| 05000445/FIN-2018001-01 | 2018Q1 | | Failure to Follow Commercial Grade Dedication Process |
| 05000445/FIN-2018001-02 | 2018Q1 | | Failure to Incorporate Design Information Into System Test Procedures |
| 05000445/FIN-2018001-03 | 2018Q1 | | Failure to Provide an Adequate Procedure |
| 05000445/FIN-2018001-04 | 2018Q1 | | Inadequate Maintenance Procedure for Feedwater Valves |
| 05000445/FIN-2018001-05 | 2018Q1 | | Failure to Correct a Significant Condition Adverse to Quality |
| 05000445/FIN-2018002-01 | 2018Q2 | H.11 | Failure to Identify and Correct a Condition Adverse to Quality |
| 05000445/FIN-2018002-02 | 2018Q2 | H.7 | Unacceptable Preconditioning of Main Steam Isolation Valves |
| 05000445/FIN-2018002-03 | 2018Q2 | | Failure to Incorporate Design Information Into System Test Procedures |
| 05000445/FIN-2018010-01 | 2018Q3 | | Failure to Establish Test Program to Verify Residual Heat Removal Suction Valve Capability |
| 05000445/FIN-2018010-02 | 2018Q3 | | Failure to Provide Procedural Guidance for the Failure of a Component Cooling Water Surge Tank Makeup Valve |
| 05000446/FIN-2018011-01 | 2018Q3 | | Failure to Maintain a Quality Record Complete and Accurate in All Material Respects |
| 05000446/FIN-2018011-02 | 2018Q3 | H.12 | Failure to Follow a Quality Procedure Associated with the Reactor Makeup and Chemical Control System |
| 05000445/FIN-2018003-01 | 2018Q3 | | Failure to Maintain the Ability to Withstand a Station Blackout |
| 05000445/FIN-2018003-02 | 2018Q3 | | Failure to Establish Adequate Procedural Guidance for Processing Technical Changes Performed by A Vendor on Installed Plant Equipment |