05000387/FIN-2011007-01
From kanterella
Jump to navigation
Jump to search
Finding | |
|---|---|
| Title | Failure to Provide Redundant Fire Water Pumps |
| Description | The team identified non-cited violations of Susquehanna Unit 1 Operating License Condition 2.C.(6) and Unit 2 Operating License Condition 2.C.(3) for the failure to implement all provisions of the approved Fire Protection Program. Specifically, PPL had not adequately implemented a fire water supply system with two redundant 100% capacity fire water pumps and three sources of supply water. PPL\'s hydraulic analysis determined that after 20 minutes of single pump operation, two fire water pumps would need to operate to supply the design rated flow for several sprinkler systems required to be operable by the Susquehanna Steam Electric Station (SSES) Technical Requirements Manual. Subsequently, seven sprinkler systems were determined to be degraded because design flow rates could not be achieved and maintained by a single pump. PPL performed an operability evaluation that determined the affected sprinkler systems were capable of performing their intended functions at lower flow rates and for a shorter duration than originally specified by plant design. In addition, the Unit 2 cooling tower basin was determined to be inoperable as a sole source of supply water for the fire water system. An Operations Directive was issued to not align the fire water system to the Unit 2 cooling tower. The team determined the failure to verify the adequacy of design to satisfy licensing basis requirements was a performance deficiency. This issue was more than minor because it was similar to NRC Inspection Manual Chapter (IMC) 0612, Appendix E, Examples of Minor Issues, Example 3.k, which states that an analysis to verify the adequacy of design contained incorrect assumptions. The example concludes that the issue is more than minor if the error resulted in a condition where there was a reasonable doubt on the operability of the component. For this issue, a knowledgeable engineer could not determine the adequacy of design based on a review of the existing hydraulic analysis and associated design details without performing additional complex analysis and preliminary calculations. The team performed a Phase 1 Significance Determination Process screening, in accordance with NRC IMC 0609, Appendix F, Fire Protection Significance Determination Process. This finding affected the fixed fire protection systems category, and was screened to very low safety significance because the affected sprinkler systems were determined to have a low degradation rating. This finding did not have a cross-cutting aspect because it was determined to be a legacy issue and was not considered to be indicative of current licensee performance. |
| Site: | Susquehanna |
|---|---|
| Report | IR 05000387/2011007 Section 1R05 |
| Date counted | Jun 30, 2011 (2011Q2) |
| Type: | NCV: Green |
| cornerstone | Mitigating Systems |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71111.05 |
| Inspectors (proximate) | W Schmidt K Young J Rogge J Richmond L Scholl |
| INPO aspect | |
| ' | |
Finding - Susquehanna - IR 05000387/2011007 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Susquehanna) @ 2011Q2
Self-Identified List (Susquehanna)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||