, Submittal of Revision 22 of the ANO Fire Hazards Analysis2023-06-20020 June 2023 Submittal of Revision 22 of the ANO Fire Hazards Analysis 1CAN062301, Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037)2023-06-0808 June 2023 Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037) 0CAN052303, Annual 10 CFR 50.46 Report for Calendar Year 20222023-05-24024 May 2023 Annual 10 CFR 50.46 Report for Calendar Year 2022 0CAN052302, Emergency Plan Rev. 482023-05-11011 May 2023 Emergency Plan Rev. 48 0CAN052301, Units 1 and 2 - Annual Radiological Environmental Operating Report for 20222023-05-0909 May 2023 Units 1 and 2 - Annual Radiological Environmental Operating Report for 2022 2CAN052301, Cycle 30 Core Operating Limits Report (COLR)2023-05-0303 May 2023 Cycle 30 Core Operating Limits Report (COLR) 0CAN042302, Annual Occupational Radiation Exposure Report for 20222023-04-27027 April 2023 Annual Occupational Radiation Exposure Report for 2022 0CAN042301, Radioactive Effluent Release Report for 20222023-04-14014 April 2023 Radioactive Effluent Release Report for 2022 2CAN042301, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-04-0505 April 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 2CAN032304, Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032303, Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032305, 03 Post Examination Analysis2023-03-23023 March 2023 03 Post Examination Analysis 1CAN032302, Inspection Summary Report for the Thirtieth Refueling Outage (1R30)2023-03-20020 March 2023 Inspection Summary Report for the Thirtieth Refueling Outage (1R30) 1CAN012301, Responses to Request for Additional Information for Request for Relief ANO1-ISI-0352023-01-30030 January 2023 Responses to Request for Additional Information for Request for Relief ANO1-ISI-035 2CAN012303, U.S. Additional Protocol2023-01-23023 January 2023 U.S. Additional Protocol 2CAN012302, Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-01-20020 January 2023 Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 2024-08-13
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23142A2022023-06-29029 June 2023 Issuance of Amendment Nos. 279 and 332 Emergency Plan Staffing Requirements 2CAN042301, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-04-0505 April 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN102202, Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2022-10-31031 October 2022 Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 0CAN082201, License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements2022-08-30030 August 2022 License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements ML21279A2312021-10-0606 October 2021 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements Using the Consolidated Line-Item Improvement 1CAN102101, SAR Amendment 30, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report2021-10-0606 October 2021 SAR Amendment 30, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report 1CAN092101, License Amendment Request Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2021-09-30030 September 2021 License Amendment Request Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations ML21266A1612021-09-23023 September 2021 Application to Revise Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated ML21182A1582021-07-0101 July 2021 Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections 1CAN052102, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2021-05-26026 May 2021 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors 2CAN052102, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2021-05-26026 May 2021 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors 1CAN022102, Supplement Related to License Amendment Request to Replace the Reactor Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate2021-02-22022 February 2021 Supplement Related to License Amendment Request to Replace the Reactor Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate 0CAN022102, Unit 2; License Amendment Request - One-Time Change to Support Proactive Upgrade of the Emergency - Cooling Pond Supply Piping2021-02-0808 February 2021 Unit 2; License Amendment Request - One-Time Change to Support Proactive Upgrade of the Emergency - Cooling Pond Supply Piping 2CAN112004, License Amendment Request - Application to Adopt a Safety Function Determination Program (SFDP)2020-11-17017 November 2020 License Amendment Request - Application to Adopt a Safety Function Determination Program (SFDP) 2CAN092003, License Amendment Request, Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2020-09-24024 September 2020 License Amendment Request, Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions 1CAN072001, Supplemental Information Related to License Amendment Request to Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate2020-07-21021 July 2020 Supplemental Information Related to License Amendment Request to Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate 1CAN022001, License Amendment Request: Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate2020-02-24024 February 2020 License Amendment Request: Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate 1CAN012002, License Amendment Request: Revise Loss of Voltage Relay Allowable Values2020-01-24024 January 2020 License Amendment Request: Revise Loss of Voltage Relay Allowable Values 2CAN121903, License Amendment Request, Revise Control Element Assembly Drop Time2019-12-18018 December 2019 License Amendment Request, Revise Control Element Assembly Drop Time 2CAN121901, License Amendment Request Technical Specification Deletions, Additions, and Relocations2019-12-16016 December 2019 License Amendment Request Technical Specification Deletions, Additions, and Relocations 1CAN101903, Supplement to License Amendment Request: Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO2019-10-23023 October 2019 Supplement to License Amendment Request: Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO 0CAN091901, Unit 2: License Amendment Request - Change in Implementation Date for Amendments 263 and 3142019-09-0505 September 2019 Unit 2: License Amendment Request - Change in Implementation Date for Amendments 263 and 314 2CAN081903, License Amendment Request Technical Specification (TS) Change Related to Revised Fuel Handling Accident Analysis and Adoption of TS Improvements Consistent with NUREG-14322019-08-29029 August 2019 License Amendment Request Technical Specification (TS) Change Related to Revised Fuel Handling Accident Analysis and Adoption of TS Improvements Consistent with NUREG-1432 1CAN051901, License Amendment Request Application to Revise Technical Specifications to Adopt TSTF 563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program.2019-05-29029 May 2019 License Amendment Request Application to Revise Technical Specifications to Adopt TSTF 563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program. 0CAN041904, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into the Licensing Basis2019-04-29029 April 2019 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into the Licensing Basis 1CAN031901, License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an Lco.2019-03-25025 March 2019 License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an Lco. CNRO-2019-00003, Application to Revise Technical Specifications to Adopt TSTF-529 11 Clarify Use and Application Rules, 11 Revision 42019-01-31031 January 2019 Application to Revise Technical Specifications to Adopt TSTF-529 11 Clarify Use and Application Rules, 11 Revision 4 1CAN121801, Application to Revise Technical Specifications to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues2018-12-19019 December 2018 Application to Revise Technical Specifications to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues 2CAN121801, License Amendment Request, Add Actions to Address Inoperability of the Containment Building Sump2018-12-19019 December 2018 License Amendment Request, Add Actions to Address Inoperability of the Containment Building Sump 2CAN051801, License Renewal Pressurizer Surge Line and Safety Injection Nozzle Inspection2018-05-24024 May 2018 License Renewal Pressurizer Surge Line and Safety Injection Nozzle Inspection ML18094A1552018-03-29029 March 2018 Enclosures 2 - 6: Proposed EAL Technical Basis Document, NEI 99-01. Rev. 6., Proposed EAL Matrix Chart/Review Table and Supporting Referenced Document Pages 0CAN031801, Unit 2 - License Amendment Request - Adoption of Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 62018-03-29029 March 2018 Unit 2 - License Amendment Request - Adoption of Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6 1CAN031801, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425)2018-03-12012 March 2018 Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425) 2CAN121702, License Amendment Request Post-Accident Instrumentation Technical Specification Revision2017-12-14014 December 2017 License Amendment Request Post-Accident Instrumentation Technical Specification Revision 2CAN111702, License Amendment Request - Updating the Reactor Coolant System Pressure-Temperature Limits2017-11-20020 November 2017 License Amendment Request - Updating the Reactor Coolant System Pressure-Temperature Limits 1CAN101701, License Amendment Request Revision to Technical Specification Bases Related to Emergency Feedwater Turbine-Driven Pump Steam Supply Valves2017-10-0202 October 2017 License Amendment Request Revision to Technical Specification Bases Related to Emergency Feedwater Turbine-Driven Pump Steam Supply Valves ML17268A2132017-09-21021 September 2017 ISFSI, River Bend Station Unit 1 & ISFSI, Waterford 3 Steam Electric Station & ISFSI, Grand Gulf Nuclear Station & ISFSI, Application for Order Approving Transfers of Licenses and Conforming License Amendments 1CAN081701, Application to Revise Technical Specifications to Adopt TSTF-427, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability.2017-08-14014 August 2017 Application to Revise Technical Specifications to Adopt TSTF-427, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability. 