05000443/FIN-2008003-01
From kanterella
Jump to navigation
Jump to search
Finding | |
|---|---|
| Title | Failure to follow tagging procedure caused inadvertent drain of 200 gallons from RCS |
| Description | A self-revealing non-cited violation of Technical Specification 6.7.1.a was identified for the failure to implement written procedures governing safety-related activities. Specifically, on April 20, 2008, FPL Energy Seabrook (FPLE) failed to implement tagging and configuration control procedures, resulting in the loss of configuration control during shutdown operations when flow was established through a partially disassembled charging system valve. This resulted in a 200 gallon leak of reactor cavity water onto the floor of the Primary Auxiliary Building (PAB). The letdown flow path was established while work was in progress on valve CS-V-299. A clearance boundary was modified with the incorrect assumption that CS-V-299 was intact. This finding was more than minor because it was associated with the configuration control attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of plant events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the loss of configuration control in the charging system unintentionally drained 200 gallons from the reactor cavity, which affected the shutdown critical safety function of maintaining adequate reactor inventory, and caused an uncontrolled leak of radioactively contaminated water to a work area. The finding was determined to be of very low safety significance (Green) using the SDP Appendix G assessment, since the finding did not result in a loss of control of shutdown operations and adequate mitigation capabilities remained available. FPLE entered this issue into the corrective action program as Condition Report 08-06270. The finding has a cross-cutting aspect in the area of human performance, work control, since FPL Energy did not plan and coordinate work activities consistent with nuclear safety (H.3(b)). Specifically, FPLE revised a clearance tagging boundary without verifying the status of affected work activities in accordance with site procedures. (Section 1R20 |
| Site: | Seabrook |
|---|---|
| Report | IR 05000443/2008003 Section 1R20 |
| Date counted | Jun 30, 2008 (2008Q2) |
| Type: | NCV: Green |
| cornerstone | Initiating Events |
| Identified by: | Self-revealing |
| Inspection Procedure: | IP 71111.2 |
| Inspectors (proximate) | T Moslak D Silk L Scholl R Moore G Johnson T Burns A Ziedonis W Raymond A Burritt J Johnson |
| CCA | H.5, Work Management |
| INPO aspect | WP.1 |
| ' | |
Finding - Seabrook - IR 05000443/2008003 | |||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Seabrook) @ 2008Q2
Self-Identified List (Seabrook)
| |||||||||||||||||||||||||||