05000382/LER-2002-003

From kanterella
Jump to navigation Jump to search
LER-2002-003, Inoperable Auxiliary Component Cooling Water Pump due to Lack of Lubrication
Waterford Steam Electric Station, Unit 3
Event date: 02-15-2002
Report date: 04-01-2002
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
3822002003R00 - NRC Website

REPORTABLE OCCURRENCE

On February 15, 2002, it was determined that the Auxiliary Component Cooling Water Pump had been inoperable for a period of approximately 7 days. The required Technical Specification actions were not entered, as this condition was unknown to plant personnel. Accordingly, this condition is being reported pursuant to 10CFR 50.73(a)(2)(i)(B) as operation or condition prohibited by Technical Specifications.

INITIAL CONDITIONS

Upon discovery of this event, Waterford 3 was operating in mode 1 at 100% reactor power. There were no major systems, structures or components that were inoperable at the time of discovery that contributed to the condition.

SYSTEM DESCRIPTION

The Auxiliary Component Cooling Water (ACCW) [BS] and the Component Cooling Water (CCW) [CC] systems work together to supply sufficient cooling to safety and non-safety related reactor auxiliaries. This cooling is also maintained to mitigate the consequences of a design basis accident. The ACCW pumps provide the driving head for the ACCW system. The ACCW System removes heat from the CCW System via the CCW Heat Exchanges during normal operation, normal shutdown, and accident conditions. The heat is transferred to the Wet Cooling Towers (WCT) for dispersal to the atmosphere. The ACCW System is required to operate whenever the heat rejection capacity of the CCW System is exceeded by accident conditions, or whenever ambient conditions prevent the CCW System from rejecting its required heat load by way of the Dry Cooling Towers. If not required, the ACCW system is placed in standby with the ACCW Pumps secured.

EVENT DESCRIPTION

On December 23, 2001, ACCW pump B was started for chemical mixing of the WCT basin. Prior to the pump start, lubricant levels were confirmed to be satisfactory. On December 30, 2001, ACCW pump B was again started for chemical mixing of the WCT basin. Again, prior to the pump start, lubricant levels were confirmed to be satisfactory. Subsequent to this start, the pump's outboard bearing temperature increased to 270°F over a five-minute period. (Normal outboard bearing temperatures are near 110°F). The pump was declared inoperable and then disassembled, where it was determined the outboard bearing had been damaged (i.e. wiped).

Following the December 30, 2001 pump failure, a failure analysis was performed which included a review of the data from the December 23, 2001 run. The review revealed that eight minutes following this pump start, the outboard bearing temperature increased to 179°F and then returned to its normal temperature of 110°F. The pump's lube oil reservoir temperature remained constant for approximately nine minutes following the pump start, increased to 125°F and then return to its normal temperature of 110°F.

ROOT CAUSE

A root cause determination was completed to investigate this event. It was concluded that the lubricant inlet port was partially blocked by foreign material subsequent to the pump start on December 23, 2002. The foreign material prevented oil from reaching the bearing for several minutes. During this time, the bearing was starved for oil and the shaft scored the soft babbit material of the bearing. The outboard pump bearing thermocouple temperature then increased to approximately 60°F above normal operating temperature. It was surmised that foreign material was then dislodged from the inlet port. Consequently, oil began flowing pass the outboard bearing and draining to the pump reservoir. Reservoir temperature increased rapidly to 125°F. Pump flow rate increased which resulting in reduced load on the outboard bearing. This reduction in load allowed the pump's shaft to move clockwise, away from the damage area on the bearing. The shaft movement allowed an oil wedge to be formed in the bearing. The outboard bearing and reservoir temperature then returned to normal.

The root cause determination attributed the root cause of this event to be the failure to exclude foreign material from the lubricant during maintenance or oil addition.

CORRECTIVE ACTIONS

The bearing oil was drained from ACCW Pump B, all pump accessible areas were cleaned and the outboard bearing was replaced.

Additional corrective actions to preclude recurrence (i.e. preventing intrusion of foreign material into the pump oil) have been entered, and are being tracked in the plant's corrective action program. (Reference Condition Report CR-WF3-2001-1399)

SAFETY SIGNIFICANCE

The inoperable condition of the Auxiliary Component Cooling Water Pump B rendered one train of ACCW inoperable for approximately 7 days. During this period Train A of ACCW was available to perform necessary functions of the ACCW system.

The risk impact of this condition was quantified. The evaluation assumes the condition (inoperable ACCW pump B) existed for a one week period. The increase in Core Damage Probability was determined to be not risk significant (8.2E-7).

Therefore, the condition identified in this LER has minimal safety significance. This event is not considered a Safety System Functional Failure.

SIMILAR EVENTS

be inoperable beyond the Technical Specification allowed outage time.

ADDITIONAL INFORMATION

Energy Industry Identification System (EIIS) codes are identified in the text within brackets [ ].