2CAN081701, Application to Revise Technical Specifications to Adopt TSTF-427, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability.2017-08-14014 August 2017 Application to Revise Technical Specifications to Adopt TSTF-427, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability. 2CAN071701, License Amendment Request, Application for Technical Specification Improvement to Provide Actions for Emergency Feedwater Pump Inoperability Consistent with NUREG-14322017-07-17017 July 2017 License Amendment Request, Application for Technical Specification Improvement to Provide Actions for Emergency Feedwater Pump Inoperability Consistent with NUREG-1432 1CAN071701, License Amendment Request, Application for Technical Specification Improvement to Revise Actions for Inoperable Using the Consolidated Line Item Improvement Process2017-07-17017 July 2017 License Amendment Request, Application for Technical Specification Improvement to Revise Actions for Inoperable Using the Consolidated Line Item Improvement Process 1CAN061701, Amendment 27 of the SAR, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report2017-06-0707 June 2017 Amendment 27 of the SAR, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report 1CAN041702, License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using the Consolidated Line.2017-04-24024 April 2017 License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using the Consolidated Line. 2CAN041702, License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection.2017-04-24024 April 2017 License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection. 2CAN101601, License Amendment Request to Revise the National Fire Protection Association (NFPA) Standard 805 Modifications2016-10-27027 October 2016 License Amendment Request to Revise the National Fire Protection Association (NFPA) Standard 805 Modifications 1CAN051602, Update to Tables S-1 and S-2 - Adoption of National Fire Protection Association Standard NFPA-8052016-05-19019 May 2016 Update to Tables S-1 and S-2 - Adoption of National Fire Protection Association Standard NFPA-805 2CAN031602, Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the Asme..2016-03-25025 March 2016 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the Asme.. 2023-07-27
[Table view] Category:Technical Specification
MONTHYEAR2CAN042401, Request to Revise Typographical Errors in Arkansas Nuclear One, Unit 2 Technical Specifications2024-04-0404 April 2024 Request to Revise Typographical Errors in Arkansas Nuclear One, Unit 2 Technical Specifications 2CAN112302, Submittal of Amendment 31 to Safety Analysis Report2023-11-16016 November 2023 Submittal of Amendment 31 to Safety Analysis Report 1CAN092301, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-09-21021 September 2023 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN102202, Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2022-10-31031 October 2022 Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 1CAN102201, Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2022-10-13013 October 2022 Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations ML21279A2312021-10-0606 October 2021 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements Using the Consolidated Line-Item Improvement 1CAN102101, SAR Amendment 30, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report2021-10-0606 October 2021 SAR Amendment 30, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report ML21266A1612021-09-23023 September 2021 Application to Revise Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated ML21182A1582021-07-0101 July 2021 Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections 1CAN012002, License Amendment Request: Revise Loss of Voltage Relay Allowable Values2020-01-24024 January 2020 License Amendment Request: Revise Loss of Voltage Relay Allowable Values 2CAN121901, License Amendment Request Technical Specification Deletions, Additions, and Relocations2019-12-16016 December 2019 License Amendment Request Technical Specification Deletions, Additions, and Relocations 1CAN061902, Supplemental Change Related to Revise Technical Specifications to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues2019-06-18018 June 2019 Supplemental Change Related to Revise Technical Specifications to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues 1CAN031901, License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an Lco.2019-03-25025 March 2019 License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an Lco. 1CAN111802, ANO Unit 1 SAR Amendment 28, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report2018-11-12012 November 2018 ANO Unit 1 SAR Amendment 28, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report 2CAN121705, Exigent License Amendment Request Allowance to Exclude Exercise of Control Element Assembly 4 with Respect to Surveillance Requirement 4.1.3.1.2 for the Remainder of Cycle 262017-12-28028 December 2017 Exigent License Amendment Request Allowance to Exclude Exercise of Control Element Assembly 4 with Respect to Surveillance Requirement 4.1.3.1.2 for the Remainder of Cycle 26 2CAN111702, License Amendment Request - Updating the Reactor Coolant System Pressure-Temperature Limits2017-11-20020 November 2017 License Amendment Request - Updating the Reactor Coolant System Pressure-Temperature Limits 1CAN031604, Arkansas, Unit 1 - Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the ASME Co2016-03-25025 March 2016 Arkansas, Unit 1 - Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the ASME Code 2CAN031602, Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the Asme..2016-03-25025 March 2016 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the Asme.. 2CAN121502, Application to Revise Technical Specifications to Adopt TSTF-426, Revise or Add Actions to Preclude Entry Into LCO 3.0.3 - RITSTF Initiatives 6b & 6c, Using the Consolidated Line Item Improvement Process2015-12-22022 December 2015 Application to Revise Technical Specifications to Adopt TSTF-426, Revise or Add Actions to Preclude Entry Into LCO 3.0.3 - RITSTF Initiatives 6b & 6c, Using the Consolidated Line Item Improvement Process 1CAN121403, License Amendment Request Supplemental ANO-1 Adoption of TSTF-431, Revision 3, Change in Technical Specifications End States (BAW-2441).2014-12-0505 December 2014 License Amendment Request Supplemental ANO-1 Adoption of TSTF-431, Revision 3, Change in Technical Specifications End States (BAW-2441). 2CAN101401, Arkansas, Unit 2 - License Amendment Request Supplemental Adoption of Technical Specification Task Force (TSTF)-422, Revision 2, Change in Technical Specifications End States (CE NPSD-1186)2014-10-22022 October 2014 Arkansas, Unit 2 - License Amendment Request Supplemental Adoption of Technical Specification Task Force (TSTF)-422, Revision 2, Change in Technical Specifications End States (CE NPSD-1186) 1CAN011406, Amendment 25 of the ANO Unit 1 Safety Analysis Report2014-01-29029 January 2014 Amendment 25 of the ANO Unit 1 Safety Analysis Report 1CAN121301, Clarification of Proposed Change to Technical Specification 2.1.1.1 Reactor Core Safety Limits2013-12-11011 December 2013 Clarification of Proposed Change to Technical Specification 2.1.1.1 Reactor Core Safety Limits 2CAN061302, License Amendment Request - Supplemental Technical Specification (TS) Change Related to Revised Fuel Assembly Drop Analysis and Adoption of TSTF-51, TSTF-272, TSTF-286, and TSTF-4712013-06-18018 June 2013 License Amendment Request - Supplemental Technical Specification (TS) Change Related to Revised Fuel Assembly Drop Analysis and Adoption of TSTF-51, TSTF-272, TSTF-286, and TSTF-471 1CAN031306, License Amendment Request, Adoption of Technical Specification Task Force (TSTF)-431, Revision 3 Change in Technical Specifications End States (BAW-2441)2013-03-26026 March 2013 License Amendment Request, Adoption of Technical Specification Task Force (TSTF)-431, Revision 3 Change in Technical Specifications End States (BAW-2441) 2CAN071201, License Amendment Request - Supplemental Technical Specification (TS) Change Related to Revised Fuel Assembly Drop Analysis and Adoption of TSTF-51, TSTF-272, TSTF-286, and TSTF-4712012-07-0909 July 2012 License Amendment Request - Supplemental Technical Specification (TS) Change Related to Revised Fuel Assembly Drop Analysis and Adoption of TSTF-51, TSTF-272, TSTF-286, and TSTF-471 2CAN041201, License Amendment Request, Technical Specification (TS) Change Related to Revised Fuel Assembly Drop Analysis and Adoption of TSTF-51, TSTF-272, TSTF-286, and TSTF-4712012-04-0404 April 2012 License Amendment Request, Technical Specification (TS) Change Related to Revised Fuel Assembly Drop Analysis and Adoption of TSTF-51, TSTF-272, TSTF-286, and TSTF-471 1CAN041102, License Amendment Request, Adoption of Technical Specification Task Force (TSTF)513, Revision 3, Revise PWR Operability Requirements and Actions for RCS Leakage Instrumentation.2011-04-29029 April 2011 License Amendment Request, Adoption of Technical Specification Task Force (TSTF)513, Revision 3, Revise PWR Operability Requirements and Actions for RCS Leakage Instrumentation. 1CAN081001, License Amendment Request, Technical Specification Change Associated with Main Feedwater Isolation Valves2010-08-24024 August 2010 License Amendment Request, Technical Specification Change Associated with Main Feedwater Isolation Valves 2CAN081009, Emergency License Amendment Request Extension of ANO-2 Emergency Diesel Generator Allowed Outage Time2010-08-19019 August 2010 Emergency License Amendment Request Extension of ANO-2 Emergency Diesel Generator Allowed Outage Time 1CAN081002, License Amendment Request, Changes to Technical Specification 3.9.3, Technical Change Traveler - TSTF-312, Rev. 12010-08-10010 August 2010 License Amendment Request, Changes to Technical Specification 3.9.3, Technical Change Traveler - TSTF-312, Rev. 1 2CAN061003, Arkansas Nuclear One, Unit 2 - License Amendment Request, Technical Specification Change to Extend the Type a Test Frequency to 15 Years2010-06-17017 June 2010 Arkansas Nuclear One, Unit 2 - License Amendment Request, Technical Specification Change to Extend the Type a Test Frequency to 15 Years ML1016803802010-06-17017 June 2010 License Amendment Request, Technical Specification Change to Extend the Type a Test Frequency to 15 Years 1CAN021004, Response to Request for Additional Information, Application for Technical Specification Improvement to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec.2010-02-28028 February 2010 Response to Request for Additional Information, Application for Technical Specification Improvement to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec. 2CAN060903, License Amendment Request, Technical Specification Changes to Relocate Pressurizer Heater Requirements to Technical Requirements Manual2009-06-18018 June 2009 License Amendment Request, Technical Specification Changes to Relocate Pressurizer Heater Requirements to Technical Requirements Manual 2CAN050902, License Amendment Request to Revise Technical Specification 6.6.5, Core Operating Limits Report2009-05-15015 May 2009 License Amendment Request to Revise Technical Specification 6.6.5, Core Operating Limits Report 2CAN050901, License Amendment Request to Revise the Departure from Nucleate Boiling Ratio (DNBR) Safety Limit2009-05-13013 May 2009 License Amendment Request to Revise the Departure from Nucleate Boiling Ratio (DNBR) Safety Limit ENOC-09-00009, Entergy Nuclear Operations, Inc. - License Amendment Request; Proposed Adoption of TSTF-511 Regarding Elimination of Technical Specification Work Hour Restrictions2009-04-27027 April 2009 Entergy Nuclear Operations, Inc. - License Amendment Request; Proposed Adoption of TSTF-511 Regarding Elimination of Technical Specification Work Hour Restrictions 2CAN030902, License Amendment Request, Technical Specification Change to Delete COLR References2009-03-10010 March 2009 License Amendment Request, Technical Specification Change to Delete COLR References 1CAN030901, License Amendment Request on Technical Specification Change to Delete Low Pressurizer Level Limit2009-03-10010 March 2009 License Amendment Request on Technical Specification Change to Delete Low Pressurizer Level Limit 2CAN120801, License Amendment Request Supplemental Regarding Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers and Relocate TS 3.7.8 to the TRM2008-12-11011 December 2008 License Amendment Request Supplemental Regarding Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers and Relocate TS 3.7.8 to the TRM 2CAN070801, Supplement to License Amendment Request Regarding Technical Specification Changes Associated with Adoption of TSTF-3592008-07-0808 July 2008 Supplement to License Amendment Request Regarding Technical Specification Changes Associated with Adoption of TSTF-359 2CAN030806, Supplemental to License Amendment Request, Technical Specification 3.1.1.4, Moderator Temperature Coefficient2008-03-27027 March 2008 Supplemental to License Amendment Request, Technical Specification 3.1.1.4, Moderator Temperature Coefficient 2CAN100701, License Amendment Request - Technical Specification Changes Regarding Mode Change Limitations and Associated Bases Using the Consolidated Line Item Improvement Process2007-10-22022 October 2007 License Amendment Request - Technical Specification Changes Regarding Mode Change Limitations and Associated Bases Using the Consolidated Line Item Improvement Process 1CAN100703, License Amendment Request - Technical Specification Changes and Analyses Relating to Use of Alternate Source Term2007-10-22022 October 2007 License Amendment Request - Technical Specification Changes and Analyses Relating to Use of Alternate Source Term 2CAN100703, Unit 2 License Amendment Request for Technical Specification Change Associated with Replacement of Containment Sump Buffer2007-10-0505 October 2007 Unit 2 License Amendment Request for Technical Specification Change Associated with Replacement of Containment Sump Buffer ML0726300862007-09-28028 September 2007 License and Technical Specification Pages - Amendment No. 273 Revisions to TS to Support Partial Re-Rack and Revised Loading Patterns in the Spent Fuel Pool 2024-04-04
[Table view] Category:Bases Change
MONTHYEAR2CAN112302, Submittal of Amendment 31 to Safety Analysis Report2023-11-16016 November 2023 Submittal of Amendment 31 to Safety Analysis Report ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN102201, Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2022-10-13013 October 2022 Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations 2CAN042201, Amendment 30 to the ANO Unit 2 Safety Analysis Report2022-04-27027 April 2022 Amendment 30 to the ANO Unit 2 Safety Analysis Report 1CAN102101, SAR Amendment 30, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report2021-10-0606 October 2021 SAR Amendment 30, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report ML21279A2312021-10-0606 October 2021 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements Using the Consolidated Line-Item Improvement 2CAN121901, License Amendment Request Technical Specification Deletions, Additions, and Relocations2019-12-16016 December 2019 License Amendment Request Technical Specification Deletions, Additions, and Relocations 1CAN061902, Supplemental Change Related to Revise Technical Specifications to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues2019-06-18018 June 2019 Supplemental Change Related to Revise Technical Specifications to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues 1CAN031901, License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an Lco.2019-03-25025 March 2019 License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an Lco. 1CAN111802, ANO Unit 1 SAR Amendment 28, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report2018-11-12012 November 2018 ANO Unit 1 SAR Amendment 28, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report 2CAN111702, License Amendment Request - Updating the Reactor Coolant System Pressure-Temperature Limits2017-11-20020 November 2017 License Amendment Request - Updating the Reactor Coolant System Pressure-Temperature Limits 1CAN031604, Arkansas, Unit 1 - Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the ASME Co2016-03-25025 March 2016 Arkansas, Unit 1 - Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the ASME Code 2CAN031602, Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the Asme..2016-03-25025 March 2016 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the Asme.. 2CAN121502, Application to Revise Technical Specifications to Adopt TSTF-426, Revise or Add Actions to Preclude Entry Into LCO 3.0.3 - RITSTF Initiatives 6b & 6c, Using the Consolidated Line Item Improvement Process2015-12-22022 December 2015 Application to Revise Technical Specifications to Adopt TSTF-426, Revise or Add Actions to Preclude Entry Into LCO 3.0.3 - RITSTF Initiatives 6b & 6c, Using the Consolidated Line Item Improvement Process 1CAN121403, License Amendment Request Supplemental ANO-1 Adoption of TSTF-431, Revision 3, Change in Technical Specifications End States (BAW-2441).2014-12-0505 December 2014 License Amendment Request Supplemental ANO-1 Adoption of TSTF-431, Revision 3, Change in Technical Specifications End States (BAW-2441). 1CAN011406, Amendment 25 of the ANO Unit 1 Safety Analysis Report2014-01-29029 January 2014 Amendment 25 of the ANO Unit 1 Safety Analysis Report 2CAN061302, License Amendment Request - Supplemental Technical Specification (TS) Change Related to Revised Fuel Assembly Drop Analysis and Adoption of TSTF-51, TSTF-272, TSTF-286, and TSTF-4712013-06-18018 June 2013 License Amendment Request - Supplemental Technical Specification (TS) Change Related to Revised Fuel Assembly Drop Analysis and Adoption of TSTF-51, TSTF-272, TSTF-286, and TSTF-471 1CAN031306, License Amendment Request, Adoption of Technical Specification Task Force (TSTF)-431, Revision 3 Change in Technical Specifications End States (BAW-2441)2013-03-26026 March 2013 License Amendment Request, Adoption of Technical Specification Task Force (TSTF)-431, Revision 3 Change in Technical Specifications End States (BAW-2441) 1CAN041102, License Amendment Request, Adoption of Technical Specification Task Force (TSTF)513, Revision 3, Revise PWR Operability Requirements and Actions for RCS Leakage Instrumentation.2011-04-29029 April 2011 License Amendment Request, Adoption of Technical Specification Task Force (TSTF)513, Revision 3, Revise PWR Operability Requirements and Actions for RCS Leakage Instrumentation. 1CAN081001, License Amendment Request, Technical Specification Change Associated with Main Feedwater Isolation Valves2010-08-24024 August 2010 License Amendment Request, Technical Specification Change Associated with Main Feedwater Isolation Valves 2CAN081009, Emergency License Amendment Request Extension of ANO-2 Emergency Diesel Generator Allowed Outage Time2010-08-19019 August 2010 Emergency License Amendment Request Extension of ANO-2 Emergency Diesel Generator Allowed Outage Time 1CAN081002, License Amendment Request, Changes to Technical Specification 3.9.3, Technical Change Traveler - TSTF-312, Rev. 12010-08-10010 August 2010 License Amendment Request, Changes to Technical Specification 3.9.3, Technical Change Traveler - TSTF-312, Rev. 1 1CAN021004, Response to Request for Additional Information, Application for Technical Specification Improvement to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec.2010-02-28028 February 2010 Response to Request for Additional Information, Application for Technical Specification Improvement to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec. 2CAN060903, License Amendment Request, Technical Specification Changes to Relocate Pressurizer Heater Requirements to Technical Requirements Manual2009-06-18018 June 2009 License Amendment Request, Technical Specification Changes to Relocate Pressurizer Heater Requirements to Technical Requirements Manual 1CAN030901, License Amendment Request on Technical Specification Change to Delete Low Pressurizer Level Limit2009-03-10010 March 2009 License Amendment Request on Technical Specification Change to Delete Low Pressurizer Level Limit 2CAN030902, License Amendment Request, Technical Specification Change to Delete COLR References2009-03-10010 March 2009 License Amendment Request, Technical Specification Change to Delete COLR References 2CAN120801, License Amendment Request Supplemental Regarding Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers and Relocate TS 3.7.8 to the TRM2008-12-11011 December 2008 License Amendment Request Supplemental Regarding Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers and Relocate TS 3.7.8 to the TRM 2CAN070801, Supplement to License Amendment Request Regarding Technical Specification Changes Associated with Adoption of TSTF-3592008-07-0808 July 2008 Supplement to License Amendment Request Regarding Technical Specification Changes Associated with Adoption of TSTF-359 1CAN100703, License Amendment Request - Technical Specification Changes and Analyses Relating to Use of Alternate Source Term2007-10-22022 October 2007 License Amendment Request - Technical Specification Changes and Analyses Relating to Use of Alternate Source Term ML0722901082007-08-0202 August 2007 Supplement to Amendment Request to Delete the Fuel Handling Area Ventilation System and Associated Filter Testing Program Requirements 2CAN030701, Arkansas One, Unit 2, License Amendment Request, Proposed Technical Change Regarding Containment Spray Nozzle Test Requirements2007-03-15015 March 2007 Arkansas One, Unit 2, License Amendment Request, Proposed Technical Change Regarding Containment Spray Nozzle Test Requirements ML0600504482006-01-0303 January 2006 Arkansas Nuclear One - Unit 1, License Amendment Request - Request for Emergency Technical Specification Change to Revise the Actuation Allowable Value for Emergency Feedwater Initiation and Control Function ML0619401702005-09-19019 September 2005 Arkansas Unit 2, Technical Specifications, Channell Functional Test 2CAN010505, Arkansas, Unit 2 - License Amendment Request Proposed Technical Specification Change to Relocate Containment Overcurrent Protection Devices from the ANO-2 Technical Specifications2005-01-31031 January 2005 Arkansas, Unit 2 - License Amendment Request Proposed Technical Specification Change to Relocate Containment Overcurrent Protection Devices from the ANO-2 Technical Specifications ML0318909122003-06-30030 June 2003 Arkansas, Unit 1 - License Amendment Request to Add New Control Room Emergency Ventilation System Surveillance Requirement 2CAN060303, Arkansas, Unit 2, License Amendment Request, Revision of Section 6.0, Administrative Controls2003-06-30030 June 2003 Arkansas, Unit 2, License Amendment Request, Revision of Section 6.0, Administrative Controls 2023-07-27
[Table view] Category:Technical Specifications
MONTHYEARML24198A0722024-08-21021 August 2024 Correction to Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting 0CAN042301, Radioactive Effluent Release Report for 20222023-04-14014 April 2023 Radioactive Effluent Release Report for 2022 ML22104A2222022-05-12012 May 2022 Issuance of Amendments Revise Technical Specifications to Adopt TSTF 554 ML21279A2312021-10-0606 October 2021 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements Using the Consolidated Line-Item Improvement ML21208A4492021-09-20020 September 2021 Issuance of Amendment No. 325 Revise Loss of Voltage Relay Allowable Values and Number of Degraded Voltage Channels ML21088A4332021-04-14014 April 2021 Issuance of Amendment No. 324 Adoption of Technical Specification Task Force Traveler, TSTF-569, Revision 2, Revise Response Time Testing Definition ML21027A4282021-03-23023 March 2021 Issuance of Amendment No. 272 Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent 1CAN022102, Supplement Related to License Amendment Request to Replace the Reactor Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate2021-02-22022 February 2021 Supplement Related to License Amendment Request to Replace the Reactor Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate ML20160A1472020-06-30030 June 2020 Issuance of Amendment No. 270 to Adopt TSTF 563, Revision 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML20135H1412020-06-30030 June 2020 Issuance of Amendment Nos. 269 and 321 Request to Incorporate the Tornado Missile Risk Evaluator Into the Licensing Basis ML19232A3792019-09-19019 September 2019 Correction to Issuance of Amendment No. 264 Adoption of Technical Specifications Task Force Traveler TSTF-425, Revision 3 ML19175A0422019-09-11011 September 2019 Arkansas Units 1 and 2; Grand Gulf, Unit 1; Indian Point 2 and 3; Palisades; River Bend, Unit 1; Waterford Unit 3 - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules ML17251A2112017-10-10010 October 2017 Issuance of Amendment No. 307 Revision of Steam Generator Technical Specifications to Reflect Adoption of Technical Specifications Task Force Traveler TSTF-510 (CAC MF9654; EPID L-2017-LLA-0222) ML16165A4232017-03-10010 March 2017 Issuance of Amendment No. 257 Adoption of Technical Specifications Task Force Traveler TSTF-545, Revision 3, ML16027A1092016-02-24024 February 2016 Issuance of Amendment Nos. 255 and 303 Cyber Security Plan Implementation Schedule (CAC Nos. MF6258 and MF6259) ML15096A3812015-04-29029 April 2015 Issuance of Amendment No. 302, Revise Technical Specification Surveillance Requirement 4.1.3.1.2 Note to Eliminate Movement of Control Element Assembly 18 for Remainder of Operating Cycle 24 ML15068A3192015-03-31031 March 2015 Issuance of Amendment No. 301, Request to Adopt Technical Specification Task Force (TSTF)-422, Revision 2, Change in Technical Specifications End States (CE NPSD-1186) ML15023A1472015-03-0303 March 2015 Issuance of Amendment No. 253, Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-431, Revision 3, Change in Technical Specifications End States (BAW-2441) ML14356A2272015-02-18018 February 2015 Issuance of Amendment No. 300, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants ML15014A0712015-02-0303 February 2015 Issuance of Amendment No. 252, Request to Revise Technical Specification 5.5.16, Reactor Building Leakage Rate Testing Program, to Extend Type a Test Frequency to 15 Years ML14350B2852015-01-22022 January 2015 Issuance of Amendment No. 299, Revise Technical Specification 6.5.16, Containment Leakage Rate Testing Program, for Requirements for Containment Building Emergency Escape Air Lock Doors ML14254A1332014-11-24024 November 2014 Issuance of Amendment No. 250, Adoption of Technical Specifications Task Force (TSTF)-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360 1CAN111401, Arkansas Nuclear One, Unit 1, License Amendment Request Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits2014-11-21021 November 2014 Arkansas Nuclear One, Unit 1, License Amendment Request Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits 1CAN111401, License Amendment Request Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits2014-11-21021 November 2014 License Amendment Request Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits 1CAN101407, Clarifications to Response to Request for Additional Information Associated with Technical Specification Change to Extend the Type a Test Frequency to 15 Years2014-10-28028 October 2014 Clarifications to Response to Request for Additional Information Associated with Technical Specification Change to Extend the Type a Test Frequency to 15 Years 1CAN031401, License Amendment Request - Revised Pages Extend the Type a Test Frequency to 15 Years2014-03-11011 March 2014 License Amendment Request - Revised Pages Extend the Type a Test Frequency to 15 Years 1CAN121302, License Amendment Request Technical Specification Change to Extend the Type a Test Frequency to 15 Years2013-12-20020 December 2013 License Amendment Request Technical Specification Change to Extend the Type a Test Frequency to 15 Years 1CAN081302, Response to Request for Additional Information, Adoption of Technical Specification Task Force (TSTF)-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360.2013-08-28028 August 2013 Response to Request for Additional Information, Adoption of Technical Specification Task Force (TSTF)-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360. 2CAN061302, License Amendment Request - Supplemental Technical Specification (TS) Change Related to Revised Fuel Assembly Drop Analysis and Adoption of TSTF-51, TSTF-272, TSTF-286, and TSTF-4712013-06-18018 June 2013 License Amendment Request - Supplemental Technical Specification (TS) Change Related to Revised Fuel Assembly Drop Analysis and Adoption of TSTF-51, TSTF-272, TSTF-286, and TSTF-471 1CAN061301, License Amendment Request, Revision to Technical Specification 2.1.1.1 Reactor Core Safety Limits2013-06-11011 June 2013 License Amendment Request, Revision to Technical Specification 2.1.1.1 Reactor Core Safety Limits 2CAN011301, License Amendment Request - Adoption of Technical Specification Task Force (TSTF)-500, Revision 2 DC Electrical Rewrite - Update to TSTF-3602013-01-28028 January 2013 License Amendment Request - Adoption of Technical Specification Task Force (TSTF)-500, Revision 2 DC Electrical Rewrite - Update to TSTF-360 1CAN011304, License Amendment Request - Adoption of Technical Specification Task Force (TSTF)-500, Revision 2 DC Electrical Rewrite - Update to TSTF-360.2013-01-28028 January 2013 License Amendment Request - Adoption of Technical Specification Task Force (TSTF)-500, Revision 2 DC Electrical Rewrite - Update to TSTF-360. CNRO-2012-00009, Entergy Responses to Request for Additional Information Regarding Changes to the Quality Assurance Program Manual & Associated Plant Technical Specifications Re Staff Qualifications2012-11-20020 November 2012 Entergy Responses to Request for Additional Information Regarding Changes to the Quality Assurance Program Manual & Associated Plant Technical Specifications Re Staff Qualifications 1CAN061201, License Amendment Request Technical Specification Change Associated with Main Feedwater Valves2012-06-19019 June 2012 License Amendment Request Technical Specification Change Associated with Main Feedwater Valves 1CAN081001, License Amendment Request, Technical Specification Change Associated with Main Feedwater Isolation Valves2010-08-24024 August 2010 License Amendment Request, Technical Specification Change Associated with Main Feedwater Isolation Valves 2CAN051001, Response to Request for Additional Information Associated with Core Operating Limits Report References2010-05-17017 May 2010 Response to Request for Additional Information Associated with Core Operating Limits Report References 1CAN021004, Response to Request for Additional Information, Application for Technical Specification Improvement to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec.2010-02-28028 February 2010 Response to Request for Additional Information, Application for Technical Specification Improvement to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec. ML0931305282009-12-23023 December 2009 License Amendment No. 241, Modified Technical Specification 3.4.9, Pressurizer, to Delete Low Pressurizer Level Limit ML0930601322009-12-23023 December 2009 License Amendment No. 240, Revised Administrative Changes to Technical Specification 5.5.8, Inservice Testing Program, to Adopt TSTF-479-A and TSTF-497-A 1CAN080901, Changes to Reflect Revision to 10 CFR 50.55a Technical Change Travelers - TSTF-479-A and TSTF-497-A2009-08-0505 August 2009 Changes to Reflect Revision to 10 CFR 50.55a Technical Change Travelers - TSTF-479-A and TSTF-497-A 2CAN030901, License Amendment Request, Technical Specification Change to Modify the Mode of Applicability for Emergency Feedwater Actuation Signal2009-03-0202 March 2009 License Amendment Request, Technical Specification Change to Modify the Mode of Applicability for Emergency Feedwater Actuation Signal 1CAN020901, License Amendment Request, Technical Specification Change to Adopt Low Pressure Air Lock Seal Test2009-02-16016 February 2009 License Amendment Request, Technical Specification Change to Adopt Low Pressure Air Lock Seal Test ML0814000372008-09-0808 September 2008 Technical Specifications for Amendment No. 282 Technical Specification Task Force TSTF-490, Rev 0, Deletion of E Bar Definition and Revision to RCS Specific Activity. ML0812203132008-08-28028 August 2008 Tech Spec Pages for Amendment No. 281 Technical Specification Task Force Change TSTF-359, Increased Flexibility in Mode Restraints. ML0823801472008-08-21021 August 2008 License Amendment Request, Technical Specification Change to Extend Integrated Leak Rate Test Interval One-Time ML0814004492008-07-23023 July 2008 Tech Spec Pages for Amendment No. 280 Reactor Coolant System Relocation to TRM (Tac MD8313) 1CAN070804, License Amendment Request Regarding Technical Specification Changes Associated with Adoption of TSTF-3592008-07-21021 July 2008 License Amendment Request Regarding Technical Specification Changes Associated with Adoption of TSTF-359 2CAN070805, License Amendment Request Regarding Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers and Relocate TS 3.7.8 to the TRM2008-07-21021 July 2008 License Amendment Request Regarding Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers and Relocate TS 3.7.8 to the TRM 2024-08-21
[Table view] |
Text
Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802 Tel 479-858-3110 Kevin T. Walsh Vice President, Operations Arkansas Nuclear One 1CAN021004 February 28, 2010 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
Response to Request for Additional Information Application for Technical Specification Improvement to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec Arkansas Nuclear One, Unit 1 Docket No. 50-313 License No. DPR-51
REFERENCES:
- 1. Entergy letter to the NRC, dated March 13, 2008, Application for Technical Specification Improvement to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec (1CAN030802)
Dear Sir or Madam:
In Reference 1, Entergy Operations, Inc. (Entergy) requested an amendment to Arkansas Nuclear One, Unit 1 (ANO-1) Technical Specifications (TS) to adopt TS Task Force traveler 490 (TSTF-490).
Subsequent to the submittal, the NRC determined that additional information was required to complete their review and provided a request for additional information (RAI) in email dated December 22, 2009. Attachment 1 of this letter contains the RAI and associated responses. As a result of responding to the RAI Question 1, the attachment to the original letter (Reference 1) is being replaced in its entirety in order to effectively remove a reference that was not necessary. The replacement attachment is included in Attachment 2 of this letter. Entergy requests the NRC remove the attachment contained in Reference 1 above and replace it with the content of Attachment 2 of this letter. Finally, in support of the response to RAI Question 3, a new markup of the affected TS page, a revised or clean TS page, and markup of affected TS Bases pages (for information only) is included in Attachments 3, 4, and 5 of this letter, respectively.
Changes resulting from Entergys response to this RAI has no impact on the original No Significant Hazards Consideration (NSHC) determination performed by Entergy.
This letter contains no new commitments.
1CAN021004 Page 2 of 2 If you have any questions or require additional information, please contact David Bice at 479-858-5338.
I declare under penalty of perjury that the foregoing is true and correct. Executed on February 28, 2010.
Sincerely, Original signed by K. T. Walsh KTW/dbb Attachments: 1. Response to Requests for Additional Information (RAI)
- 2. Revised Attachment to Entergy Letter 1CAN030802
- 3. Revised Technical Specification Page (mark-up)
- 4. Revised Technical Specification Page (clean)
- 5. Revised Technical Specification Bases Pages Mark-up (for information only) cc: Mr. Elmo E. Collins Regional Administrator U. S. Nuclear Regulatory Commission Region IV 612 E. Lamar Blvd., Suite 400 Arlington, TX 76011-4125 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 NRC Senior Resident Inspector Arkansas Nuclear One P. O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Kaly Kalyanam MS O-8 B1 One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mr. Bernard R. Bevill Arkansas Department of Health Radiation Control Section 4815 West Markham Street Slot #30 Little Rock, AR 72205
Attachment 1 to 1CAN021004 Response to Requests for Additional Information (RAI) to 1CAN021004 Page 1 of 5 RESPONSE TO REQUESTS FOR ADDITIONAL INFORMATION (RAI)
By letter dated March 13, 2008, (Agencywide Documents Access & Management System (ADAMS) ML080850906), Entergy Operations, Inc. (the licensee), submitted a license amendment request regarding proposed changes to the technical specifications (TSs) for Arkansas Nuclear One, Unit 1 (ANO-1). The proposed amendment would replace the current ANO-1 TS limit on Reactor Coolant System (RCS) gross specific activity with a new limit on RCS noble gas specific activity. The noble gas specific activity limit would be based on a new dose equivalent Xenon-133 (DEX) definition that would replace the current E Bar average disintegration energy definition. In addition, the current dose equivalent Iodine-131 definition would be revised. The amendment request is consistent with TS Task Force Traveler TSTF-490-A.
The US Nuclear Regulatory Commission (NRC) staff has determined that the following additional information is needed to complete its review of the subject license amendment request for ANO-1. This request was discussed with David Bice of your staff on December 16, 2009, and it was agreed that a response would be provided within 30 days of receipt of this email.
Entergy Response With regard to the NRC 30-day response request, the NRC later stated in email to David Bice dated January 8, 2010, that the standard 30 days would not be applied to this response in light of NRC concerns with TSTF-490 surveillance notes that limit RCS sampling requirements to Mode 1 only. Therefore, additional time was required to resolve this concern, with the NRC accepting a draft resolution via email to David Bice dated February 17, 2010. The resolution is discussed in response to RAI Question 3 of this attachment.
- 1. The application dated March 13, 2008, refers to an NRC staff Safety Evaluation (SE),
described as Reference 1, dated September 27, 2006 (ADAMS Accession No. ML062700612). This document is not publicly available. The NRC acknowledges that reference to ADAMS Accession No. ML062700612 was mistakenly contained in the notice of availability of model application for this TS improvement that was published in the Federal Register (72 FR 12217). However, since the submittal states that the methodology described in this NRC staffs SE was applied to develop the proposed TS changes, it is not clear how this was accomplished. In order to make the application complete, the NRC staff requests that Entergy supplement the application to provide a corrected reference for the methodology used to develop this proposed TS change as well as a correct reference to the public version of the NRC's SE for this Technical Specification Task Force Traveler (TSTF-490).
Entergy Response Entergy Operations, Inc. (Entergy) concurs that the subject reference should be deleted.
As stated in Attachment 1 of the original submittal, Sections 1.0, 3.0, 4.0, 5.0, 6.0, and 7.0, Entergy verified the ANO-1 relationship to applicable regulatory requirements and guidance provided in the NRC Notice of Availability (NOA) published on March 15, 2007 (72FR12217). Therefore, deletion of any and all reference to the September 27, 2006 NRC SE has no impact on Entergys original assessment that the adoption of TSTF-490 is appropriate for ANO-1. Attachment 2 of this letter contains a new attachment to the to 1CAN021004 Page 2 of 5 original ANO-1 submittal, dated March 13, 2008, with any reference to the aforementioned September 27, 2006 NRC SE deleted (one occurrence in Section 1.0 and once by reference in Sections 4.0 and 8.0 of the original letter attachment). Entergy requests the NRC replace the attachment to the original letter in its entirety with the pages contained in Attachment 2 of this letter.
- 2. Consistent with the SE for TSTF-490, please confirm that the site-specific limits for both dose equivalent iodine (DEI) and DEX, and the dose conversion factors (DCFs) used for the determination of DEI and DEX surveillances, are consistent with the current design bases radiological dose consequence analyses (for example, steam generator tube rupture and main steam line break). For DEX, the licensee states a reactor coolant DEX specific activity of 2200 µCi/gm. Please provide the information necessary (dose conversion factors and RCS radioisotopic concentrations) for the NRC to verify the proposed value in the limiting condition for operation (LCO).
Entergy Response As stated in Section 4.0 of the original submittal, the adoption of TSTF-490 was tied to the adoption of an Alternate Source Term (AST) for ANO-1. Entergys original submittal referenced the AST submittal, dated October 22, 2007 (1CAN100703), for information relating to the development of the DEI and DEX values because the DEI and DEX values selected were based on the adoption of the AST. However, given the size of the AST submittal, Entergy understands the difficulty in ascertaining only the DEI and DEX related information from the AST submittal. Therefore, the relevant information is included below.
Note that the NRC has approved the AST for ANO-1 in letter dated October 21, 2009 (TAC No. MD7178). The DCFs are associated with the respective NRC Federal Guidance Report (FGR) effective dose equivalent (EDE) and committed dose equivalent (CEDE) used to translate activities into equivalent Xe-133 and I-131 activities.
Primary Coolant Source Term, DCF, and DEX Activity ISOTOPE CURIES FGR-12 Xe-133 EQUIVALENT Kr-85 4.80E+02 1.19E-16 3.66E+01 Kr-85m 1.31E+03 7.48E-15 6.28E+03 Kr-87 2.09E+03 4.12E-14 5.52E+04 Kr-88 2.93E+03 1.02E-13 1.92E+05 Xe-131m 3.78E+02 3.89E-16 9.43E+01 Xe-133 3.02E+04 1.56E-15 3.02E+04 Xe-133m 7.64E+02 1.37E-15 6.71E+02 Xe-135 1.30E+04 1.19E-14 9.92E+04 Xe-135m 1.18E+03 2.04E-14 1.54E+04 Xe-138 3.46E+03 5.77E-14 1.28E+05 TOTAL 5.2663E+05 to 1CAN021004 Page 3 of 5 Primary Coolant Source Term, DCF, and DEI Activity ISOTOPE CURIES FGR-11 I-131 EQUIVALENT I-131 7.33E+01 8.89E-09 7.33E+01 I-132 1.00E+03 1.03E-10 1.16E+01 I-133 6.91E+02 1.58E-09 1.23E+02 I-134 1.48E+03 3.55E-11 5.91E+00 I-135 1.22E+03 3.32E-10 4.56E+01 TOTAL 2.5917E+02 The ANO-1 RCS mass is ~5.2395E+05 lbm at maximum pressurizer level. This mass translates into 2.3766E+08 grams (a rounded RCS mass of 2.38E+08 grams was provided in letter 1CAN030803). Thus, the dose equivalent Xe-133 (DEX) concentration in the RCS is (5.2663E+05 Ci / 2.3766E+08 g) x 1E+06 µCi/Ci = ~2216 µCi/g. The dose equivalent I-131 (DEI) concentration in the RCS is (2.5917E+02 Ci / 2.3766E+08 g) x 1E+06 µCi/Ci = 1.09 µCi/g. A DEX value of 2200 µCi/g and a DEI value of 1.0 µCi/g have been conservatively chosen for the proposed TS change.
Significant detail is provided in the aforementioned Entergy letter (1CAN100703) and amplified in Entergy letter dated March 13, 2008 (1CAN030803), both associated with adoption of the now NRC approved AST for ANO-1.
- 3. In the subject license amendment request, the licensee proposed TS changes to revise LCO 3.4.12, "RCS Specific Activity," APPLICABILITY requirements to specify that the LCO is applicable in MODES 1, 2, 3, and 4. In accordance with this proposal, the licensee also proposed to add the NOTE that states, "Only required to be performed in MODE 1," to the surveillance requirements (SR) of the TS, thus removing the applicability of the SR to other MODES.
The proposed change revises the conditions for sampling, and may exclude sampling during the plant conditions where LCO 3.4.12 may be exceeded. After transient conditions (i.e. reactor trip, plant depressurization, shutdown or startup) that end in MODES 2, 3, or 4, the SR is not required to be performed. Isotopic spiking and fuel failures are more likely during transient conditions than during steady state plant operations.
Because LCO 3.4.12 could potentially be exceeded after plant transient or power changes, please justify why sampling is no longer needed in the plant MODES that are proposed to be eliminated and justify how the LCO 3.4.12 remains consistent with the design bases analysis from which the LCO limits are derived (i.e. main steamline break, steam generator tube rupture, etc.). Furthermore, please justify why there is an apparent disparity between the modes of applicability (MODES 1, 2, 3, and 4) and the limited mode (MODE 1) under which the surveillance is required.
to 1CAN021004 Page 4 of 5 Entergy Response For ANO-1, the total gas value and a separate radiogas sample (collected via an inverted funnel) are required to determine DEX. The radiogas sample may be obtained from system piping other than the high pressure RCS Purification (or Letdown) system; however, the results from alternate sample points are meaningless without the ability to correlate the amount of radioactivity in the radiogas sample to total radioactivity within the RCS. The total gas value allows for this correlation. The total gas value is important because it allows radioactivity in the radiogas sample to be proportioned to radioactivity within the total RCS volume.
The ANO-1 reactor coolant sample system is not designed to accommodate a total gas sample in lower Modes of operation. This is due to the total gas sample bomb being hard-piped to the RCS Purification system. In lower modes of operation, the Purification system is either not in-service or there is insufficient pressure to obtain necessary sample flow from this sample point. At 500 °F RCS temperature (current TS applicability for sampling) and assuming a minimum of 30 °F margin-to-saturation is maintained (equivalent to 530 °F),
RCS pressure can be as low as 900 psia. At the entry condition to Mode 4 (300 °F), RCS pressure, while maintaining a 30 °F margin to saturation, can be as low as 70 psia. Given the heat exchangers, isolation valves, flow control valves, and long sample piping run that RCS fluid must pass through to reach the sample bomb, sufficient flow cannot be maintained to continue sampling as RCS cool down proceeds. This is due to significant pressure breakdown as sample flow travels through these various components and paths.
The existing LCO applicability requirements are limited to Modes 1, 2 and Mode 3 with RCS average temperature 500 °F. The ANO-1 Steam Generator Tube Rupture (SGTR) and Main Steam Line Break (MSLB) analyses are based on power operating conditions, which are bounding for lower modes of operation. The analyses assume RCS activity at TS limits. The TSs recognize that operation above TS RCS activity limits is a condition beyond that assumed in the plant safety analysis and, therefore, severely limits the time the licensee has to restore activity to within limits before a plant shutdown is required. Once RCS activity limits are exceeded, further sample results that continue to indicate elevated activity will have no bearing on the TS requirement to perform a plant shutdown or actions the licensee is required to take. In addition, the next follow-up sample would not be required for 7 days, well after the unit would reach Mode 5 conditions. This is not to imply more frequent sampling will not be performed, since it is the interest of the licensee to track RCS activity limits in order to assess the source and more quickly determine corrective actions to repair. Because the current analyses are bounding for lower modes of operation and because further sampling will not change the TS requirements to restore activity to within limits or perform a plant shutdown, the safety significance of not obtaining a DEX below an RCS temperature of 500 °F is negligible.
The DEX sample is also not safety significant in these lower modes from the aspect of a SGTR or MSLB that might initiate while operating in lower mode. The MSLB is only of concern due to the stress it may place on the Steam Generator (SG) tubes or if a SG tube is already exhibiting significant leakage. However, the SG tubes are designed against the thermodynamic and other stresses placed upon them at full power operations. TSs require that SG tubes be verified acceptable to remain in service following each inspection until the next inspection outage. This evaluation must assume worse case conditions. If a SG tube to 1CAN021004 Page 5 of 5 cannot be shown to remain below TS allowed flaw limits prior to reaching the next inspection outage, it must be removed from service prior to plant startup. Because the SG tube integrity program controls are based on full power operation, it is extremely unlikely that the stresses placed on SG tubes during low pressure, temperature, and flow operations would result in a SG tube leak in these lower modes of operation. The RCS activity TS is intended to limit the amount of activity that could be released to the public should a SGTR occur. Since a SGTR is not expected during lower modes of operation, the significance of performing samples to determine DEX activity in the RCS below 500 °F is negligible.
In addition to the above, Emergency Operating Procedures require Operators to rapidly reduce RCS pressure in any SG tube leak event that requires a unit shutdown (this is administratively required for SG tube leakage well below TS limits). The goal of the procedures is to reduce RCS pressure to be equal to or slightly less than SG pressure so that RCS fluid will cease to enter the secondary side of the SG through the leaking tube.
These actions aid in preventing or limiting any release to the environment, regardless of RCS activity levels.
Other than a SG tube leak, RCS fluid is contained within the reactor building except as processed through the aforementioned Purification system or sample piping. The Purification system is removed from service during cool down of the RCS when pressure is no longer sufficient to maintain adequate flow. While in service, any leakage from the Purification system or sample system is collected in tanks or sumps contained within the Auxiliary Building. In addition, building air is filtered through ventilation systems, which include a charcoal filter, prior to release to the atmosphere. Therefore, sufficient design is provided to minimize any possibility of RCS fluid from inadvertently reaching the environment due to leakage from the Purification or sample system.
Note also that the source of a high RCS activity must be eliminated or otherwise resolved before unit restart. This includes replacement of fuel rods if the source was due to a pinhole leak in fuel cladding.
Based on the above, Entergy proposes to modify the SR 3.4.12.1 Note associated with DEX from Only required to be performed in Mode 1 to Only required to be performed in Modes 1, 2, and Mode 3 with RCS cold leg temperature 500 °F. This is consistent with the current TS applicability and the current licensing basis for ANO. However, to provide continued assessment of RCS activity conditions during plant shutdown and startup, the SR 3.4.12.2 Note associated with DEI will be deleted in its entirety. Therefore, DEI samples will no longer be limited to only Mode 1 operation.
The above changes have no adverse impact to nuclear or public safety since the adoption of TSTF-490 will remain conservative to existing requirements (neither DEI or DEX is currently required to be sampled when RCS temperature is below 500 °F. The changes affect TS Page 3.4.12-2 (marked-up and revised page) and TS Bases Pages 3.4.12-6 and 3.4.12-7 (submitted for information only). A new markup of the affected TS page, a revised or clean TS page, and markup of affected TS Bases pages (for information only) is included in Attachments 3, 4, and 5 of this letter, respectively.
Attachment 2 to 1CAN021004 Revised Attachment to Entergy Letter 1CAN030802 to 1CAN030802 Page 1 of 4
1.0 DESCRIPTION
This letter is a request to amend Operating License DPR-51 for Arkansas Nuclear One, Unit 1 (ANO-1).
The proposed changes would replace the current limits on primary coolant gross specific activity with limits on primary coolant noble gas activity. The noble gas activity would be based on DOSE EQUIVALENT XE-133 and would take into account only the noble gas activity in the primary coolant. Technical Specification Task Force (TSTF) change traveler TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec was announced for availability in the Federal Register on March 15, 2007 (Reference 2) as part of the consolidated line item improvement process (CLIIP).
2.0 PROPOSED CHANGE
Consistent with NRC-approved TSTF-490, Revision 0, the proposed TS changes:
- Revise the definition of DOSE EQUIVALENT I-131.
- Delete the definition of -AVERAGE DISINTEGRATION ENERGY.
- Add a new TS definition for DOSE EQUIVALENT XE-133.
- Revise LCO 3.4.12, RCS Specific Activity to delete references to gross specific activity and add limits for DOSE EQUIVALENT I-131 and DOSE EQUIVALENT XE-133. (Note that ANO-1 TSs do not contain a DOSE EQUIVALENT I-131 versus percent power figure noted for deletion in TSTF 490)
- Revise LCO 3.4.12 Applicability to specify the LCO is applicable in MODES 1, 2, 3, and 4.
- Modify ACTIONS Table as follows:
A. Condition A is modified to replace specific activity with DOSE EQUIVALENT I-131 and define an upper limit for DOSE EQUIVALENT I-131 that is applicable at all power levels.
B. ACTIONS are reordered, moving Condition B to Condition C to be consistent with the Writers Guide for the improved TSs of NUREG 1430.
C. A new Condition B is added to provide a Condition and Required Action for DOSE EQUIVALENT XE-133 with a Completion Time of 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. A Note allowing the applicability of LCO 3.0.4.c is added, consistent with the Note to Required Action A.1 described above.
D. Condition C (was Condition B) is modified based on the changes to Conditions A and B and to reflect the change in the LCO Applicability.
- Revise SR 3.4.12.1 to verify the limit for DOSE EQUIVALENT XE-133. A Note is added to allow entry into MODES 2, 3, and 4 prior to performance of the SR.
to 1CAN030802 Page 2 of 4 provides a markup of the affected TSs delineated above. Attachment 3 provides the final (clean) TS pages associated with these changes. includes a markup of the impacted TS Bases pages for information only. The TS Bases will be revised in accordance with the TS Bases Control Program (TS 5.5.14) during implementation of TSTF-490 once approved by the NRC. Also note that the TS Bases markup captures the information necessary to support the ANO-1 Alternate Source Term (AST) submittal discussed below. Therefore, the wording deviates from that proposed in TSTF-490, but is consistent with the Licensing Basis assuming approval of AST for ANO-1.
Note that TSTF-490 was written and approved considering the most current version of the Improved Technical Specifications (ITS) with approved TSTFs at the time. As described above, this included reference to Limiting Condition for Operation (LCO) 3.0.4.c, which was incorporated in the ITS under TSTF-359, Mode Change Limitations. Entergy has submitted a proposal to adopt TSTF-359, which is currently under review by the NRC (Reference 3).
Therefore, the above changes associated with LCO 3.0.4 are dependent on the NRC approval of Entergys TSTF-359 adoption proposal.
In addition to the discussion of TSTF-359 above, Entergy has also submitted an application to adopt use of Alternate Source Term (AST) for ANO-1 (Reference 4). This application is currently under NRC review and affects the pages associated with TS 3.4.12 above. In support of both TSTF-490 and AST adoption, the DOSE EQUIVALENT I-131 Definition is modified to refer to the committed effective dose equivalent (CEDE), which is consistent with AST.
Therefore, the markup and final versions of TS 3.4.12 included in Attachments 2 and 3, and the TS 3.4.12 Bases markup included in Attachment 4 are shown as if the ANO-1 TSTF-359 and the AST applications have been approved (minus the addition of a new amendment number in the associated page footer). Entergy will submit new markup and final TS pages upon NRC request should either the TSTF-359 or AST application be revised or should the approval of either of these applications be significantly delayed. If the aforementioned applications are approved as anticipated, Entergy will submit new final TS pages that include the new amendment numbers upon request from the NRC.
3.0 BACKGROUND
The background for this application is as stated in the model safety evaluation (SE) in the NRCs Notice of Availability published on March 15, 2007 (72FR12217), the NRC Notice for Comment published on November 20, 2006 (71FR67170), and TSTF-490, Revision 0.
4.0 TECHNICAL ANALYSIS
In the model SE, the NRC included statements which would require the licensee to identify specific information in support of adopting TSTF-490. The following provides ANO-1 specific information in this regard.
- 1. Section 3.1.1 of the model SE includes a list of acceptable dose conversion factors (DCF) for use in the determination of dose equivalent iodine (DEI) in relation to dose consequence analyses. The ANO-1 analyses employ Table 2.1 of EPA Federal Guidance Report No. 11, 1988, Limiting Values of Radionuclide Intake and Air Concentration and Dose conversion Factors for Inhalation, Submersion, and Ingestion.
to 1CAN030802 Page 3 of 4
- 2. In the first paragraph of Section 3.1.2 of the model SE, a bracketed list of isotopes is provided that designates the noble gases that may be used in the determination of dose equivalent xenon (DEX). All isotopes depicted within these brackets are currently considered in the ANO-1 calculation of DEX. This is captured in the proposed ANO-1 definition of DEX to be included in TS Section 1.1.
- 3. Section 3.1.2 of the model SE also provides two possible determination methods for DEX.
ANO-1 uses the effective dose conversion factor for air submersion listed in Table III.1 of EPA Federal Guidance Report No. 12, 1993, External Exposure to Radionuclides in Air, Water, and Soil. This is also depicted in the proposed definition of DEX in TS Section 1.1.
- 4. Section 3.1.3 states that it is incumbent on the licensee to ensure that the site specific limits for both DEI and DEX are consistent with the current steam generator tube rupture (SGTR) and main steam line break (MSLB) radiological consequence analyses. The ANO-1 analyses value for DEI is 1.0 µCi/gm as depicted in the proposed TS markup and also provided to the NRC in the aforementioned AST submittal (Reference 4). The ANO-1 analyses value for DEX is 2200 µCi/gm, considering the adoption and use of AST discussed previously. This is also depicted in the attached TS markups.
As noted in the Section 3.0 above, the DOSE EQUIVALENT I-131 Definition depicted in TSTF-490 is modified to refer to the committed effective dose equivalent (CEDE), which is consistent with AST. This change will remove any conflict between the adoption of TSTF-490 and the adoption of AST for ANO-1. Entergy does not consider this a significant deviation from the TSTF-490 adoption under CLIIP.
Entergy Operations, Inc. (Entergy) has reviewed References 1 and 2, and the model SE published on November 20, 2006 (71FR67170) as part of the CLIIP Notice for Comment.
Entergy has applied the methodology in these references to develop the proposed TS changes. Entergy has also concluded that the justifications presented in TSTF-490, Revision 0 and the model SE prepared by the NRC staff are applicable to ANO-1 and justify this amendment for the incorporation of the changes to the ANO-1 TS.
5.0 REGULATORY ANALYSIS
A description of this proposed change and its relationship to applicable regulatory requirements and guidance was provided in the NRC Notice of Availability published on March 15, 2007 (72FR12217), the NRC Notice for Comment published on November 20, 2006 (71FR67170), and TSTF-490, Revision 0.
6.0 NO SIGNIFICANT HAZARDS CONSIDERATION Entergy Operations, Inc. (Entergy) has reviewed the proposed no significant hazards consideration determination published in the Federal Register on March 15, 2007 (72FR12217) as part of the CLIIP. Entergy has concluded that the proposed determination presented in the notice is applicable to Arkansas Nuclear One, Unit 1 (ANO-1) and the determination is hereby incorporated by reference to satisfy the requirements of 10 CFR 50.91(a).
to 1CAN030802 Page 4 of 4 7.0 ENVIRONMENTAL EVALUATION Entergy Operations, Inc. (Entergy) has reviewed the environmental consideration included in the model SE published in the Federal Register on March 15, 2007 (72FR12217) as part of the CLIIP. Entergy has concluded that the staffs findings presented therein are applicable to Arkansas Nuclear One, Unit 1 (ANO-1) and the determination is hereby incorporated by reference for this application.
8.0 REFERENCES
- 1. Federal Notice for Comment published on November 20, 2006 (71FR67170)
- 2. Federal Notice of Availability published on March 15, 2007 (72FR12217)
- 3. Entergy letter to NRC dated October 22, 2007, Technical Specification Changes Regarding Mode Change Limitations and Associated Bases Using the Consolidated Line Item Improvement Process (TSTF-359), Arkansas Nuclear One, Unit 1 (1CAN100701)
(TAC No. MD7179)
- 4. Entergy letter to NRC dated October 22, 2007, Technical Specification Changes and Analyses Relating to Use of Alternate Source Term, Arkansas Nuclear One, Unit 1 (1CAN100703) (TAC No. MD7177)
Attachment 3 to 1CAN021004 Revised Technical Specification Page (mark-up)
RCS Specific Activity 3.4.12 CB. Required Action and CB.1 Be in MODE 3 with Tavg 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion < 500°F.
Time of Condition A or B not met. AND OR C.2 Be in MODE 5 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> DOSE EQUIVALENT I-131 > 60 µCi/gm.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.12.1 ----------------------------NOTE----------------------------------
Only required to be performed in MODE 1 and 2, MODE 3 with RCS average temperature 500 °F.
Verify reactor coolant DOSE EQUIVALENT 7 days XE-133gross specific activity 220072/E _ µCi/gm.
SR 3.4.12.2 ----------------------------NOTE----------------------------------
Only required to be performed in MODE 1.
Verify reactor coolant DOSE EQUIVALENT I-131 14 days specific activity 1.0 µCi/gm.
SR 3.4.12.3 ----------------------------NOTE----------------------------------
Not required to be performed until 31 days after a minimum of 2 EFPD and 20 days of MODE 1 operation have elapsed since the reactor was last subcritical for 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />.
Determine E. 184 days ANO-1 3.4.12-2 Amendment No. 215,
Attachment 4 to 1CAN021004 Revised Technical Specification Page (clean)
RCS Specific Activity 3.4.12 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.12.1 ----------------------------NOTE----------------------------------
Only required to be performed in MODE 1 and 2, MODE 3 with RCS average temperature 500 °F.
Verify reactor coolant DOSE EQUIVALENT XE-133 7 days specific activity 2200 µCi/gm.
SR 3.4.12.2 Verify reactor coolant DOSE EQUIVALENT I-131 14 days specific activity 1.0 µCi/gm.
ANO-1 3.4.12-2 Amendment No. 215,
Attachment 5 to 1CAN021004 Revised Technical Specification Bases Pages Mark-up (for information only)
RCS Specific Activity B 3.4.12 If the Required Action and associated Completion Time of Condition A or B is not met, or if the DOSE EQUIVALENT I-131 is > 60.0 µCi/gm, the reactor must be brought to MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The allowed Completion Times are reasonable, based on operating experience, to reach the required plant conditions from full power conditions in an orderly manner and without challenging plant systems.If the Required Action and associated Completion Time are not met, the reactor must be brought to MODE 3 with RCS average temperature
< 500°F within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. Placing the unit in MODE 3 and RCS average temperature <
500°F lowers the saturation pressure of the reactor coolant below the setpoints of the main steam safety valves, and prevents venting the SG to the environment in an SGTR event. The Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is required to reach MODE 3 from full power conditions in an orderly manner and without challenging unit systems.
SURVEILLANCE REQUIREMENTS SR 3.4.12.1 SR 3.4.12.1 requires performing a gamma isotopic analysis as a measure of the noble gas specific activity of the reactor coolant at least once every 7 days. This measurement is the sum of the degassed gamma activities and the gaseous gamma activities in the sample taken. This Surveillance provides an indication of any increase in the noble gas specific activity.SR 3.4.12.1 requires performing a gamma isotopic analysis as a measure of the gross specific activity of the reactor coolant at least once per 7 days. The gross specific activity analysis consists of the quantitative measurement of the total activity of the primary coolant in units of microcuries per gram (µCi/gm). The total primary coolant activity is the sum of the degassed beta-gamma activity and the total of all identified gaseous activities 15 minutes after the primary system is sampled and any identified beta emitters (i.e.,
tritium, SR89, SR90, etc.). This Surveillance provides an indication of any increase in gross specific activity.
Trending the results of this Surveillance allows proper remedial action to be taken before reaching the LCO limit under normal operating conditions. The 7 day Frequency considers the low probability of a gross fuel failure during this time.Trending the results of this Surveillance allows proper remedial action to be taken before reaching the LCO limit under normal operating conditions. The Surveillance is applicable in MODES 1 and 2, and in MODE 3 with RCS average temperature at least 500°F. The 7 day Frequency is based on the low probability of a gross fuel failure during that time period.
Due to the inherent difficulty in detecting Kr-85 in a reactor coolant sample due to masking from radioisotopes with similar decay energies, such as F-18 and I-134, it is acceptable to include the minimum detectable activity for Kr-85 in the SR 3.4.16.1 calculation. If a specific noble gas nuclide listed in the definition of DOSE EQUIVALENT XE-133 is not detected, it should be assumed to be present at the minimum detectable activity.
ANO-1 B 3.4.12-6 Amendment No. 215
RCS Specific Activity B 3.4.12 SURVEILLANCE REQUIREMENTS (continued)
SR 3.4.12.2 This Surveillance is performed to ensure iodine specific activity remains within the LCO limit during normal operation and following fast power changes when iodine spiking is more apt to occur. The 14 day Frequency is adequate to trend changes in the iodine activity level, considering noble gas activity is monitored every 7 days.This Surveillance is performed in MODE 1 only to ensure the iodine remains within limit during normal operation and following fast power changes when fuel failure is more apt to occur. The 14 day Frequency is adequate to trend changes in the iodine activity level considering gross specific activity is monitored every 7 days.
SR 3.4.12.3 SR 3.4.12.3
_ requires radiochemical analysis for E determination every 184 days.
The E determination directly relates to the LCO and is required to verify plant operation within
_ the total specific activity LCO limit. The Frequency of 184 days recognizes E does not change rapidly.
The radiochemical analysis consists of the quantitative measurement of the activity for each radionuclide which is identified in the primary coolant 15 minutes after the primary system is_sampled. The activities for the individual isotopes are used in the determination of E. The gamma energy per disintegration for those radioisotopes determined to be present shall be as given in "Table of Isotopes" (1967) (Ref. 4) and beta energy per disintegration shall be as given in USNRDL-TR-802 (Part II) (Ref. 5) or other references using the equivalent values for the radioisotopes. Iodine isotopic activities are weighted to give DOSE EQUIVALENT I-131 activity.
This SR is modified by a NOTE that requires the determination be performed within 31 days after a minimum of 2 EFPD and 20 days of MODE 1 operation have elapsed since the reactor was last subcritical for at least 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. _This ensures the radioactive materials are at equilibrium so the analysis for E is representative and not skewed by a crud burst or other similar abnormal event.
REFERENCES
- 1. 10 CFR 50.67100.11.
- 2. ANO-1 Operating License Amendment 238, (1CNA1057509012), dated October 21May 9, 20091975.
- 3. 10 CFR 50.36.
- 4. "Table of Isotopes" (1967).
- 5. USNRDL-TR-802 (Part II).
ANO-1 B 3.4.12-7 Amendment No. 215